1 Boise Whitewater Park Ph II Public Information Meeting 11/2/2016 Presented by: John Tensen P.E., City Engineer Morton McMillen, P.E., McMillen Jacobs Scott Shipley, P.E., S2O Design Walker Christensen- DHM Design Thomas Governale, Parks Superintendent
2 Presentation Topics Introductions Esther Simplot Park/Boise Whitewater Park Phase IIA Update - John Tensen Boise Whitewater Park Phase IIB Concept Plan Whitewater Park Complex Anticipated Use Tom Governale/Scott Shipley ESP/Whitewater Park/Management Concepts Thomas Governale Major Events Use monitoring Comments Boise Whitewater Park Phase IIB Next Steps/ Construction Schedule/ Approach - Mort McMillen
3 Overall Project Configuration (McMillen Jacobs 2014) Two Projects ESP Whitewater Park Ph 2 Project Goals Irrigation Delivery (FUDC/BVID) Flood Mitigation River Safety Recreation Active Passive Greenbelt Functionality Habitat Improvement
4 Esther Simplot Park Funding J.R. Simplot Foundation Design Builder- McMillen Jacobs Park Opened November 2, 2016 Cost > $16M
5 Whitewater Park Ph IIA Farmers Union Intake Structure Highlights McMillen Jacobs Design- Build Contract with Boise City Construction: October 2015 thru February high x 26 wide x 380 long Concrete Box Culvert Funding City of Boise: Approx. $1.8M
6 Whitewater Park Ph IIA Farmers Union Intake Structure
7 Boise Whitewater Park Phase IIB Concept Plan
8 Whitewater Park Phase IIB Design and Construction Highlights McMillen Jacobs Design-Builder S2O Design DHM Design Phase IIB General Information Funding City of Boise and Albertsons Foundation Estimated Cost $7.0M Design and Permitting May 2016 thru Sept 2017 Construction October 2017 thru May 2019 (two nonirrigation seasons)
9 Boise Whitewater Park Phase IIB Overall Project Configuration Reach 1 Reach 2 Reach 3 Whitewater Park Phase II ESP
10 Whitewater Park Complex Expected Use Whitewater Park Programming/Use Concepts Phase I (Thurman Mill) targeted for surfers and experienced kayakers. Can be adjusted for various river flows/use Phase II Reach 1 and 3 Kayakers, Canoeists and SUPs Phase II (Drop Structures) Targeted for all levels of kayakers and SUPs Drop Structure 1- Intermediate/Expert Kayaker. Seasonally adjustable for flows/use Drop Structures 2&3 Novice/Intermediate Kayakers/SUPs Drop Structure 1 use will be monitored over time and adjusted accordingly
11 Draft Programming Schedule
12 Boise Whitewater Park Phase IIB Overall Project Configuration Reach 1 Reach 2 Reach 3 Whitewater Park Phase II ESP
13 Reach 1 Features Wading Area
14 Reach 1 Features
15 Reach 2 Updated Concept Plan
16 Reach 2 Updated Concept Plan River Bank Restoration/Spectator Seating
17 Reach 2 Updated Concept Plan Drop Structure 1
18 Reach 2 Updated Concept Plan Drop Structure 1
19 Reach 2 Updated Concept Plan Drop Structure 1
20
21
22 Reach 2 Updated Concept Plan Drop Structures 2 and 3
23 Hawea NZ
24
25
26
27
28
29
30
31
32
33 Whitewater Park Programming/ Management Concepts General Whitewater Park Access from Boise City Side of River Maintain HOA Privacy Parking Concerns Conservation Easement Compliance Major Events Require Permits Access control Parking Traffic management/shuttle service Trash cleanup Security Insurance/Bonding
34 Next Steps Meet with Stakeholders, Confirm Concept Plan Waterfront HOA Committee (every month) General Public 11/02/16 Permit Agencies (kickoff week of 11/14/16) Farmers Union Ditch Company (monthly) Develop 60% Plans Garden City Approval Waterfront HOA Easement Right-of-Way Agreement Permits (404, Boise River Permit) FUDC Approval
35 Construction Schedule/Approach Reach 1 Reach 2 Reach 3 Whitewater Park Phase II ESP Reaches 2 and 3: Start Construction October 2017 Divert river into canal Remove debris from FUDC and place in Veterans Pond for greenbelt Construct drop structures and bank improvements Be out of river by end of February Feb.-Sept. Complete upland improvements (greenbelt, bank improvements, landscaping)
36 Construction Schedule/Approach Reach 1 Reach 2 Reach 3 Whitewater Park Phase II ESP Reach 1: Start Construction October 2018 (could be Feb if river conditions favorable) Be out of river by end of February 2019 at latest
37 Construction Schedule/Approach Normal Work Hours 7 a.m. to 7 p.m. Access from Boise City Side of River (except Reach 1) Lighting Control Fish Salvage Greenbelt Closure
