Safe Work Method Statement Transmission Field Protection Services
|
|
- Leona Megan Bradley
- 5 years ago
- Views:
Transcription
1 Purpose Permits Authorisations Training Equipment Electrical Access Permit (EAP) or Sanction to Test (STT) Electrical worker s licence, Network Authority Card (NAC), Recipient in charge (RIC), Tester in charge (TIC) Work safely at heights, Perform pole top rescue ladder, harness, pole strap, pole top rescue kit Working at heights adders ifting equipment, EWP Scaffolding Stairs/platforms Working at height Working above others Multiple work requiring EWPs Working with electricity Static electricity/induction Substations/switch rooms Underground cables Contact with electrical equipment Electrical cables High voltage equipment Overhead cables Non-compliant earths, e.g. tagged/tested Radiation Infra-red Microwaves Ultraviolet light, i.e. sun X-ray aser Mechanical Abrasive blasting/grinding Auto-start equipment Conveyors Equipment failure Hand and power tool Impact and crushing areas Pinch/cutting points Residual/stored energy Uncontrolled movement Unguarded moving parts Welding or cutting Crimping/connecting Pressure Competitive pressures Compressed gases/air Fluid High pressure steam Hydraulic Water Human factors Rushing Complacency Fatigue Unclear work direction Stress/anxiety/frustration ack of knowledge Poor communications Negative attitudes Using mobile plant Traffic/pedestrian interaction/collision Uneven terrain Unlicensed/untrained operators Vehicle instability Vehicle access Manual handling (ergonomic) Awkward/unbalanced load High/low reach High force/heavy loads ighting Over exertion/fatigue Poor design/layout/surface Repetitive movements Environment Air contamination Soil contamination Storm water contamination Waste, i.e. effluent/hazardous Solid waste Workplace Asbestos Confined space/void space Falling objects General access Housekeeping Illumination/lighting Noise, i.e. exposure/nuisance Poor ventilation Protrusions Restricted visibility Restricted work area Slip and trip hazards Unauthorised personnel Unlabelled controls Vibration Wet/slippery Wind/storm activity Fog/mist/smoke Working in isolation Dust/particulates Chemical Chemicals/reagents Fumes/vapour/mist (e.g. SF 6 ) Flammable gases Handling flammable materials Hazardous chemical exposure Solid chemical Splashes/burns Spills to ground or work area Thermal Cold ambient temperature Heat ambient temperature Hot materials/fluids Hot surfaces UV exposure Rev 0, June 2015 DM# of 6
2 Plan and prepare Pre-plan Determine staff requirements Unfit for work Fatigue Staff skilled, trained, competent and authorised Not trained or authorised for tasks being performed H Confirm staff are fit for work Comply with fatigue, drug and alcohol policies H Ensure staff are trained/have appropriate competencies and authorisations Confirm staff have valid NAC and permit accreditation Arrange for permit/isolations Working on/near HV and V apparatus H Communicate with Field Protection Services (FPS) for EAP or STT Communicate with NCD or Network Control Transmission (NCT) to arrange for an Ope Agreement (OA), if required Arrange worksite traffic management Uncontrolled public roads and worksite E Engage accredited traffic management company Develop site specific traffic management plan Gain local authority approval for complex traffic management plans, where required Weather conditions at workplace Adverse weather H Check with NCT and Bureau of Meteorology for weather conditions PPE requirements and inspection Expired/damaged PPE Inappropriate/incorrect PPE Pre-start check vehicles Un-roadworthy vehicle Inadequately secured tools and equipment Fall from height Implement traffic management Accredited traffic management company Control unauthorised access to the workplace Unauthorised access to worksite Unprotected worksite Control vehicle movement around the workplace Vehicle and equipment movement and impact Vehicle collision M Confirm staff have required safety clothing and equipment Ensure that gloves, hats, tools and rescue equipment are within test period and Western Power approved H Inspect/check vehicle for roadworthiness Check and secure tools and equipment Maintain three points of contact when climbing onto vehicle H Confirm that an accredited traffic management company has been engaged Traffic management company used to control worksite access at all times E Traffic management plan implemented specific to the road conditions Traffic management company used to control vehicle movement around the worksite risk 2 of 6 DM# Rev 0, June 2015
