1 DRAFT FOR CLIENT REVIEW ONLY TENW Transportation Engineering NorthWest MEMORANDUM DATE: August 22, 2017 TO: FROM: SUBJECT: Patrick Yamashita City of Mercer Island Chris Forster, P.E. TENW Trip Generation & Sight Distance Evaluation TENW Project No This memorandum documents the trip generation and sight distance evaluation completed for the proposed 4320 Island Crest Way (Chiu Subdivision) development in Mercer Island, WA. The memo includes a project description, a trip generation estimate, and a sight distance assessment. Key Findings 1. The proposed Chiu Subdivision project is estimated to generate less than 10 new PM peak hour trips. Therefore, based on the City s General Traffic Impact Analysis Requirements, the project does not require a traffic impact analysis (TIA). 2. Stopping sight distance requirements are met at both site access locations on Island Crest Way. 3. Intersection sight distance is acceptable at both site access locations assuming clearing and regrading is conducted within the right-of-way to achieve clear sight lines looking north and south of the proposed access points. Project Description The project site is located at 4320 Island Crest Way in Mercer Island, WA as shown in Attachment A (vicinity map). The proposed development would include 6 single-family residential detached dwelling units. The existing site includes 2 single-family homes, both of which would be removed with the proposed project, resulting in a net addition of 4 single-family units. Vehicular access to/from five of the proposed lots (north access) would be provided via a new full-access private road onto Island Crest Way approximately 66 feet south of the north property line. This access would replace an existing driveway to the existing home on the north half of the site. Vehicular access to/from one lot (south access) would be provided at a new full access driveway located near the south property line in the same location as an existing driveway serving the existing home on the south half of the site. The project is expected to be constructed in A preliminary site plan is included as Attachment B. Transportation Planning Design Traffic Impact & Operations SE 8 th Street, Suite 200, Bellevue, WA Office (425)

2 Trip Generation Estimate The weekday daily, AM peak hour, and PM peak hour trip generation estimates for the proposed Chiu Subdivision development were based on trip rates documented in the Institute of Transportation Engineers (ITE) Trip Generation Manual, 9 th edition for land use code (LUC) 210 (Single-Family Detached Housing). Table 1 summarizes the trip generation estimate for the project (6 proposed single-family homes less 2 existing single-family homes). Table 1 Chiu Subdivision Trip Generation Summary Net New Trips Generated Time Period In Out Total Weekday Daily Weekday AM Peak Hour Weekday PM Peak Hour As shown in Table 1, the proposed Chiu Subdivision development is estimated to generate 38 net new weekday daily trips with 3 net new weekday AM peak hour trips (1 entering, 2 exiting), and 4 net new weekday PM peak hour trips (3 entering, 1 exiting). The detailed trip generation estimates are included in Attachment C. Based on the City of Mercer Island General Traffic Impact Analysis Requirements dated 7/15/2015, a project requires a traffic impact analysis if the proposed use will generate 10 or more peak hour trips. The proposed Chiu Subdivision development is estimated to generate less than 10 net new peak hour trips. Therefore, the project does not require a traffic impact analysis. Sight Distance Assessment The following summarizes the results of the sight distance assessment conducted at the two site access driveways onto Island Crest Way based on a review of engineering standards, field measurements, and aerial photography. The posted speed limit on Island Crest Way in the vicinity of the project is 35 mph. A design speed of 40 MPH (posted speed + 5 MPH) was assumed for this analysis. The grade on Island Crest Way in the vicinity of the proposed site access location is less than 3 percent. Therefore, no adjustments were made to account for grade. For this assessment, we analyzed both Intersection Sight Distance (ISD) and Stopping Sight Distance (SSD) based on the standards in AASHTO Policy on Geometric Design of Highways and Streets, 6 th Edition, 2011 (AASHTO). North Access Intersection Sight Distance (ISD): Based on AASHTO Policy on Geometric Design of Highways and Streets, 6 th Edition, 2011 Table 9-6 (Case B1, Left Turn from Stop), the minimum required left turn ISD for a 40 MPH design speed is 445 feet. Because TENW August 22, 2017 Page 2

3 Island Crest Way is a multilane roadway (vehicles must cross 2 lanes to turn left from the access driveways), this value was adjusted based on AASHTO standards to 470 feet by adjusting the time gap. ISD was measured based on an entering vehicle driver eye height of 3.5 feet, measured 14.5 feet back from the edge of traveled way. ISD Looking North: The available ISD at the Island Crest Way/North Access intersection looking north will meet or exceed 470 feet assuming existing vegetation is cleared and any slope regraded to obtain a clear line of sight. Based on our review of aerial photography and property lines from King County Parcel Viewer, it appears that all required clearing would be within existing City right-of-way (ROW). A diagram showing the ISD sight line looking north is provided in Attachment D. View looking north on Island Crest Way from north site access location (view is from a point 6 feet behind the existing curb due to existing vegetation) ISD Looking South: The maximum available ISD at the Island Crest Way/North Access intersection looking south would be approximately 404 feet (does not meet the 470-foot standard) using the existing ROW line as the limiting factor (sight line tangent to ROW line). Meeting the 470-foot standard is not feasible as the line of sight crosses into private property due to the horizontal curve in Island Crest Way. In order for 404 feet of ISD to be achieved, existing vegetation must be cleared and slope regraded within the limits of the existing ROW. TENW August 22, 2017 Page 3

4 While 404 feet of ISD is less than the AASHTO standard for left-turns, it is greater than the minimum required ISD for a right turn. Based on AASHTO Policy on Geometric Design of Highways and Streets, 6 th Edition, 2011 Table 9-7 Case B2, Right Turn from Stop, the standard for a 40 MPH design speed is 385 feet for right turns. Considering the fact that a majority of the traffic from these homes will be right turns onto Island Crest Way (as opposed to left-turns), we believe that 404 feet of ISD is acceptable (with clearing/regrading within ROW). In addition, TENW also reviewed the most recent 3-year collision history ( WSDOT data) and confirmed that there were no reported collisions at the existing north site driveway (or at any of the nearby driveways on Island Crest Way). Diagrams showing the ISD sight lines looking south (470 feet and 404 feet) are provided in Attachment D. View looking south on Island Crest Way from north site access location (view is from a point 6 feet behind the existing curb due to existing vegetation) Stopping Sight Distance (SSD): Based on AASHTO Policy on Geometric Design of Highways and Streets, 6 th Edition, 2011 Table 3-1 (Stopping Sight Distance on Level Roadways), the minimum required SSD for a 40 MPH design speed is 305 feet. SSD was measured based on an approaching vehicle driver eye height of 3.5 feet and an object height of 2.0 feet. SSD was measured along the centerline of the curb-side lane on Island Crest Way. Northbound: Based on field measurements, the existing available SSD for a vehicle traveling northbound on Island Crest Way approaching the north access location exceeds 305 feet. TENW August 22, 2017 Page 4