38 Boise Whitewater Park Phase IIB Comments? Comment Cards Questions? Concerns? Concurrence?
J.A. and Kathryn Albertson Family Foundation Boise Whitewater Park Ph II User Group Meeting 01/23/2018 Presented by: John Tensen P.E.
J.A. and Kathryn Albertson Family Foundation Boise Whitewater Park Ph II User Group Meeting 01/23/2018 Presented by: John Tensen P.E., Project Manager Kelly Burrows, Development Coordinator Morton McMillen,
More informationJAP Additional Information Sheet
JAP Additional Information Sheet Block 15: Purpose and Need The USACE purpose of the project is to provide a safe and reliable whitewater park for the recreational public in a city park, which will provide
More informationJ.A. and Kathryn Albertson Family Foundation Boise Whitewater Park Phase II Final Environmental Review Figure 5. Temporary Construction Measures McMil
J.A. and Kathryn Albertson Family Foundation Boise Whitewater Park Phase II Final Environmental Review Figure 5. emporary Construction Measures McMillen Jacobs Associates 10 November 22, 2017 LOCAION MAP
More informationINTERSECTION IMPROVEMENTS
MCHENRY COUNTY DIVISION OF TRANSPORTATION SEPTEMBER 2012 RIVER ROAD AT DOWELL ROAD INTERSECTION IMPROVEMENTS INSIDE: Public Meeting #1 Summary 1 Public Meeting #2 Summary 1 Key Issues Raised at Public
More informationInspection Modifications Recommend increasing the culvert size to a 48" squashed pipe. Discussion Board Decision
4:00 310 Business Agenda: MEETING CALLED TO ORDER: THOSE PRESENT: GUESTS: 310 INSPECTION REPORTS ~ READY FOR DECISION: Inspection Date 8 /13/2014 Application GD-036-14 Applicant River Landing, LLC Landowner
More informationTOWN OF PALM BEACH FOR IMMEDIATE RELEASE. Patricia Strayer, P.E., Town Engineer Phone: ,
TOWN OF PALM BEACH DATE: November 9, 2018 FOR IMMEDIATE RELEASE MEDIA CONTACT: Patricia Strayer, P.E., Town Engineer Phone: 561-838-5440, Email: pstrayer@townofpalmbeach.com Construction & Traffic Highlights
More informationPurple Line Extension Community Meeting
Purple Line Extension Community Meeting August 22, 2016 Agenda Introductions Meeting Goals Project Overview and Schedules Proposed Memorandum of Agreement Overview Stay in Touch! Q & A Meeting Goals Provide
More informationWelcome to the Open House
Leslie Street Between 19 th Avenue and Stouffville Road Addendum to Class Environmental Assessment Study Welcome to the Open House Please sign in at the front desk. March 28, 2017 Richmond Green Sports
More informationCurrent Travel Needs and Operating Conditions (See pages 4 9 of the Discussion Guide)
Phase 1 Consultation: Understanding the Need Feedback Form Thank you for participating in this phase of planning for the George Massey Tunnel Replacement. Your feedback is important to us. Input received
More informationwww.missouriwhitewater.org MISSION Encourage the growth of paddling as a recreational sport Teach paddling skills, river safety, first aid, outfitting and conservation Encourage the development of state-of-the-art
More informationKootenai River Habitat Restoration Program. Kootenai Tribe of Idaho - January 27, 2014 Presentation for Kootenai Valley Resource Initiative
Kootenai River Habitat Restoration Program Kootenai Tribe of Idaho - January 27, 2014 Presentation for Kootenai Valley Resource Initiative Decline of native species Kootenai River White Sturgeon ENDANGERED
More informationUnless otherwise noted, images throughout the presentation are by FWC.