3 Safe Work Method Statement Transmission Field Protection Services Control pedestrian movement around the workplace Isolation and permits Communicate with NCT or NCD for an OA if required Impact with vehicle Uncontrolled pedestrians Failure to obtain correct permit for plant that is required to be accessed Plant or electrical apparatus operated by another OA Plant or electrical apparatus becomes live Equipment isolated and earthed prior to access Contact with live apparatus Induced voltages Insufficient or incorrect earthing EAP or STT permit issued to RIC/TIC, all staff briefed on permit conditions and all staff sign on to permit Workplace setup Conduct a Workplace Risk Assessment Plan (WRAP) Failure to understand permit boundaries and work area Flagging/ropes wrong position or inadequate for the site Induced voltages E Traffic management company used to control pedestrian movement around the worksite E OA issued for plant/electrical apparatus Maintain contact with NCT or NCD and confirm OA conditions with Issuing Officer E Ensure the RIC/TIC and all staff understand and are aware of the location of the isolation points and earths Understand the boundaries of the working area Ensure staff are aware of the risk from induced voltages and to use working earths as required (record on/off the EAP) Workers confirm earthing is adequate and positioned correctly to mitigate the added hazard of induced voltages H RIC/TIC and all staff to confirm that all isolations points are correct Use up-to-date maps and drawings, if required Ensure the RIC/TIC and all staff understand the permit conditions and are aware of the boundaries of the working area Ensure that all staff have signed on to the permit RIC/TIC to confirm the secondary isolations that have been performed, and initiates additional, if required RIC to oversee the application of all working earths and record on/off the EAP Site specific hazards at the workplace H Inspect the workplace for conditions and hazards, discuss and write on WRAP Ensure control measures have been implemented to control all hazards identified Continually review potential hazards and controls risk Rev 0, April 2015 DM# of 6
4 Establish emergency procedures Personnel unsure of action to take in an emergency M Communicate emergency procedure to team Establish muster point Confirm correct location/apparatus Incorrect location, live apparatus H Check permit conditions and pole numbers Communicate with RIC/TIC and FPS to confirm correct poles to be worked on Confirm correct location, apparatus, service order details Ensure portable programmed or working earths can be seen each side of the worksite Establish safe access route to apparatus No clear access/egress Slip and trip Setup and check plant, tools and equipment Poor site setup/unsafe positioning of vehicles and equipment Damaged or faulty plant, tools and equipment Manual handling injury Sharp edges and pinch points Vehicle movement, impact Multiple parties on site miscommunication Working at height - adders Confirm correct apparatus as per limitations of the permit Check ladder condition adder failure Damaged ladder Inspect electrical apparatus (poles, wires, hardware), include adjacent poles Failure to understand the conditions of the permit and the work boundaries Damaged or rotten poles Pole, conductor and/or asset failure Unsupported poles Altering loads on poles M Establish safe access route and walk carefully when setting up site Communicate with land owner/consumer to determine safe entry requirements, if required M Conduct site discussion, to confirm the position of equipment and vehicles, taking into account any new site hazards Inspect/check plant, tools and equipment to be used Use of correct gloves and PPE Site coordinator assigned orange site coordinator armband worn by assigned person all parties report to them upon arrival and when leaving site H Permit signed onto and understood by all staff. imitations of the permit and work area discussed with the RIC H Check ladder is within test period Check and inspect ladder for damage prior to use Select and use correct ladder for the task H Visually inspect all poles, hardware and conductors, include adjacent poles Visually inspect existing pole supports Support poles using approved supports where required prior to altering the load risk 4 of 6 DM# Rev 0, June 2015
5 Safe Work Method Statement Transmission Field Protection Services Use ladder to climb pole to access the pilot cable Check and set up pole top rescue kit, if required Fall from height Unstable ladder Working at height on a pole Fall from height Falling objects Not able to perform pole top rescue in an emergency H Inspect and wear fall arrest harness and pole strap Foot ladder while ascending or descending when ladder is not secured Secure ladder to the pole Always maintain three points of contact M Appoint a trained rescuer Inspect and setup pole top rescue kit H Attach pole strap Establish drop zone below work area risk Rev 0, April 2015 DM# of 6
6 Document control Author Document owner Stakeholders During document update, consult with the following Distribution list If updated, supply the new version of the document to the following Name Work Practice Development team, Field Protection Services Work Practice Development Work Practice Development Field Protection Services Network Total Workforce References Corporate Risk Assessment Criteria Safety ife Savers Workplace Risk Assessment Plan (WRAP) Electrical System Safety Rules (ESSR) Work Practice Manual (WPM) Transmission Substation Work Practice Manual (TXM) Risk matrix and s For details on assessing risks, see Workplace Risk Assessment Plan, 4. Assess the risks 6 of 6 DM# Rev 0, June 2015
Safe Work Method Statement Transmission Field Protection Services