5 Southbound: Based on field measurements, the existing available SSD for a vehicle traveling southbound on Island Crest Way approaching the north access location exceeds 305 feet. South Access Intersection Sight Distance (ISD): Based on AASHTO Policy on Geometric Design of Highways and Streets, 6 th Edition, 2011 Table 9-6 (Case B1, Left Turn from Stop), the minimum required left turn ISD for a 40 MPH design speed is 445 feet. Because Island Crest Way is a multilane roadway (vehicles must cross 2 lanes to turn left from the access driveways), this value was adjusted based on AASHTO standards to 470 feet by adjusting the time gap. ISD was measured based on an entering vehicle driver eye height of 3.5 feet, measured 14.5 feet back from the edge of traveled way ISD Looking North: The available ISD at the Island Crest Way/South Access intersection looking north will meet or exceed 470 feet assuming existing vegetation is cleared and any slope regraded to obtain a clear line of sight (currently the available ISD is only 255 feet due to existing vegetation). Based on our review of aerial photography and property lines from King County Parcel Viewer, it appears that all required clearing would be within existing City right-of-way (ROW). A diagram showing the ISD sight line looking north is provided in Attachment E. View looking north on Island Crest Way from south site access location (14.5 feet behind curb) TENW August 22, 2017 Page 5

6 ISD Looking South: The maximum available ISD at the Island Crest Way/South Access intersection looking south would be approximately 310 feet (does not meet the 470-foot standard) using the existing ROW line as the limiting factor (sight line tangent to ROW line). Meeting the 470-foot standard is not feasible as the line of sight crosses into private property due to the horizontal curve in Island Crest Way. In order for 310 feet of ISD to be achieved, existing vegetation must be cleared and possibly slope regraded within the limits of the existing ROW. While 310 feet of ISD is less than the AASHTO standard, it is greater than the required SSD standard of 305 feet. Meeting the minimum SSD standard ensures that safe ingress/egress can occur as there will be more than sufficient sight distance available for vehicles travelling on Island Crest Way to be able to stop for conflicting traffic. In addition, it should be noted that this is a driveway to one single family home at a location where one already exists. The existing available ISD looking south at this location is only 145 feet. If the recommended clearing of vegetation and regrading is conducted within the limits of existing ROW, the resulting ISD will be a significant improvement over existing conditions (more than 2 times the existing ISD). TENW also reviewed the most recent 3-year collision history ( WSDOT data) and confirmed that there were no reported collisions at the existing driveway (or at any of the adjacent driveways on Island Crest Way). Based on these considerations, we believe that 310 feet of ISD is acceptable (with clearing/regrading within ROW) for an access to a single family dwelling. Diagrams showing the ISD sight lines looking south (470 feet and 310 feet) are provided in Attachment E. View looking south on Island Crest Way from south site access location (14.5 feet behind curb) TENW August 22, 2017 Page 6

7 Stopping Sight Distance (SSD): Based on AASHTO Policy on Geometric Design of Highways and Streets, 6 th Edition, 2011 Table 3-1 (Stopping Sight Distance on Level Roadways), the minimum required SSD for a 40 MPH design speed is 305 feet. SSD was measured based on an approaching vehicle driver eye height of 3.5 feet and an object height of 2.0 feet. SSD was measured along the centerline of the curb-side lane on Island Crest Way. Northbound: Based on field measurements, the existing available SSD for a vehicle traveling northbound on Island Crest Way approaching the south access location exceeds 305 feet. Southbound: Based on field measurements, the existing available SSD for a vehicle traveling southbound on Island Crest Way approaching the south access location exceeds 305 feet Sight Distance: Conclusions 1. Stopping sight distance requirements are met at both site access locations on Island Crest Way. 2. Intersection sight distance is acceptable at both site access locations assuming clearing and regrading is conducted within the right-of-way to achieve clear sight lines looking north and south of the proposed access points. If you have any questions regarding the information presented in this memo, please call me at or at cc: Jayson Taylor Alan Chiu Attachments A. Vicinity Map B. Preliminary Site Plan C. Trip Generation Estimate D. Preliminary ISD Sight Line Diagrams North Access E. Preliminary ISD Sight Line Diagrams South Access TENW August 22, 2017 Page 7

8 ATTACHMENT A Site Vicinity Map

9 ATTACHMENT B Preliminary Site Plan

10 ATTACHMENT C Trip Generation Estimate Weekday Daily ITE Directional Split Trip Rate Trips Generated Land Use Units 1 LUC 2 In Out Total In Out Total Proposed Use Single-Family 6 DU % 50% Less Existing Use Single-Family 2 DU % 50% Total Net New Weekday Daily Trips Generated = AM Peak Hour Trip Generation ITE Directional Split Trip Rate Trips Generated Land Use Units LUC 1 In Out Total In Out Total Proposed Use Single-Family 6 DU % 75% Less Existing Use Single-Family 2 DU % 75% Total Net New AM Peak Hour Trips Generated = PM Peak Hour Trip Generation ITE Directional Split Trip Rate Trips Generated Land Use Units LUC 1 In Out Total In Out Total Proposed Use Single-Family 6 DU % 37% Less Existing Use Single-Family 2 DU % 37% Notes: Total Net New PM Peak Hour Trips Generated = DU = Dwelling Units. 2 Institute of Transportation Engineers, Trip Generation Manual, 9th edition Land Use Code.

11 ATTACHMENT D North Access ISD Sight Line Diagrams

12 D1 NORTH ACCESS: ESD Looking North 40 MPH Design Speed AASHTO Standard = 470' ESD MET assuming clearing within ROW 80'-0" Sight Line 66'-0" 470'-0" CENTER OF SITE ACCESS 5'-6"

13 D2 NORTH ACCESS: ESD Looking South 40 MPH Design Speed AASHTO Standard = 470' ESD NOT MET 20'-0" 80'-0" 5'-6" 66'-0" CENTER OF SITE ACCESS ESD SIGHT LINE OUTSIDE OF CITY RIGHT OF WAY 470'-0" Sight Line

14 D3 NORTH ACCESS: ESD Looking South Approx. Max ESD Measured = 404 FT (assuming clearing within City ROW) 20.0 ft 80.0 ft 5.5 ft 66.0 ft CENTER OF SITE ACCESS ESD SIGHT LINE TANGENT TO CITY RIGHT OF WAY ft Sight Line

15 ATTACHMENT E South Access ISD Sight Line Diagrams

16 E1 SOUTH ACCESS: ESD Looking North 40 MPH Design Speed AASHTO Standard = 470' ESD MET assuming clearing within ROW 20'-0" 80'-0" Sight Line 470'-0" CENTER OF SITE ACCESS 5'-6"

17 E2 SOUTH ACCESS: ESD Looking South 40 MPH Design Speed AASHTO Standard = 470' ESD NOT MET 5'-6" CENTER OF SITE ACCESS ESD SIGHT LINE OUTSIDE CITY RIGHT OF WAY 90'-0" 470'-0" Sight Line

18 E3 SOUTH ACCESS: ESD Looking South Approx. Max ESD Measured = 310 FT (assuming clearing within City ROW) 5'-6" CENTER OF SITE ACCESS ESD SIGHT LINE TANGENT TO CITY RIGHT OF WAY 310'-0" 90'-0" Sight Line

This Chapter sets forth the minimum design, technical criteria and specifications to be used in the preparation of all roadway plans.