This presentation provides a summary of a series of proposed final rules intended to address management of the shore-based shark fishery and shark-related cleanup of existing Florida Fish and Wildlife
More informationCFH Boise City Parks and Recreation
CFH13-00029 Boise City Parks and Recreation Summary The Parks and Recreation Department requests approval of a Boise River System Permit for the repair of ±200 feet of river bank generally located at 5845
More informationTraffic and Flood Control Improvements in the Transit Oriented Development District Project Updates Tuesday, November 29, 2016 Meriden Public Library
Traffic and Flood Control Improvements in the Transit Oriented Development District Project Updates Tuesday, November 29, 2016 Meriden Public Library Presentation Format Project Goals and Overview Sidewalk
More informationENERGY SECTOR COORDINATION
ENERGY SECTOR COORDINATION Darin Kosmak, Deputy Director TxDOT Rail Division November 4, 2013 Energy Sector Considerations Existing FM roads not built to handle truck traffic resulting from: Oil & natural
More informationCreston Golf Club Development Plan
Creston Golf Club Development Plan Completed by Creston Golf Club Development Committee 2018 Document Acceptance/Sign-off: President: Don Vaillancourt Vice President: Tim Park Signature: Signature: Table
More informationMeeting Date 10/18/2005 Type Internal Team Progress Other Date of Issuance 10/25/05. Coordination See attached sign-in sheet
Meeting Date 10/18/2005 Type Internal Team Progress Other Date of Issuance 10/25/05 Coordination Attendees See attached sign-in sheet Location Great Hall, Holland Tunnel Route 139 Contract 2 PANYNJ Coordination
More informationTechnical Advisory Committee (TAC)
Technical Advisory Committee (TAC) January 17, 2018 CareerSource Heartland Sebring, FL 1) ROLL CALL 2) PUBLIC COMMENT 3) APPROVAL OF MINUTES* October 18, 2017 Meeting 4) SR 710 Extension in Okeechobee
More informationSC 41/Joe Rouse Intersection Improvements
SC 41/Joe Rouse Intersection Improvements Scope: Add dual left-turn lanes from Joe Rouse Road onto southbound SC 41 to reduce re-occurring peak hour congestion, particularly the AM peak. Construction Cost
More informationTonight is for you. Learn everything you can. Share all your ideas.
Strathcona Neighbourhood Renewal Draft Concept Design Tonight is for you. Learn everything you can. Share all your ideas. What is Neighbourhood Renewal? Creating a design with you for your neighbourhood.