Safe Work Method Statement Transmission Field Protection Services Purpose Permits Authorisations Training Equipment Fault finding on live V changeover/distribution boards N/A Electrical worker s licence,
More informationWestern Power Safe Work Method Statement Task details
Western Power Safe Work Method Statement Task details Description Install and Maintain V Overhead Equipment and Associated ardware (de-energised) DM 10716988 Approved by Manager, Work Practices Review
More informationWestern Power Safe Work Method Statement Task details
Western Power Safe Work ethod Statement Task details Description High Voltage Testing D 10697056 Approved by Work Practices anager Review team SWS Development Approval date ay 2013 Qualifications/icences
More informationWestern Power Safe Work Method Statement Task details
Western Power Safe Work ethod Statement Task details Description Transmission Tower Work D 10696821 Approved by Work Practices anager Review team SWS Development Approval date October 2015 Qualifications
More informationWestern Power Safe Work Method Statement Task details
Western Power Safe Work ethod Statement Task details Description Substation aintenance D 10721527 Approved by anager, Work Practices Review team SWS Development Approval date October 2015 Qualifications/icences
More informationWestern Power Safe Work Method Statement Task details
Western Power Safe Work ethod Statement Task details Description Transmission conductor stringing D 10696968 Approved by Work Practices anager Review team SWS Development Approval date October 2015 Qualifications/icences
More informationWestern Power Safe Work Method Statement Task details
Western Power Safe Work ethod Statement Task details Description Cable Pitch Removal D 10715491 Approved by anager, Work Practices Review team SWS Development Approval date October 2015 Qualifications/icences
More informationWestern Power Safe Work Procedures Task details
Western Power Safe Work Procedures Task details Description ive ine Safe Work Procedures for use with the SWS, ive ine Work (D# 10696821) D 10708984 Approved by Work Practices anager Review team SWS Development
More informationWestern Power Safe Work Method Statement Task details
Western Power Safe Work ethod Statement Task details Description igh Voltage (V) etering Installation Commissioning D 10643700 Approved by Work Practices Development anager Review team SWS Development
More informationWestern Power Safe Work Method Statement Task details
Western Power Safe Work ethod Statement Task details Description Replace overhead service at SWER transformer connected via V tap or bridge D 10720885 Approved by anager, Work Practices Review team SWS
More informationTemporary load-bearing support for structural alterations or repairs
CRITICAL NOTE This document only becomes a Safe Work Method Statement where the High Risk Construction Work section of this document is completed Company: ABN: Contact Person: Ph: Project/Site: Principal
More informationJob Safety & Environment Analysis
Job Safety & Environment Analysis To be used when the risk is greater than LOW and / or Defined Hazardous Work and there is no standard procedure for the task. All sections of this JSEA form must be completed.
More informationContractor Hazard Identification and Control Guide
Exposure to Asbestos Containing Materials (ACM) Accidental disturbance or removal of ACM. Asbestos Containing Materials are to be removed outside school hours. No DET employees, students or visitors are
More informationSAFETY MANAGEMENT SYSTEM
Equipment Location: Hazard Entanglement Hired From All Master Hire Stores Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving
More informationRISK ASSESSMENT. Bobcat Excavator. Models , (Series D & G) For. Version 1.2
PO Box 50, Hornsby, NSW 2077 Phone: 1800 643 853 Web: www.bobcat.com.au RISK ASSESSMENT For Bobcat Excavator Models 322 341, (Series D & G) CONTENTS Applicability Standards referenced in the preparation
More informationTitle: Plant and Equipment Risk Management Form Issue Date: Review Date: Page Number: 1 of 11
Issue Date: Review Date: Page Number: 1 of 11 1. Hazard Management Details General Plant/Equipment Item: WOOD LATHE Make/Model No.: Serial No.: School: Work Location: Name of Person(s) Conducting Activity:
More informationField Instruction. Stringing new bare conductors above or below live bare overhead conductors
5.10 Stringing, Tensioning and Sagging Conductors/Cables Purpose The purpose of this instruction is for all Horizon Power workers who undertake the stringing and tensioning of bare overhead conductors
More informationPotential risk of injury to staff
Register Fire, Earthquake - other Emergencies Manual Handling and Repetitive Work Repetitive, Forceful Work Poor Housekeeping Not Wearing PPE (Personal Protective Equipment) Potential risk of injury to
More informationUniversity College Dublin Machinery/Equipment Risk Assessment Template
1. General Information Name of Person(s) carrying out assessment and their position Principal Investigator / Supervisor / Head of School or Unit (Person responsible for ensuring safety) Date of assessment
More informationField Instruction. The purpose of this instruction is to inform all Horizon Power workers of the safety requirements when working from a EWP.