This Chapter sets forth the minimum design, technical criteria and specifications to be used in the preparation of all roadway plans. 4.1 GENERAL This Chapter sets forth the minimum design, technical criteria and specifications to be used in the preparation of all roadway plans. These Roadway Standards are for new construction and modification

More information

5858 N COLLEGE, LLC N College Avenue Traffic Impact Study

5858 N COLLEGE, LLC N College Avenue Traffic Impact Study 5858 N COLLEGE, LLC nue Traffic Impact Study August 22, 2016 Contents Traffic Impact Study Page Preparer Qualifications... 1 Introduction... 2 Existing Roadway Conditions... 5 Existing Traffic Conditions...

More information

TRAFFIC IMPACT STUDY And A TRAFFIC SIGNAL WARRANT ANALYSIS FOR A SENIOR LIVING AND APARTMENT DEVELOPMENT

TRAFFIC IMPACT STUDY And A TRAFFIC SIGNAL WARRANT ANALYSIS FOR A SENIOR LIVING AND APARTMENT DEVELOPMENT TRAFFIC IMPACT STUDY And A TRAFFIC SIGNAL WARRANT ANALYSIS FOR A SENIOR LIVING AND APARTMENT DEVELOPMENT DEERFIELD TOWNSHIP, WARREN COUNTY, OHIO Nantucket Circle and Montgomery Road () Prepared for: ODLE

More information

SELECTED ROADWAY CAPACITY ANALYSIS

SELECTED ROADWAY CAPACITY ANALYSIS CHAPTERFOUR SELECTED ROADWAY CAPACITY ANALYSIS 4.1 SELECTED ROADWAY CAPACITY ANALYSIS Introduction Capacity analysis was performed on six selected roadways within the Dearborn County study area using the

More information

City of Prince Albert Statement of POLICY and PROCEDURE. Department: Public Works Policy No. 66. Section: Transportation Issued: July 14, 2014

City of Prince Albert Statement of POLICY and PROCEDURE. Department: Public Works Policy No. 66. Section: Transportation Issued: July 14, 2014 Page: 1 of 8 1 POLICY 1.01 The City shall follow all of the specifications in the Manual of Uniform Traffic Control Devices for Canada, prepared by the National Committee of Uniform Traffic Control, and

More information

Roadway Design Manual

Roadway Design Manual Roadway Design Manual Manual Notice Archive by Texas Department of Transportation (512) 302-2453 all rights reserved Manual Notice 2009-1 From: Manual: Mark A. Marek, P.E Roadway Design Manual Effective

More information

POWELL BUTTE HIGHWAY/NEFF ROAD INTERSECTION Interim Report: Existing Conditions, Needs, and Alternatives Review

POWELL BUTTE HIGHWAY/NEFF ROAD INTERSECTION Interim Report: Existing Conditions, Needs, and Alternatives Review POWELL BUTTE HIGHWAY/NEFF ROAD INTERSECTION Interim Report: Existing Conditions, Needs, and Alternatives Review Date: December 30, 2013 Project #: 13963.0 To: Chris Doty PE and George Kolb, Deschutes County

More information

1609 E. FRANKLIN STREET HOTEL TRAFFIC IMPACT STUDY EXECUTIVE SUMMARY

1609 E. FRANKLIN STREET HOTEL TRAFFIC IMPACT STUDY EXECUTIVE SUMMARY 1609 E. FRANKLIN STREET HOTEL TRAFFIC IMPACT STUDY EXECUTIVE SUMMARY Prepared for: The Town of Chapel Hill Public Works Department Traffic Engineering Division Prepared by: HNTB North Carolina, PC 343

More information

Figure 1: Graphical definitions of superelevation in terms for a two lane roadway.

Figure 1: Graphical definitions of superelevation in terms for a two lane roadway. Iowa Department of Transportation Office of Design Superelevation 2A-2 Design Manual Chapter 2 Alignments Originally Issued: 12-31-97 Revised: 12-10-10 Superelevation is the banking of the roadway along

More information

180 Grand Avenue, Suite x117 Dowling Associates, Inc.

180 Grand Avenue, Suite x117 Dowling Associates, Inc. 180 Grand Avenue, Suite 250 510.839.1742 x117 Oakland, CA 94612 510.839.0871 fax www.dowlinginc.com mbowman@dowlinginc.com Dowling Associates, Inc. Date: Memorandum To: CC: From: Ms. Leah Greenblat City

More information

Practical Application of Turn Lane Design Criteria in Developing Suburban & Urban Corridors

Practical Application of Turn Lane Design Criteria in Developing Suburban & Urban Corridors Practical Application of Turn Lane Design Criteria in Developing Suburban & Urban Corridors Presented by Gilmer D. Gaston, P.E., PTOE October 14, 2014 San Antonio Austin Houston Fort Worth Dallas When

More information

Geometric Design Tables

Geometric Design Tables Design Manual Chapter 5 - Roadway Design 5C - Geometric Design Criteria 5C-1 Geometric Design Tables A. General The following sections present two sets of design criteria tables - Preferred Roadway Elements

More information

City of Margate, Florida. Neighborhood Traffic Management Manual

City of Margate, Florida. Neighborhood Traffic Management Manual City of Margate, Florida Neighborhood Traffic Management Manual Table of Contents Page No. I. INTRODUCTION... 1 II. TRAFFIC CALMING REQUEST AND PROCESSING PROCEDURES... 2 1. COMPLETE AND SUBMIT PROJECT

More information

CITY OF COCONUT CREEK IMPLEMENTATION GUIDELINES FOR TRAFFIC CALMING

CITY OF COCONUT CREEK IMPLEMENTATION GUIDELINES FOR TRAFFIC CALMING CITY OF COCONUT CREEK IMPLEMENTATION GUIDELINES FOR TRAFFIC CALMING I. Introduction: The City of Coconut Creek recognizes that the conditions of residential streets can greatly affect neighborhood livability;

More information

200 Horizontal and Vertical Design. Table of Contents

200 Horizontal and Vertical Design. Table of Contents 200 Horizontal and Vertical Design Table of Contents 201 Sight Distance... 2-1 201.1 General... 2-1 201.2 Stopping Sight Distance... 2-1 201.2.1 Horizontal Sight Distance... 2-2 201.2.2 Vertical Stopping

More information

Windy Ridge Elementary School

Windy Ridge Elementary School Windy Ridge Elementary School SCHOOL ROUTE PLAN For WINDY RIDGE ELEMENTARY SCHOOL LOCATION 54 ORANGE COUNTY Prepared for: ORANGE COUNTY SCHOOL ASSESSMENT PROGRAM ORANGE COUNTY PUBLIC WORKS Traffic Engineering