More informationTempe Streetcar Public Meeting
Tempe Streetcar Public Meeting April 19, 2017 Agenda Project Background and Status Design Progress Streetcar Stops Art Program Streetcar Vehicles Mill Avenue Configuration Utility Relocation 2 Route and
More informationConceptual Design Report for the Fabri Dam Modifications Project
Conceptual Design Report for the Fabri Dam Modifications Project Flint, Michigan Prepared For: City of Flint P.O. Box 99 Flint, MI 48501-0099 Flint River Watershed Coalition 432 N. Saginaw St. Suite 1001
More informationINGHAM COUNTY ROAD DEPARTMENT AUSTIN E. CAVANAUGH ADMINISTRATION BUILDING 301 Bush Street, P.O. Box 38, Mason, MI
INGHAM COUNTY ROAD DEPARTMENT AUSTIN E. CAVANAUGH ADMINISTRATION BUILDING 301 Bush Street, P.O. Box 38, Mason, MI 48854-0038 March 27, 2018 William M. Conklin, P.E. Managing Director FOR IMMEDIATE RELEASE:
More information122 Avenue: 107 Street to Fort Road
: 107 Street to Fort Road November 24, 2015 4:30 8:00 p.m. Meeting Purpose Summarize project work completed to date Share results of public input from Phase 1 Share the draft concept plan and proposed
More information2015 Data review. Capturing Ready Lane NEXUS vehicles
2015 Data review Capturing Ready Lane NEXUS vehicles Problem: NEXUS users make up the majority of traffic using the Ready Lane, but they are currently considered either standard traffic or Ready Lane traffic.
More informationGraeme Wilson Vice President, Whitewater NZ & Vice President, Whitewater Canoe Club
Graeme Wilson Vice President, Whitewater NZ & Vice President, Whitewater Canoe Club May 2011 Formerly NZ Recreational Canoeing Association National body for kayaking and canoeing Principal activities are
More informationBAYOU BYLINE. Calendar of Events. November Kent Rogers will do a power point presentation on the I-49 Route thru Allendale, from I-20 to I-220.
Bayou Chapter, Ozark Society Thursday, November 16, 2017 BAYOU BYLINE Calendar of Events November 2017 November 21 Monthly Meeting - Speaker: Kent Rogers, who is the head of the Northwest Louisiana Council
More informationDEPARTMENT OF ENVIRONMENTAL PROTECTION Office of Oil and Gas Management
DEPARTMENT OF ENVIRONMENTAL PROTECTION Office of Oil and Gas Management DOCUMENT NUMBER: 800-0810-003 TITLE: EFFECTIVE DATE: AUTHORITY: POLICY: PURPOSE: APPLICABILITY: DISCLAIMER: Guidelines for Development
More informationDelaware Basin Stream Management Program
Delaware Basin Stream Management Program A partnership between NYCDEP and Delaware County Soil & Water Conservation District 2015 Update Delaware Basin - Topics 2015 Project Updates Restoration Projects
More informationWelcome to the Sellwood Bridge Project Open House!
Welcome to the Sellwood Bridge Project Open House! 5:30 7:30 pm Please sign in here Information stations and project staff are located throughout the room. Goals for Tonight s Meeting: Learn how the Preferred
More informationTABLE OF CONTENTS LEGAL NOTICE
Surface Impoundments Page No. i TABLE OF CONTENTS 1. INTRODUCTION... 1 2. PROPOSED CCR IMPOUNDMENT CLOSURE PROCEDURE... 3 3. PROPOSED COVER SYSTEM... 4 4. ESTIMATED MAXIMUM INVENTORY OF CCR... 4 5. ESTIMATED
More informationTABLE OF CONTENTS LEGAL NOTICE
Closure Plan for Existing CCR Revision: 1 Surface Impoundments Page No. i TABLE OF CONTENTS 1. INTRODUCTION... 1 2. PROPOSED CCR IMPOUNDMENT CLOSURE PROCEDURE... 3 3. PROPOSED COVER SYSTEM... 4 4. ESTIMATED
More informationProject Overview. Rolling Road Widening Fairfax County. Get Involved. Design Public Hearing. Contact Information
Get Involved VDOT representatives will review and evaluate information received as a result of this meeting. Please fill out the comment sheet provided in this brochure if you have any comments or questions.