2.7 Safety Requirements When Working from an EWP Purpose The purpose of this instruction is to inform all Horizon Power workers of the safety requirements when working from a EWP. Scope The scope of this
More informationSafe Work Method Statement LRB TREE SERVICES 6 Behland St, Kearneys Spring QLD, 4350 ABN
JOB NO: PROJECT: DATE: 1/1/2018 SWMS NO: SWMS 001.1 PREPARED BY: LUKE BLINCO REVISED BY: ACTIVITY: TREE REMOVAL & PRUNING SIGNED BY: REVISION DATE: MINIMUM PERSONAL PROTECTIVE EQUIPMENT (PPE) REQUIREMENTS
More informationSafety at Work. Rules for Staying Alive
Safety at Work Rules for Staying Alive Safety at Work Rules for Staying Alive Introduction The purpose of Dana Gas Rules For Staying Alive is to address the key causes of deaths in our industry. These
More informationContractor OHS Induction. AOHS-05-GUI September 2016
Contractor OHS Induction AOHS-05-GUI-002 8 September 2016 1 About AQWEST AQWEST is a Government Trading Enterprise responsible for supplying drinking water to Bunbury. Formed in 1906 as the Bunbury Water
More informationMaterial Lift Risk and Hazard Management
Material Lift Risk and Hazard Management Models GH 3.8 Safe 136 kg Maximum 3.80 m GH5.6 Working 113 kg Lifting 5.60 m LL Load (kg) 91 kg Height (m) 1.70 m GL-4 227 kg 1.80 m GL-8 181 kg 3.06 m GL-10 159
More informationPLANT HAZARD AND EQUIPMENT RISK ASSESSMENT
Plant Identification : HAULOTTE HA16RTJ Potential Hazard Entanglement Can anything become entangled in moving parts? Crushing/Striking Can anyone be crushed or struck by moving objects due to: Risk es
More informationSAFE WORK METHOD STATEMENT SWMS No Version
SAFE WORK METHOD STATEMENT SWMS No Version Company Name: Hunter Readymixed Concrete Pty Ltd 00 004 Location: Thornton Cessnock Tea Gardens Gateshead ABN: 6 076 08 695 SWMS Developed By: Duane Harrison
More informationSAFETY MANAGEMENT SYSTEM
Equipment Location: Hazard Hired From All Master Hire Stores Entanglement Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving
More informationSAFE WORK METHOD STATEMENT WORKING IN CONFINED SPACE HSE NET NAT SWMS APAND00030
SAFE WORK METHOD STATEMENT WORKING IN CONFINED SPACE HSE NET NAT SWMS APAND00030 HIGH RISK APT AM Holdings Pty. Ltd. [ABN] 95124754383 Principal Contractor (PC) APA Group Level 19, HSBC Building 580 George
More informationPLANT HAZARD AND EQUIPMENT RISK ASSESSMENT
Plant Identification : HAULOTTE LIGHT BOOMS 3522A (HTA 13P); 4527A (HTA 16P); 5533A (HTA 19P) and 3632T (HTT 13) Potential Hazard Entanglement Can anything become entangled in moving parts? Crushing/Striking
More informationPLANT/EQUIPMENT/ASSET HAZARD REPORT
Asset Description: EL-08001-011 : Harrison 550 CNC Lathe Large Sale Type For what use is this asset being sold? Re-Use þ Spare Parts Scrap Note 1: Assets are sold only for the use indicated. Any other
More informationConfined Spaces. This procedure applies to all workers of the Diocese of Maitland Newcastle (DoMN).
Purpose To provide guidance in controlling the risks associated with confined spaces including identifying confined spaces, working in a confined space and issuing confined space entry permits. Scope This
More informationRISK ASSESSMENT. Bobcat Skid Steer Loader. Series F & G (incl. S Models) For. SSL Version 2
PO Box 50, Hornsby, NSW 2077 Phone: 1800 643 853 Web: www.bobcat.com.au RISK ASSESSMENT For Bobcat Skid Steer Loader Series F & G (incl. S Models) CONTENTS Applicability Standards referenced in the preparation
More informationSWMS No 012 Samark North Qld Pty Ltd ABN : Electrical Contractors License C37121 Page 2 of 6
Samark North Qld Pty Ltd SWMS SWMS No 0 Samark North Qld Pty Ltd ABN : 99 08 98 87 Electrical Contractors License C37 Page of 6 Safe Work Method Statement Title: SWMS:0 INSTALLING LIGHT POLES Work Method
More informationSafe Work Method Statement (SWMS)
Safe Work Method Statement (SWMS) Work Activity/Description: Site Name: Date: Site Address: Name Position Signature Document No: Prepared By: OHS Manager Revision: Reviewed By: National Program Manager
More informationField Instruction. This instruction outlines the minimum requirements for all Horizon Power workers who undertake Vegetation Management Work.