More information

SCHOOL CROSSING PROTECTION CRITERIA

SCHOOL CROSSING PROTECTION CRITERIA CITY OF MADISON TRAFFIC ENGINEERING SCHOOL CROSSING PROTECTION CRITERIA AUGUST 1990 Adopted as Policy on August 31, 1976, by Common Council by Amended Resolution #29,540 Amended on September 14, 1976,

More information

DRAFT Sellwood Bridge Existing Roadway Deficiencies

DRAFT Sellwood Bridge Existing Roadway Deficiencies Technical Memorandum DRAFT Sellwood Bridge Existing Roadway Deficiencies Executive Summary Purpose Roadway design standards are developed to support safety and mobility goals. Roadway deficiencies have

More information

Design of Turn Lane Guidelines

Design of Turn Lane Guidelines Design of Turn Lane Guidelines CTS Transportation Research Conference May 24, 2012 Howard Preston, PE Minnesota Department of Transportation Research Services Office of Policy Analysis, Research & Innovation

More information

City of Edinburg Department of Public Works 415 W. University Dr. Edinburg, TX (956) SPEED HUMPS INSTALLATION POLICY

City of Edinburg Department of Public Works 415 W. University Dr. Edinburg, TX (956) SPEED HUMPS INSTALLATION POLICY City of Edinburg Department of Public Works 415 W. University Dr. Edinburg, TX 78541 (956) 388-8210 SPEED HUMPS INSTALLATION POLICY A. GENERAL Speed humps are an effective and appropriate device for safely

More information

Appendix B Transportation Report

Appendix B Transportation Report Project File Report Appendix B Transportation Report Town of Whitby HMM Project No. 327878 Final Report October 2014 Revision and Version Tracking CP Rail Crossing at New Coronation Road Class EA Study

More information

THE FUTURE OF THE TxDOT ROADWAY DESIGN MANUAL

THE FUTURE OF THE TxDOT ROADWAY DESIGN MANUAL THE FUTURE OF THE TXDOT ROADWAY DESIGN MANUAL Kenneth Mora, P.E. (Design Division) 10/10/2017 Table of contents 1 2 Reduction in FHWA design controlling criteria Innovative Intersection Guidance 3-7 8-42

More information

CITY OF LOMITA CITY COUNCIL REPORT

CITY OF LOMITA CITY COUNCIL REPORT CITY OF LOMITA CITY COUNCIL REPORT TO: FROM: City Council Ryan Smoot, City Manager Item No. SCH 12 PREPARED BY: Mark A. McAvoy, P.E., Public Works Director/City Engineer MEETING DATE: August 1, 2017 SUBJECT:

More information

CROSSING GUARD PLACEMENT CONSIDERATIONS AND GAP ASSESSMENT

CROSSING GUARD PLACEMENT CONSIDERATIONS AND GAP ASSESSMENT CROSSING GUARD PLACEMENT CONSIDERATIONS AND GAP ASSESSMENT Many factors contribute to the need for a Crossing Guard. General federal guidance, provided by the FHWA MUTCD, states that adult crossing guards

More information

4.0 TRAFFIC IMPACT STUDIES

4.0 TRAFFIC IMPACT STUDIES SECTION 4 4.0 TRAFFIC IMPACT STUDIES 4.1 TRAFFIC IMPACT STUDY REQUIREMENTS The City has established Traffic Impact Study (TIS) requirements for the purpose of ensuring that both the quantitative and qualitative

More information

South Albion-Bolton Community Plan North Hill Supermarket Transportation Study Part B: Evaluation of Alternatives

South Albion-Bolton Community Plan North Hill Supermarket Transportation Study Part B: Evaluation of Alternatives Community Plan North Hill Supermarket Transportation Study Part B: Evaluation of Alternatives Prepared for: The Town of Caledon August 9 Transportation Solutions Ltd. 43 Forest Road Cambridge, ON N1S 3B4

More information

Route 28 (South Orleans Road)/Route 39 (Harwich Road)/Quanset Road Intersection

Route 28 (South Orleans Road)/Route 39 (Harwich Road)/Quanset Road Intersection TRAFFIC FEASIBILITY STUDY Route 28 (South Orleans Road)/Route 39 (Harwich Road)/Quanset Road Intersection Orleans, Massachusetts Prepared for: Town of Orleans Prepared by: Fay, Spofford & Thorndike, LLC

More information

ALLEY 24 TRAFFIC STUDY

ALLEY 24 TRAFFIC STUDY ALLEY 24 TRAFFIC STUDY in City of Frostburg, Maryland January 2013 3566 Teays Valley Road Hurricane, WV Office: (304) 397-5508 www.denniscorporation.com Alley 24 Traffic Study January 2013 Frostburg, Maryland

More information

SIGHT DISTANCE GUIDELINES

SIGHT DISTANCE GUIDELINES SIGHT DISTANCE GUIDELINES According to the 2011 AASHTO, 2011 MMUTCD, and Michigan Department of Transportation Guidelines PREPARED BY GEOMETRICS AND OPERATIONS UNIT TRAFFIC AND SAFETY April 22, 2015 Providing

More information

DRAFT TENNYSON STREET ANGLED PARKING ANALYSIS

DRAFT TENNYSON STREET ANGLED PARKING ANALYSIS DRAFT TENNYSON STREET ANGLED PARKING ANALYSIS Prepared for: City and County of Denver Department of Public Works, Engineering Division Traffic Engineering Services Parking Operations 201 W. Colfax Avenue,

More information

Community Transportation Plan

Community Transportation Plan Community Transportation Plan Appendix A: Traffic Calming CITY OF DECATUR COMMUNITY TRANSPORTATION PLAN Appendix A: City of Decatur City-wide Residential Traffic Calming Program Process & Procedures The

More information

INTRODUCTION THOROUGHFARE SYSTEM CLASSIFICATIONS

INTRODUCTION THOROUGHFARE SYSTEM CLASSIFICATIONS INTRODUCTION The thoroughfare plan will assist public officials in the development of a specialized system for efficient and safe movement of vehicular traffic while minimizing potential conflicts with

More information

Residential Traffic Calming Program Guide. Town of Ashland, Virginia

Residential Traffic Calming Program Guide. Town of Ashland, Virginia Residential Traffic Calming Program Guide Town of Ashland, Virginia August 1, 2006 TABLE OF CONTENTS A. INTRODUCTION... 1 B. GOALS... 1 C. CRITERIA... 1 D. IDENTIFYING NEIGHBORHOOD TRAFFIC CONCERNS...