More informationEnvironmental Review Binder Documentation McGilchrist Street SE: 12th Street SE to 25th Street SE Project City of Salem, Marion County, Oregon
Environmental Review Binder Documentation McGilchrist Street SE: 12th Street SE to 25th Street SE Project City of Salem, Marion County, Oregon Updated Project Information (as of August 11, 2017) STIP Project
More informationBexar County Environmental Services 233 North Pecos La Trinidad, Suite 420, San Antonio, Texas (210) Office (210) Fax
Bexar County Environmental Services 233 North Pecos La Trinidad, Suite 420, San Antonio, Texas 78207 (210) 335-6700 Office (210) 335-6713 Fax The Southern Edwards Plateau Habitat Conservation Plan (or
More informationNEIGHBORHOOD TRAFFIC CALMING PROGRAM. Policy and Procedure. Roswell Department of Transportation (770)
NEIGHBORHOOD TRAFFIC CALMING PROGRAM Policy and Procedure Roswell Department of Transportation (770) 594 6420 Approved by M&CC on December 19, 2011 Table of Contents 1. Application and Intent 2. Program
More informationCity of Fairfax, Virginia City Council Work Session
City of Fairfax, Virginia City Council Work Session Agenda Item # City Council Meeting 12a 9/8/2015 TO: FROM: SUBJECT: ISSUE(S): SUMMARY: FISCAL IMPACT: RECOMMENDATION: ALTERNATIVE COURSE OF ACTION: RESPONSIBLE
More informationDoes DFO Need to Review My Project?
Working Together for Responsible Erosion & Sediment Control Workshop Does DFO Need to Review My Project? June 6, 2014 Fisheries Protection Program Department of Fisheries and Oceans Amendments to the Fisheries
More informationRun of the Charles Boston s Premier Paddling Race
Charles River Watershed Association presents the 35 th Annual Run of the Charles Boston s Premier Paddling Race Sunday, April 30, 2017 2017 Sponsor Proposal About the Run of the Charles The Run of the
More informationConceptual Design Report for the Hamilton Dam Modifications Project. Flint, Michigan. Prepared For: City of Flint P.O. Box 99 Flint, MI
Conceptual Design Report for the Hamilton Dam Modifications Project Flint, Michigan Prepared For: City of Flint P.O. Box 99 Flint, MI 48501-0099 Flint River Watershed Coalition 432 N. Saginaw St. Suite
More informationSection 7 Complete Green Street Guidelines DRAFT
Section 7 Complete Green Street Guidelines DRAFT 1 Section: 7.0 COMPLETE GREEN STREET GUIDELINES These guidelines serve as options to mitigate the environmental impact of a project as well as guide the
More informationWELCOME PTH 59N - PTH 101 INTERCHANGE FUNCTIONAL DESIGN STUDY PUBLIC INFORMATION SESSION MONDAY, JUNE 13, :00 P.M. - 8:00 P.M.
WELCOME - PTH 1 INTERCHANGE FUNCTIONAL DESIGN STUDY PUBLIC INFORMATION SESSION MONDAY, JUNE 13, 11 4:00 P.M. - 8:00 P.M. PROJECT STUDY AREA 1 Wenzel Street PR 2 Pritchard Farm Farm Road Road McGregor Farm
More informationAGENDA REPORT. Issue: Discussion of potential improvements on Barnwell Road at Niblick Drive
AGENDA REPORT To: From: By: Honorable Mayor and City Council Members Warren Hutmacher, City Manager Tom Black, Public Works Director Date: March 23, 2016 Agenda: March 28, 2016 WORK SESSION AGENDA: Barnwell
More informationCapital Metro Downtown Multimodal Station
Capital Metro Downtown Multimodal Station Open House December 11, 2015 Project Goals & Objectives 1 2 3 4 Address near- and long- term MetroRail operational needs Address existing safety issues and modal
More informationBrooklyn Boulevard (County Road 152) Reconstruction Project Phase I. OPEN HOUSE June 20, 2017
Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I OPEN HOUSE June 20, 2017 Brooklyn Boulevard (County Road 152) Phase I Project Partners Project Lead Other Project Partners include Brooklyn
More informationDrought Situations and Management Policy in Vietnam
Regional Workshop for Asia-Pacific Capacity Development to Support National Drought Management Policy Drought Situations and Management Policy in Vietnam Nguyen Van Tinh, Dang Thanh Mai Hanoi, May 2014
More informationENGINEERING AND PUBLIC WORKS. Transportation Improvements: Santa s Village Road (MR15) Public Meeting
ENGINEERING AND PUBLIC WORKS Transportation Improvements: Santa s Village Road (MR15) Public Meeting March 22, 2018 Agenda Welcome and Introductions Fred Jahn: Commissioner of Engineering and Public Works
More informationFairfax County Parkway Widening Fairfax County
Get Involved VDOT representatives will review and evaluate information received as a result of this meeting. Please fill out the comment sheet provided in this brochure if you have any comments or questions.