10.6 Management Work Purpose This instruction outlines the minimum requirements for all Horizon Power workers who undertake Management Work. Scope The scope of this instruction is to inform all Horizon
More informationPLANT HAZARD AND EQUIPMENT RISK ASSESSMENT
PLAT HAZARD AD EQUIPMET RISK ASSESSMET Plant Identification : HAULOTTE STAR 10 Potential Hazard Entanglement Can anything become entangled in moving parts? Crushing/Striking Can anyone be crushed or struck
More informationPLANT/EQUIPMENT/ASSET HAZARD REPORT
Asset Description: EL-0001-003 - Overhead Transfer System and EMS. Sale Type For what use is this asset being sold? Re-Use Spare Parts Scrap Note 1: Assets are sold only for the use indicated. Any other
More informationContractor handbook. Purpose
Page no: 1 / 6 Contractor handbook Purpose Mitie aims to ensure that the highest levels of performance are achieved by all persons working for us or on our behalf. We require the same level of performance
More informationHealth & Safety Contractor rules
Health & Safety Contractor rules Contents 1. Introduction... 1 2. The legal bit explaining our terminology... 1 2.1 Legal requirements... 1 3. Our health and safety requirements... 1 3.1 Access to BT premises...
More informationPrint this activity then complete it and keep it as evidence in your folder, or portfolio.
Workplace hazards Workplace Learning and Assessment Activity Workplace Learning and Assessment Activity Print this activity then complete it and keep it as evidence in your folder, or portfolio. Hazard
More informationPLANT/EQUIPMENT/ASSET HAZARD REPORT
Asset Description: EL-09100-060 : Gantry hoist system Sale Type For what use is this asset being sold? Re-Use Spare Parts Scrap Note 1: Assets are sold only for the use indicated. Any other use is at the
More informationSafety Essentials. Mandatory rules for our high risk activities
Mandatory rules for our high risk activities Remember... Only undertake activities for which you are trained, competent and authorised to do Before you start a job take a step back, think about all the
More informationSAFETY MANAGEMENT SYSTEM
Equipment Location: Hazard Hired From All Master Hire Stores Entanglement Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving
More informationPLANT RISK ASSESSMENT
PLANT RISK ASSESSMENT Forktruck: Year of Manufacture Make: Model: Serial : TCM FD30T3 Attachment: Name: Mfg: Model : Owner: Business/Organisation: Address: This header page and the following 5 pages have
More informationFLYING OBJECTS MANUAL HANDLING EXCESSIVE NOISE
JOB NO: PROJECT: DATE: SWMS NO: SWMS 002 PREPARED BY: Ian Hartley REVISED BY: Nick Bragg & Cameron McNeil ACTIVITY: STUMP REMOVAL SUPERVISED BY: REVISION DATE: April 2016 MINIMUM PERSONAL PROTECTIVE EQUIPMENT
More informationSafe Work Method Statement (SWMS)
Safe Work Method Statement (SWMS) Organisation Details : Organisation Name Northern Plumbing Contact ABN 17 15 41 4 Position Director Address 47 Thomas Street Edgeworth 85 Phone Number 0411 10 4 Project
More informationSAFETY MANAGEMENT SYSTEM
Equipment Location: Hazard Hired From All Master Hire Stores Entanglement Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving
More informationSafety Checklist for Events Held at Hillbrook
Safety Checklist for Events Held at Hillbrook Hazards/ Issues or Tasks 1. EVENT ACCESS AND EGRESS Entry / Exit areas are kept clear and accessible. For an evening event, that you have appropriate Lighting.