More information

Existing Conditions. Date: April 16 th, Dan Holderness; Coralville City Engineer Scott Larson; Coralville Assistant City Engineer

Existing Conditions. Date: April 16 th, Dan Holderness; Coralville City Engineer Scott Larson; Coralville Assistant City Engineer Date: April 16 th, 2015 To: From: Re: Dan Holderness; Coralville City Engineer Scott Larson; Coralville Assistant City Engineer Darian Nagle-Gamm, Traffic Engineering Planner Highway 6 (2 nd Street) /

More information

BI-DIRECTIONALS FREE-ACCESS

BI-DIRECTIONALS FREE-ACCESS BI-DIRECTIONALS FREE-ACCESS Dimensions may vary depending on design vehicle and turning movements. See GEO-650-Series for addtional details. SPECIAL Special situations, i.e., See Notes 4 & 5 wide streets,

More information

REDEVELOPMENT TRAFFIC IMPACT STUDY

REDEVELOPMENT TRAFFIC IMPACT STUDY REDEVELOPMENT TRAFFIC IMPACT STUDY For Wendy s Parker, Colorado January 215 Prepared for: Sterling Design Associates, LLC 29 W. Littleton Boulevard #3 Littleton, Colorado 812 Prepared by: 1233 Airport

More information

Topic No January 2000 Manual on Uniform Traffic Studies Revised July Chapter 8 GAP STUDY

Topic No January 2000 Manual on Uniform Traffic Studies Revised July Chapter 8 GAP STUDY Chapter 8 8.1 PURPOSE GAP STUDY (1) The Gap Study is used to determine the size and the number of gaps in the vehicular traffic stream for unsignalized intersections and access points, pedestrian studies,

More information

Mont Vernon - NH 13 Access Management Study

Mont Vernon - NH 13 Access Management Study Mont Vernon - NH 13 Access Management Study April 2006 Prepared by the Nashua Regional Planning Commission TABLE OF CONTENTS MONT VERNON - NH 13 ACCESS MANAGEMENT STUDY...1 A. Introduction...1 B. Study

More information

SCHOOL CROSSING PROTECTION CRITERIA

SCHOOL CROSSING PROTECTION CRITERIA CITY OF MADISON TRAFFIC ENGINEERING SCHOOL CROSSING PROTECTION CRITERIA January 2016 Adopted as Policy on August 31, 1976, by Common Council by Amended Resolution #29,540 Amended on September 14, 1976,

More information

Pedestrian Hybrid Beacon Guide Recommendations and Case Study. FHWA Safety Program.

Pedestrian Hybrid Beacon Guide Recommendations and Case Study. FHWA Safety Program. Pedestrian Hybrid Beacon Guide ecommendations and Case Study FHWA Safety Program http://safety.fhwa.dot.gov A pedestrian hybrid beacon (PHB) is a traffic control device similar to a European pedestrian

More information

UNCONTROLLED PEDESTRIAN CROSSING GUIDELINES

UNCONTROLLED PEDESTRIAN CROSSING GUIDELINES City and County of Denver UNCONTROLLED PEDESTRIAN CROSSING GUIDELINES Prepared for: Prepared by: Adopted September 2016 This page is intentionally left blank. Contents for Denver Uncontrolled Pedestrian

More information

Downtown Signals Traffic Analysis

Downtown Signals Traffic Analysis Downtown Signals Traffic Analysis City of St. Mary s April 16, 2018 Presented by: Allan Heitbrink, P.E. & Craig Eley, P.E. Who We Are Craig Eley, P.E o o o Previously the ODOT D7 Traffic and Safety Engineer.

More information

Table 1.0 Grade Crossing Enhancements PVL San Jacinto Branch Line

Table 1.0 Grade Crossing Enhancements PVL San Jacinto Branch Line Grade Crossing Enhancements CPUC 1 2 3 4 5 Citrus Avenue, Riverside County Palmyrita Ave., Columbia Avenue, Marlborough Ave., Spruce St., MP 0.57 002X-0.6 027301Y MP 1.00 002X-1.0 027302F MP 1.24 002X-1.3

More information

Railroad-Highway Grade Crossing Analysis for Corridor Planning Projects

Railroad-Highway Grade Crossing Analysis for Corridor Planning Projects Railroad-Highway Grade Crossing Analysis for Corridor Planning Projects Word Count: 4,305 Submission Date: August 1, 2015 Author: Adriana Rodriguez, E.I Assistant Engineer Parsons Brinckerhoff 1420 South

More information

Chapter 4 On-Road Bikeways

Chapter 4 On-Road Bikeways Chapter 4: 4-1.0 Introduction On-Road Bikeways This chapter provides guidelines to help select and design safe on-road bikeways. On-road bikeways include bicycle lanes, shared lanes, shoulders, and wide

More information

VDOT Crash Analysis Procedures for Roadway Safety Assessments

VDOT Crash Analysis Procedures for Roadway Safety Assessments Crash analysis is a critical component of road safety analysis. The crash analysis procedures defined in this document will help: Identify where to target resources for detailed crash analysis Assess the

More information

APPENDIX D Traffic Impact Study (Draft Report)

APPENDIX D Traffic Impact Study (Draft Report) ENVIRONMENTAL IMPACT ASSESSMENT (EIA) REGISTRATION, TRAFFIC IMPACT STUDY (DRAFT REPORT), AND WATER SUPPLY SOURCE ASSESSMENT (WSSA): CAMPING PLAGE ABOITEAU BEACH, CAP-PELÉ, NB APPENDIX D (Draft Report)

More information

Clyde Brown Elementary School Millis, MA

Clyde Brown Elementary School Millis, MA Clyde Brown Elementary School Millis, MA Transportation Assessment August 8, 2017 Prepared for: Tappe Architects Six Edgerly Place Boston, MA 02116 Submitted by: Nitsch Engineering 2 Center Plaza, Suite

More information

Traffic Impact Study. Roderick Place Columbia Pike Thompson s Station, TN. Transportation Group, LLC Traffic Engineering and Planning

Traffic Impact Study. Roderick Place Columbia Pike Thompson s Station, TN. Transportation Group, LLC Traffic Engineering and Planning F i s c h b a c h Transportation Group, LLC Traffic Engineering and Planning Traffic Impact Study Roderick Place Columbia Pike Thompson s Station, TN Prepared March 2016 Ms. Gillian L. Fischbach, P.E.,

More information

Duwamish Way-finding and CTR Report

Duwamish Way-finding and CTR Report V. North Tukwila When the North Tukwila Manufacturing and Industrial Center was designated in 1992 as part of the region s land use and transportation plan, the plan called for the area to set a light-rail

More information

APPENDIX E GRADE CROSSING LOCATIONS

APPENDIX E GRADE CROSSING LOCATIONS APPENDIX E GRADE CROSSING LOCATIONS 1 2 3 Citrus Avenue Riverside County and City Palmyrita Avenue Columbia Avenue MP 0.57 002X-0.6 027301Y MP 1.00 002X-1.0 027302F MP 1.24 002X-1.3 027303M 1. Existing