More informationProject Fact Sheet July, 2018
BELLEVUE AND SYRINGA BIKE SKILLS PARKS Project Fact Sheet July, 2018 Bike parks construction expected to start in August, 2018 After completing a competitive bid process, the City has accepted a bid from
More informationFOREST SERVICE HANDBOOK NATIONAL HEADQUARTERS (WO) WASHINGTON, DC
Page 1 of 14 FOREST SERVICE HANDBOOK NATIONAL HEADQUARTERS (WO) WASHINGTON, DC FSH 7709.55 - TRAVEL PLANNING HANDBOOK Amendment No.: 7709.55-2009-3 Effective Date: January 8, 2009 Duration: This amendment
More informationDevelopment Services Department
Development Services Department Project/File: Lead Agency: Site address: Harris Ranch Specific Area Plan Text Amendments/ZOA14-00001 The applicant is requesting approval of a text amendment application
More informationConcrete Pavements ACCELERATED CONSTRUCTION OF URBAN INTERSECTIONS WITH PORTLAND CEMENT CONCRETE PAVEMENT (PCCP)
Concrete Pavements ACCELERATED CONSTRUCTION OF URBAN INTERSECTIONS WITH PORTLAND CEMENT CONCRETE PAVEMENT (PCCP) Pavements Asphalt pavement has long been a popular road construction material. In areas
More informationDetroit River International Crossing Study Local Advisory Council/Local Agency Group Meeting September 24, 2008, 7:00 p.m. Southwestern High School
Detroit River International Crossing Study Local Advisory Council/Local Agency Group Meeting September 24, 2008, 7:00 p.m. Southwestern High School Introductions Mohammed Alghurabi opened the meeting and
More informationDry Creek Project. The Dry Creek Habitat Enhancement Project provides a. Slowing velocity, creating refuge are key to habitat project
Dry Creek Habitat Enhancement Bulletin The Dry Creek Habitat Enhancement Project provides a unique opportunity for the Sonoma County Water Agency (Water Agency) and landowners to protect endangered fish
More informationCypress Lake Country Club Board of Directors Meeting Minutes
Cypress Lake Country Club Board of Directors Meeting Minutes September 26, 2017 PRESENT: EX-OFFICIO: ABSENT: CALL TO ORDER: Scott, Fischer, Ralph Hutchins, Steve Weisberg, Steve Shimp, Cheryl Schramm,
More informationAdvanced Construction Techniques. Concrete Pavements ACCELERATED CONSTRUCTION OF URBAN INTERSECTIONS WITH PORTLAND CEMENT CONCRETE PAVEMENT (PCCP)
CM 510 Concrete Pavements ACCELERATED CONSTRUCTION OF URBAN INTERSECTIONS WITH PORTLAND CEMENT CONCRETE PAVEMENT (PCCP) Pavements Asphalt pavement has long been a popular road construction material. In
More informationYakima/Klickitat Fisheries Project
Yakima/Klickitat Fisheries Project Lower Yakima River Supplementation and Research Project Operations and Maintenance Annual Report 2002-2003 March 2004 DOE/BP-00006677-1 This Document should be cited
More informationPE17.1 REPORT FOR ACTION
PE17.1 REPORT FOR ACTION Encouraging a paddling and fishing friendly City Date: February 2, 2017 To: Parks and Environment Committee From: General Manager, Parks, Forestry and Recreation Division Wards:
More informationCommunity Open House December 13, A project of the Green Infrastructure Center, supported by Skeo Solutions
Community Open House December 13, 2011 A project of the Green Infrastructure Center, supported by Skeo Solutions Project Background The Green Infrastructure Center, Inc. (GIC) was formed in 2006 to help