More information: Electric Power Generation, Transmission, and Distribution. Region IV - OSHA
1910.269: Electric Power Generation, Transmission, and Distribution Region IV - OSHA Scope This standard covers the operation and maintenance of electric power generation, control, transformation transmission,
More informationMeet Today s Webinar Team
Meet Today s Webinar Team Moderator: Stacy Rose, CSP Stacy is a certified professional with 16 years experience in workplace safety. Stacy holds a bachelor s in industrial engineering and a master s in
More informationSAFE WORK METHOD STATEMENT
SAFE WORK METHOD STATEMENT EXCAVATION OR TRENCHING Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES
More informationSWMS No 009 Samark North Qld Pty Ltd ABN : Electrical Contractors License C37121 Page 2 of 4
Samark North Qld Pty Ltd SWMS Manual SWMS No 009 Samark North Qld Pty Ltd ABN : 99 082 98 87 Electrical Contractors License C72 Page 2 of Safe Work Method Statement Title: SWMS:009 Confined Space Work
More informationRisk and Hazard Management
Risk and Hazard Management Models TZ34 Safe 200 Maximum 12.4 Maximum 10.4 TZ50 Working 200 Platform 15 Working 17 Z30/20NRJ Load (kg) 227 Drive 8.9 Height (m) 10.9 Z33/18 200 Height (m) 10 12 Z34/22 227
More informationPowerplay Paintball Brighouse Risk Assessment
Chemical Gas bottles Vehicles Physical Electricity Environment Machinery Powerplay Paintball Brighouse Risk Assessment Location Powerplay Paintball Wakefield and Brighouse Venues Carried out by: Steven
More informationMinimum Safety Requirements for Contractors Working on Railway Property
Minimum Safety Requirements for Contractors Working on Railway Property Effective_ April 1, 2007 Introduction Canadian Pacific is committed to provide a Safe and Healthy working environment for all Railway
More informationPLANT HAZARD AND EQUIPMENT RISK ASSESSMENT
PLAT HAZARD AD EQUIPMET RISK ASSESSMET Plant Identification : HAULOTTE OPTIMUM 8.1 Potential Hazard Entanglement Can anything become entangled in moving parts? Crushing/Striking Can anyone be crushed or
More informationSAFETY MANAGEMENT SYSTEM
Equipment Location: Hazard Hired From All Master Hire Stores Entanglement Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving
More informationWORK METHOD STATEMENT STRUCTURAL STEEL
ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 52 284 873 581 Contact Position: Director Address: PO Box 1138, Townsville QLD 4810 Contact Phone
More informationHow severely could the risk hurt someone? Low/Insignificant First aid
Safe Work Method Statement No: WMS-02 Task: Concreting, Formwork and Steel Fixing This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia)
More information6. Each mitigation was verified and individually documented
CHESM/MSW Field Verification Instructions: All information in sections A, B and C must be completed. Information in section B related to subcontractors should be obtained from the work crew if possible.
More information2.0 Management Systems and Documentation
SHE Rules BOW142.3 1.0 Introduction This document details the safety, health and environment rules that apply to anyone accessing Arqiva sites and describes the standards of performance expected. This
More informationEHS Workplace Inspection Checklist (Ref. SOP QMS-080; EHS-010)
(Ref. SOP QMS-080; EHS-010) Form-445 Inspected by: Date of inspection Date of Report Report # Pages Area Manager: Area Inspected: General This EHS Workplace Inspection was conducted by: Scope of the Inspection:
More informationSAFETY POLICY AND PROCEDURE MANUAL QUESTIONNAIRE
The following questionnaire is designed to aid us in the creation of your policy and procedure manual. Please place a checkmark in the boxes that correspond to the sections that you would like to be included
More informationSITE SPECIFIC SAFETY PLAN (SSSP)
SITE SPECIFIC SAFETY PLAN (SSSP) This plan shall be completed and reviewed with the Corporate Safety Department before work commences. Completed plans shall be maintained and kept on site with the project
More informationRisk and Hazard Management
Risk and Hazard Management Models S40 Safe 227 Maximum 12.2 Maximum 14.2 S45 Working 227 Platform 13.7 Working 15.7 S60 Load (kg) 227 Drive 18.3 Height (m) 20.3 S65 227 Height (m) 19.8 21.8 S65 TRAX 227
More informationSafety Risk Assessment Roofing Works / Surveying / Inspections
One Direct aintenance td Persons at (Groups) Assessor Appointment Tel. No. Description of Task or Activity A One Direct employees ark Bloxidge H&S anager 0208 821 5197 One Direct Operatives accessing roof
More informationRisk and Hazard Management
Risk and Hazard Management Models GS1532 Safe 272 Maximum 4.6 Maximum 6.6 GS1930 Working 227 Platform 5.8 Working 7.8 GS1932 Load (kg) 227 Drive 5.8 Height (m) 7.8 GS2032 363 Height (m) 6.1 8.1 GS2632
More informationISS Safety Rules. Make safety second nature