More information

Memorandum 1. INTRODUCTION. To: Cc: From: Denise Marshall Northumberland County

Memorandum 1. INTRODUCTION. To: Cc: From: Denise Marshall Northumberland County 255 Adelaide Street West Toronto, ON M5H 1X9 www.hdrinc.com File: 4.0 Memorandum To: Cc: From: Denise Marshall Northumberland County Tony Reitmeier HDR Guinevere Ngau HDR Andrew O Connor HDR Date: August

More information

SCHOOL ROUTE PLAN. For HUNTER S CREEK ELEMENTARY SCHOOL LOCATION 14 ORANGE COUNTY. Prepared for:

SCHOOL ROUTE PLAN. For HUNTER S CREEK ELEMENTARY SCHOOL LOCATION 14 ORANGE COUNTY. Prepared for: SCHOOL ROUTE PLAN For HUNTER S CREEK ELEMENTARY SCHOOL LOCATION 14 ORANGE COUNTY Prepared for: ORANGE COUNTY SCHOOL ASSESSMENT PROGRAM ORANGE COUNTY PUBLIC WORKS Traffic Engineering Division 42 South John

More information

CHAPTER 7 STREET DESIGN AND TECHNICAL CRITERIA TABLE OF CONTENTS

CHAPTER 7 STREET DESIGN AND TECHNICAL CRITERIA TABLE OF CONTENTS CHAPTER 7 STREET DESIGN AND TECHNICAL CRITERIA TABLE OF CONTENTS Section Title Page 7.1 General... 7-1 7.1.1 Conforming to Standards and Master Plans... 7-1 7.1.2 Construction Drawings Relating to Chapter

More information

Issues Relating to the Geometric Design of Intersections Vergil G. Stover

Issues Relating to the Geometric Design of Intersections Vergil G. Stover Introduction Issues Relating to the Geometric Design of Intersections Vergil G. Stover This paper presents five issues, or topics, that the author suggests be addressed in the design of intersections.

More information

01. VICINITY OF GREENBRAE POC: EXISTING CONDITIONS

01. VICINITY OF GREENBRAE POC: EXISTING CONDITIONS 01. VICINITY OF GREENBRAE POC: EXISTING CONDITIONS Existing Bus Stop Existing US101 On-ramp Existing POC Old Redwood Highway Rich Street City ROW Environmental Study Limit Industrial Way NO DESIGNATED

More information

CITY OF SASKATOON COUNCIL POLICY

CITY OF SASKATOON COUNCIL POLICY ORIGIN/AUTHORITY Clause 1, Report No. 1-1980 and Clause 4, Report No. 22-1990 of the Works and Utilities Committee; Clause 6, Report No. 17-2004 of the Planning and Operations Committee; and Clause D5,

More information

URBAN QUARRY HEADQUARTERS 2717 STEVENAGE DRIVE CITY OF OTTAWA TRANSPORTATION OVERVIEW. Prepared for: Urban Quarry 4123 Belgreen Drive, Ottawa K1G 3N2

URBAN QUARRY HEADQUARTERS 2717 STEVENAGE DRIVE CITY OF OTTAWA TRANSPORTATION OVERVIEW. Prepared for: Urban Quarry 4123 Belgreen Drive, Ottawa K1G 3N2 URBAN QUARRY HEADQUARTERS 2717 STEVENAGE DRIVE CITY OF OTTAWA TRANSPORTATION OVERVIEW Prepared for: Urban Quarry 4123 Belgreen Drive, Ottawa K1G 3N2 February 27, 2014 113-584 Overview_1.doc D. J. Halpenny

More information

THE LANDMARK AT TALBOT PARK

THE LANDMARK AT TALBOT PARK TRAFFIC IMPACT STUDY FOR THE LANDMARK AT TALBOT PARK IN NORFOLK, VA INTERMODAL ENGINEERING, P.C. OCTOBER, 200 The Landmark at Talbot Park is a proposed redevelopment of the existing apartments along the

More information

CHAPTER 1 STANDARD PRACTICES

CHAPTER 1 STANDARD PRACTICES CHAPTER 1 STANDARD PRACTICES OBJECTIVES 1) Functions and Limitations 2) Standardization of Application 3) Materials 4) Colors 5) Widths and Patterns of Longitudinal Pavement Marking Lines 6) General Principles

More information

SECTION 1 - TRAFFIC PLANNING

SECTION 1 - TRAFFIC PLANNING SECTION 1 - TRAFFIC PLANNING 1.1 TRAFFIC OPERATIONS 1.1.1 Roadway Functional Classification The Multnomah County Comprehensive Framework Plan s Policy 34: Trafficways and the Functional Classification

More information

Regulations and Standards to Enhance Traffic Safety and Mobility in Powhatan County, VA

Regulations and Standards to Enhance Traffic Safety and Mobility in Powhatan County, VA Regulations and Standards to Enhance Traffic Safety and Mobility in Powhatan County, VA November 9, 2000 Richmond Regional Planning District Commission 2104 West Laburnum Avenue, Suite 101 Richmond, Virginia

More information

3.0 ACCESS CONTROL PLAN - HARMONY ROAD (SH68)

3.0 ACCESS CONTROL PLAN - HARMONY ROAD (SH68) 3.0 ACCESS CONTROL PLAN - HARMONY ROAD (SH68) 3.1 Existing Conditions Roadway Physical Characteristics Typical Section The existing typical cross-section for SH68 is shown on Figure 3-1 and is comprised

More information

Roundabouts Near At-Grade Railroad Crossings

Roundabouts Near At-Grade Railroad Crossings Roundabouts Near At-Grade Railroad Crossings May 12, 2008 1,592 Words Alex J. Ariniello LSC Transportation Consultants, Inc., 1889 York Street Denver, CO 80206 Phone: 303-333-1105 FAX: 303-333-1107 email:

More information

Traffic Impact Study Flathead County Rail Park Kalispell, Montana DRAFT. Prepared for Flathead County Economic Development Association

Traffic Impact Study Flathead County Rail Park Kalispell, Montana DRAFT. Prepared for Flathead County Economic Development Association Flathead County Rail Park Kalispell, Montana DRFT Prepared for Flathead County Economic Development ssociation Prepared by KLJ May 2013 KLJ Project # 15413003 CERTIFICTION I hereby certify that this traffic

More information

Intersec ons. Alignment. Chapter 3 Design Elements. Standards AASHTO & PennDOT: As close to 90 as possible, but a minimum of 60.