ISS Safety Rules Make safety second nature 2 ISS SAFETY RULES ISS SAFETY RULES 3 INTRODUCTION We are a company driven by close to 500,000 strong people spread across 77 countries around the globe. And
More informationWaste Industry Safety & Health
Waste Industry Safety & Health A practical pocket guide for the Waste industry Supported by: Delivering the Solution Together Introduction The Waste Industry Safety and Health (WISH) forum is supporting
More informationInstructions for the Use of the Excel Spreadsheet. There are Three tabs at the bottom of this worksheet. Instructions tab is the one you are reading
Instructions for the Use of the Excel Spreadsheet There are Three tabs at the bottom of this worksheet Instructions tab is the one you are reading H&S Plan Tab The Plan Tab is the front cover pages of
More informationManually Propelled Risk and Hazard Management
Manually Propelled Risk and Hazard Management Models AWP-20S Safe 159 Maximum N/A Maximum 6.12 AWP-25S Working 159 Platform N/A Working 7.57 AWP-30S Load (kg) 159 Height (m) N/A Height (m) 9.00 AWP-36S
More informationWHS OHS HAZARD REGISTER (SITE AND OFFICE OPERATIONS)
WHS 017 - WHS 017 Hazard Register - Version 5.0 April 20 Doc No: WHS 017 Effective Date: 04/04/20 1 WORKING WITH EARTHMOVING PLANT/ TRUCKS/SITE VEHICLES COLLISIONS OTHER PLANT EQUIPMENT SITE VEHICLES PERSONNELL
More informationHEAT, COLD, SOLAR ULTRAVIOLET & INCLEMENT WEATHER
CONTRACTOR WHS HAZARD STANDARD HEAT, COLD, SOLAR ULTRAVIOLET & INCLEMENT WEATHER EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS
More informationAccident Investigation and Hazard Analysis
Accident Investigation and Hazard Analysis June 18, 2015 Objectives: Accident Investigation Define accidents Review why accident investigations are important Review the purpose of accident investigations
More informationRisk and Hazard Management
Risk and Hazard Management Models S40/45 Safe 227 Maximum 12.2/13.72 Maximum 14.2/15.72 S60/65 Working 227/499 Platform 18.34/19.8 Working 20.34/21.8 S80/85 Load (kg) 227/454 Drive 24.2/25.7 Height (m)
More informationRisk Assessment Form (Qualitative)
Assessment Form (Qualitative) Project / ocation:..d.a.s WATERS Contract No: RA & Issue No: 008 Prepared by:.r.smit Date: 10/10/16 Signature: ACTIVITY DESCRIPTION: Person (s) at risk: General Ground works
More informationCourse Title: Industrial Safety in Electronics Engineering Technology Number of Credits: 3 B.A. B.S. B.A.S A.A. A.S. Degree Type
GENERAL INFORMATION Name: Diane King Phone #: 77021 Course Prefix/Number: ETI3704 Course Title: Industrial Safety in Electronics Engineering Technology Number of Credits: 3 B.A. B.S. B.A.S A.A. A.S. Degree
More informationBSO Plus ANNUAL SAFETY REFRESHER 2015
The BSO Plus Safety Refresher is an annual checkpoint designed from the content in BSO Plus. Completing this refresher is a requirement for the Basic Safety Recertification (BSR) course, so please ensure
More informationThe University of British Columbia Department of Earth, Ocean and Atmospheric Sciences Hazard Identification and Risk Assessment for Field Activities
azard Identification and Risk Assessment for Field Activities 1. Critical components (a) A comprehensive appraisal of the hazards to be encountered on field activities and an assessment of the risks associated
More informationSWMS documented by: Feb Bo Ceprnja Date Feb Feb Feb 2018
Contractor Company Details: BUILDSAFE SAFE WORK METHOD STATEMENT 0002 (Void Platform Stairs) Part 1 (To be used in conjunction with SWMS 0001 General Site Activities & SWMS 0002 Void Platform) Additional
More informationPLANT HAZARD AND RISK ASSESSMENT WORKSHEET (PHA)
Matrix Assessment Date: 15.2.2011 Consequences Likelihood or Probability Plant Type: CRANE Plant Make: TADANO Plant Model: TL250E Fleet: 281 Plant Serial No. 335347 Assessment Facilitated by: A WHEELER
More informationRIIWMG203D Drain and Dewater Civil Construction Site Learner Guide
RIIWMG203D Drain and Dewater Civil Construction Site Table of Contents 1.1 Introduction... 3 1.1.1 Drainage and Dewatering... 3 1.2 Site Policies and Procedures... 5 1.3 Work Instructions... 6 1.3.1 Reading
More informationCourse outline: 111 WH&S E101A UEENEEE101A - Occupational Health and Safety regulations, codes and practices in the workplace
RTO Code 41319 Course outline: 111 WH&S E101A UEENEEE101A - Occupational Health and Safety regulations, codes and practices in the workplace Qualification: Applicable to: Unit of competency: Related policies:
More informationSection J. How to develop safety elements for project safety management system. How to develop safety elements for project SMS
Section J How to develop safety elements for project safety management system 1. Once the project management has developed or adopted a safety policy, it needs to develop safety elements to meet the objectives
More informationNZQA Expiring unit standard version 7 Page 1 of 8. Demonstrate knowledge of safe working practices in telecommunications.
Page 1 of 8 Title Demonstrate knowledge of safe working practices in telecommunications Level 2 Credits 4 Purpose This unit standard covers basic instruction in safe working practices in the telecommunications
More informationCode of Practice and Instructions to Contractors Working for Viridor
Date of issue: 20 Code of Practice and Instructions to Contractors Working for Viridor Prepared by: Ian Powell Head of Safety Management 4.6.3 Revision: 2.0 Contents Introduction... 2 Legal obligations...
More informationAppendix 4C - Sample SWMS Trenching
Appendix 4C - Sample SWMS Trenching SAFE WORK METHOD STATEMENT SWMS Reference : Insert document number : Version A Date : Workplace / Project : Company Address: Work Activity / Job / Task or Process :
More informationCWA Work-at-Height Certification Assessment Criteria Competent Climbing Wall Worker
Course Date(s): Course Location: Provider(s): Candidate s Name: Candidate s Company: Candidate s Personal Contact Information (complete personal mailing address, mobile phone and personal email address):
More informationHazard Identification and Risk Management
Hazard Identification and Risk Management Australian Workcover Authorities [supported by the Company] currently use a risk management approach in developing their legislative controls. This means that:
More informationPower Unit 075. Maintain Substation Circuit Breakers
Power Unit 075 Maintain Substation Circuit Breakers The specification details the required skills, knowledge and behaviours to establish competence to carry out the maintenance of high voltage power circuit
More informationSAFETY AND OSHA GUIDELINE CURRICULUM
SAFETY AND OSHA GUIDELINE CURRICULUM CertiLearn - Non-Industrial OSHA Safety Guidelines These courses are ideal for any small business or non-industrial environment Safety Basics In this course you will
More informationBuchanan. Approved: John Downes
Severity Site triio Activity Vacuum Excavator Persons conducting assessment SHEQ DEPT Assessment No triio 21 Review Date 11/01/2021 Revision No. 10 Name: Paul Disley/Ian Buchanan Signature Date: 11/01/2019
More informationHAZARD RECOGNITION EVALUATION and CONTROL
What is a hazard? HAZARD RECOGNITION EVALUATION and CONTROL Hazard - a dangerous object, event, behaviour or condition (in the workplace) which has the potential to cause injury, illness or property damage.
More informationList all key terms and acronyms used in the procedure, and their definitions.
Purpose The purpose of this procedure is to provide guidelines for electrical safety in general within Seqwater in compliance with the Electrical Safety Act 2002, Industry Codes of Practice, Regulations,
More information1. SHEWMS DETAILS. Project No. Valid From
Name of Project Name / Description of Work Activity being undertaken Location at which Activity is being undertaken Name of SHEWMS Owner (Contractor) SHEWMS Owner Business Address Name of person who prepared
More informationSummary of Standards for Key Items of PPE
Summary of Standards for Key Items of PPE This is a guide to the selection of suitable PPE. In some cases certain PPE is mandatory and forms part of a safe system of work. These are the minimum requirements
More informationPlant hazard checklist
110797 VWA PlantHazard Cvr 21/11/05 10:28 AM Page 1 Plant hazard checklist Some of the questions you should ask to help identify hazards arising from plant WorkSafe Victoria is a division of the Victorian
More informationNew Hire Safety Orientation. Welcome to Flexicrew, our number one priority is you and your safety.
New Hire Safety Orientation Welcome to Flexicrew, our number one priority is you and your safety. 1 New Employee Responsibilities As a contract worker with Flexicrew Staffing, I understand by signing this
More informationThe modern, fast and easy to use risk analysis tool. Advanced Features. Using HAZID in BowTie Pro
The modern, fast and easy to use risk analysis tool Advanced Features Using HAZID in BowTie Pro Enterprise Business Centre Admiral Court Poynernook Road Aberdeen, AB11 5QX, UK Tel: +44 (0) 1224 51 50 94
More informationWINDMILL (pre-start) HAZARD INSPECTION CHECKLIST
Windmill Hazard Inspection Checklist WINDMILL (pre-start) HAZARD INSPECTION CHECKLIST Authorised by: LOCATION OF INSPECTION...... Inspected By (1)........... (2)..... PRINT PRINT Signature (1):. (2)....
More information