Intersec ons. Alignment. Chapter 3 Design Elements. Standards AASHTO & PennDOT: As close to 90 as possible, but a minimum of 60. Intersec ons Intersec ons pertains to mul ple design elements concerning intersec- ons, including: alignment, channeliza on, grades, off set, radii, sight distance, signaliza on, spacing, and traffic control

More information

Northbound San Jose Avenue & I-280 Off-Ramp Road Diet Pilot Project

Northbound San Jose Avenue & I-280 Off-Ramp Road Diet Pilot Project Project Overview Fed by a two-lane Interstate-280 (I-280) off-ramp, high vehicular volumes and speeds are longstanding issues along San Jose Avenue. Residents in the surrounding neighborhoods have expressed

More information

TRAFFIC IMPACT STUDY CANYON HILLS PROJECT LOS ANGELES, CALIFORNIA INTRODUCTION This traffic analysis has been conducted to identify and evaluate the potential traffic impacts of the proposed Canyon Hills

More information

ORLEANS GARDENS SHOPPING CENTRE 1615 ORLEANS BOULEVARD CITY OF OTTAWA, ONTARIO TRANSPORTATION IMPACT STUDY. Prepared for:

ORLEANS GARDENS SHOPPING CENTRE 1615 ORLEANS BOULEVARD CITY OF OTTAWA, ONTARIO TRANSPORTATION IMPACT STUDY. Prepared for: ORLEANS GARDENS SHOPPING CENTRE 1615 ORLEANS BOULEVARD CITY OF OTTAWA, ONTARIO TRANSPORTATION IMPACT STUDY Prepared for: Orleans Gardens Shopping Centre Inc. 2851 John Street, Suite 1 Markham, ON K3R 5R7

More information

TRAFFIC IMPACT STUDY. Creekside Thornton, Colorado. For. August 2015 November 2015 Revised: August Prepared for:

TRAFFIC IMPACT STUDY. Creekside Thornton, Colorado. For. August 2015 November 2015 Revised: August Prepared for: TRAFFIC IMPACT STUDY For Creekside Thornton, Colorado August 215 November 215 Revised: August 216 Prepared for: Jansen Strawn Consulting Engineers 45 West 2 nd Avenue Denver, Colorado 8223 Prepared by:

More information

INTERSECTIONS AT GRADE INTERSECTIONS

INTERSECTIONS AT GRADE INTERSECTIONS INTERSECTIONS 1 AT GRADE INTERSECTIONS INTERSECTIONS INTERSECTIONS = INTERRUPTED FACILITIES Definitions and key elements An intersection is defined as an area where two or more roadways join or cross.

More information

ROUNDABOUTS. Improving Safety and Efficiency. SR83 & Smithville Western Rd. Joel Montgomery, PE Director of Administration

ROUNDABOUTS. Improving Safety and Efficiency. SR83 & Smithville Western Rd. Joel Montgomery, PE Director of Administration ROUNDABOUTS Improving Safety and Efficiency SR83 & Smithville Western Rd. Joel Montgomery, PE Director of Administration The Ohio Department of Transportation District 3 906 North Clark Ave. Ashland, OH

More information

PROJECT NO. 093 MA 199 H C. FEDERAL NO. xxxx WIKIEUP-WICKENBURG-PHOENIX HIGHWAY TEGNER STREET, ALTERNATIVE 10 PROJECT IMPROVEMENT

PROJECT NO. 093 MA 199 H C. FEDERAL NO. xxxx WIKIEUP-WICKENBURG-PHOENIX HIGHWAY TEGNER STREET, ALTERNATIVE 10 PROJECT IMPROVEMENT PROJECT NO. 093 MA 199 H 5807 01C FEDERAL NO. xxxx WIKIEUP-WICKENBURG-PHOENI HIGHWAY TEGNER STREET, ALTERNATIVE 10 PROJECT IMPROVEMENT (INTERSECTION IMPROVEMENT) US 93/US 60 FINAL PROJECT ASSESSMENT April

More information

Access Management Regulations and Standards

Access Management Regulations and Standards Access Management Regulations and Standards Efficient highway operation Reasonable property access Concept of Access Management The way to manage access to land development while simultaneously preserving

More information

Colerain Avenue Roadway Improvements. Sponsored by Hamilton County Engineer

Colerain Avenue Roadway Improvements. Sponsored by Hamilton County Engineer Colerain Avenue Roadway Improvements Sponsored by Hamilton County Engineer Participants Lead Agency: Hamilton County Engineer Review and Approval: Ohio Department of Transportation Design Engineer: Edwards

More information

5. Requiring cross access between development parcels. This section shall apply to the following:

5. Requiring cross access between development parcels. This section shall apply to the following: CHAPTER 900. SECTION 901. DEVELOPMENT STANDARDS TRANSPORTATION 901.3. Access Management A. Intent and Purpose The intent and purpose of access management is to provide safe access to land development while

More information

LIST OF FIGURES Figure Title

LIST OF FIGURES Figure Title TABLE OF CONTENTS Table of Contents... 1 List of Figures... 2 44-1A Critical Length of Grade for Trucks... 3 44-1B Critical Length of Grade for Recreational Vehicles... 3 44-1C Measurement for Length of

More information

JUNE, 2000 ROAD DESIGN MANUAL 5-0(1) CHAPTER 5 AT-GRADE INTERSECTIONS

JUNE, 2000 ROAD DESIGN MANUAL 5-0(1) CHAPTER 5 AT-GRADE INTERSECTIONS JUNE, 2000 ROAD DESIGN MANUAL 5-0(1) CHAPTER 5 AT-GRADE INTERSECTIONS 5-1.0 INTRODUCTION 5-1.01 Definition 5-1.02 Policy 5-1.03 Design Considerations 5-1.04 Vehicle Characteristics 5-1.04.01 Turning Radii

More information

PENNDOT HPMS DATA COLLECTION GUIDE

PENNDOT HPMS DATA COLLECTION GUIDE PENNDOT HPMS DATA COLLECTION GUIDE Bureau of Planning and Research April 2016 (Updated September 2017) State Street Dauphin County INTRODUCTION The purpose of this document is to provide you with some

More information

THE INSTALLATION OF PRE-SIGNALS AT RAILROAD GRADE CROSSINGS

THE INSTALLATION OF PRE-SIGNALS AT RAILROAD GRADE CROSSINGS THE INSTALLATION OF PRE-SIGNALS AT RAILROAD GRADE CROSSINGS Lisa D. Sherman, Kenneth J. Petraglia, P.E. INTRODUCTION Each signalized intersection adjacent to a highway-rail grade crossing presents the

More information

Roundabout Feasibility Memorandum

Roundabout Feasibility Memorandum Roundabout Feasibility Memorandum To From Gwen Pipkin Bill Howell Date June 18, 2013 Subject Roundabout Feasibility Study SR 29 PD&E Study From Oil Well Road to SR 82 Collier County, FL FPID 417540-1-22-01

More information

Prepared for Lutheran Services Carolinas. Project Number: /07/2017. Trinity Landing. New Hanover County, NC

Prepared for Lutheran Services Carolinas. Project Number: /07/2017. Trinity Landing. New Hanover County, NC Prepared for Lutheran Services Carolinas Project Number: 16273 4/7/217 Trinity Landing New Hanover County, NC Trinity Landing Transportation Impact nalysis Prepared for Lutheran Services Carolinas New

More information

Chapter 5 Shared-Use Paths

Chapter 5 Shared-Use Paths Chapter 5: 5-1.0 Introduction Shared-Use Paths This chapter provides guidelines for design of bicycle transportation facilities that are separated from the roadway. In most cases, a path separated from

More information

Lawrence Loop SWOT Analysis

Lawrence Loop SWOT Analysis Alignment: A1 (Map Color: Red) Description: This alignment connects to the Sandra Shaw Trail on the north side of the pond and heads north through undeveloped property and then west to Michigan Street

More information

Multifamily Development on Preston Road at Northwest Highway in Dallas, Texas

Multifamily Development on Preston Road at Northwest Highway in Dallas, Texas Traffic Impact Analysis Multifamily Development on Preston Road at Northwest Highway in Dallas, Texas Prepared by: Kimley-Hom and Associates, Inc. Dallas, Texas April 25, 2014 KHA # 064469600 Traffic Impact

More information

Introduction Additional Safe Routes to School Resources Main Street Elementary School Survey Results Field Audit...

Introduction Additional Safe Routes to School Resources Main Street Elementary School Survey Results Field Audit... Contents Introduction... 2 Additional Safe Routes to School Resources... 2... 3 Survey Results... 4 Field Audit... 6 Proposed Safe Routes to School Elements... 9 Typical Safe Routes to School Summary...

More information

A Comprehensive HCM 2010 Urban Streets Analysis Using HCS 2010 US 31W in Elizabethtown, KY

A Comprehensive HCM 2010 Urban Streets Analysis Using HCS 2010 US 31W in Elizabethtown, KY A Comprehensive HCM 2010 Urban Streets Analysis Using HCS 2010 US 31W in Elizabethtown, KY Ashley McLain, PE, PTOE Abstract The HCS 2010 Streets module was used to analyze a segment of the US 31W corridor

More information

APPENDIX F. Access Management Design Standards for Entrances and Intersections

APPENDIX F. Access Management Design Standards for Entrances and Intersections APPENDIX F Access Management Design Standards for Entrances and Intersections PREFACE The access management regulations and standards do not apply in cities, towns of more than 3,500 and in counties (Henrico

More information

Harrah s Station Square Casino

Harrah s Station Square Casino Transportation Analysis Harrah s Station Square Casino Pittsburgh, Pennsylvania Submitted To: City of Pittsburgh and Pennsylvania Gaming Control Board Prepared By: DKS Associates GAI Consultants December

More information

Off-Road Facilities Part 1: Shared Use Path Design

Off-Road Facilities Part 1: Shared Use Path Design Off-Road Facilities Part 1: Shared Use Path Design Presentation by: Eric Mongelli, P.E. Tom Huber October 9, 2012 FOLLOW THE CONVERSATION ON TWITTER Toole Design Group is live tweeting this webinar @tooledesign

More information

444 North Capitol Street NW, Suite 249, Washington, DC (202) Fax: (202) ERRATA

444 North Capitol Street NW, Suite 249, Washington, DC (202) Fax: (202) ERRATA Larry L. Butch Brown, Sr., President Executive Director, Mississippi Department of Transportation John Horsley, Executive Director 444 North Capitol Street NW, Suite 249, Washington, DC 20001 (202) 624-5800

More information

MEMORANDUM. Earl Haugen and UND Transportation and Traffic Coordination Committee

MEMORANDUM. Earl Haugen and UND Transportation and Traffic Coordination Committee SRF No. 7766 MEMORANDUM TO: FROM: Earl Haugen and UND Transportation and Traffic Coordination Committee Rick Lane, P.E. DATE: November 26, 2013 SUBJECT: UNIVERSITY AVE REVIEW Our review of the University

More information

Introduction to Transportation Engineering. Discussion of Stopping and Passing Distances

Introduction to Transportation Engineering. Discussion of Stopping and Passing Distances Introduction to Transportation Engineering Discussion of Stopping and Passing Distances Dr. Antonio A. Trani Professor of Civil and Environmental Engineering Virginia Polytechnic Institute and State University

More information

Access Management Considerations for High Capacity Multi-Lane Roundabout Design and Implementation

Access Management Considerations for High Capacity Multi-Lane Roundabout Design and Implementation Access Management Considerations for High Capacity Multi-Lane Roundabout Design and Implementation Prepared By Mark T. Johnson, PE MTJ Engineering, LLC 313 Price Place, #205 Madison, WI 53705 www.mtjengineering.com

More information

Sharing the Road. with Pedestrians Edition. A guide for drivers and pedestrians published by the Arizona Department of Transportation

Sharing the Road. with Pedestrians Edition. A guide for drivers and pedestrians published by the Arizona Department of Transportation Sharing the Road with Pedestrians 2017 Edition A guide for drivers and pedestrians published by the Arizona Department of Transportation Sponsored by Tips for Sharing the Road Legally and Safely This pocket

More information

Roadway Geometric Design I: Functions, Controls and Alignments

Roadway Geometric Design I: Functions, Controls and Alignments : Functions, Controls and Alignments Course No: C05-023 Credit: 5 PDH Gregory J. Taylor, P.E. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980 P: (877) 322-5800 F:

More information

TABLE OF CONTENTS TABLE OF CONTENTS... I APPENDICES... III LIST OF EXHIBITS... V LIST OF TABLES... VII LIST OF ABBREVIATED TERMS...

TABLE OF CONTENTS TABLE OF CONTENTS... I APPENDICES... III LIST OF EXHIBITS... V LIST OF TABLES... VII LIST OF ABBREVIATED TERMS... TABLE OF CONTENTS TABLE OF CONTENTS... I APPENDICES... III LIST OF EXHIBITS... V LIST OF TABLES... VII LIST OF ABBREVIATED TERMS... IX 1 INTRODUCTION... 1 1.1 Project Overview... 1 1.2 Analysis Scenarios...

More information

ATTACHMENT NO. 11. RRLRT No. 2. Railroad / Light Rail Transit Technical Committee TECHNICAL COMMITTEE: Busway Grade Crossings STATUS/DATE OF ACTION

ATTACHMENT NO. 11. RRLRT No. 2. Railroad / Light Rail Transit Technical Committee TECHNICAL COMMITTEE: Busway Grade Crossings STATUS/DATE OF ACTION ATTACHMENT NO. 11 RRLRT No. 2 TECHNICAL COMMITTEE: TOPIC: Railroad / Light Rail Transit Technical Committee Busway Grade Crossings STATUS/DATE OF ACTION RRLRT TC Draft: 06/23/2011 RRLRT TC Approval: 06/27/2014

More information

Right and Left Turn Lane Warrants

Right and Left Turn Lane Warrants Right and Left Turn Lane Warrants TRS 1406 Published April 2014 Introduction The genesis of this project stems from a perception by city and county engineers that there is a lack of guidance relative to

More information

Traffic Circulation & Pedestrian Safety Study

Traffic Circulation & Pedestrian Safety Study Lyons Township High School North Campus La Grange, Illinois Parking Lot Vaughan Building N Main Building Prepared for: Prepared by: July 23, 2015 Contents List of Figures, iii 1. Introduction...1 2. Existing

More information