More informationFollowing are our comments and findings based on the site visit and review of the complete Traffic Impact Study:
3600 Horizon Boulevard Suite 250 Trevose, Pennsylvania 19053-4900 Voice 215.355.3577 Fax 215.355.3147 www.ekcorp.com November 1, 2006 Pennsylvania Department of Transportation Bureau of Highway Safety
More informationCapital Projects Update: N. Lynn Street Esplanade and Custis Trail Improvements Advertisement for Construction - Progress Report
Capital Projects Update: N. Lynn Street Esplanade and Custis Trail Improvements Advertisement for Construction - Progress Report UPC Design 70762 / CN 109813 Locally Administered PE Phase VDOT Administered
More informationTime of Change We Are Growing We Are An Attractive Place To Live We Are Age Diverse + Living Longer 50000 40000 30000 20000 10000 0 2010 Census Job Density Housing Sheds Transit Sheds The Project FUNDING
More informationLaSalle Park Marina Wave Break
LaSalle Park Marina Wave Break Federal and Municipal Environmental Assessment Background History of the Marina and LaSalle Park The LaSalle Park Marina is located in LaSalle Park at the foot of LaSalle
More informationRECOMMENDATION. POLICY The Park Board approves all use of lands under its jurisdiction.
March 24, 2016 TO: Park Board Chair and Commissioners FROM: General Manager Vancouver Board of Parks and Recreation SUBJECT: Creekside Paddling Centre License Agreements RECOMMENDATION THAT the Vancouver
More informationGuidance Note. Hydropower Guidance Note: HGN 8 Fish Passage. When do you need to install a fish pass?
Guidance Note Hydropower Guidance Note: This guidance note is not intended as a statement of law. It should be read in combination with, and in the context of, the relevant enactments and EU obligations.
More informationJune 13, 2016 Tom Garigen Re: Myrtle Beach Golf and Yacht Club Drainage assessment
INFRASTRUCTURE & REGULATION DIVISION- STORMWATER DEPARTMENT 4401 Privetts Road Conway, South Carolina 29526 Post Office Box 1236 Conway, South Carolina 29528-1236 Phone: (843) 915-5160 Fax: (843) 365-2208
More informationUTAH RECLAMATION MITIGATION AND CONSERVATION COMMISSION [RC0ZCUPCA0, 155R0680R1, RR ]
This document is scheduled to be published in the Federal Register on 07/07/2015 and available online at http://federalregister.gov/a/2015-16600, and on FDsys.gov DEPARTMENT OF THE INTERIOR UTAH RECLAMATION
More informationLESLIE BARNS & CONNECTION TRACK. Construction Liaison Group Meeting #2
LESLIE BARNS & CONNECTION TRACK Construction Liaison Group Meeting #2 July 23, 2013 1 UPDATE (SINCE LAST CLG) Cyclist safety walk (June 26) to review current construction configurations and discuss how
More informationRequest for Authorization to Open Public Comment Period
Request for Authorization to Open Public Comment Period May 12, 2015 LRP, TIPs, and Conformity Reasons for Requested Action: LRP and TIP Amendment to Connections 2040 LRP, and Draft FY 2016 TIP for New
More informationCapital Projects Update: N. Lynn Street Esplanade and Custis Trail Improvements 100% Engineering Design - Progress Report
Capital Projects Update: N. Lynn Street Esplanade and Custis Trail Improvements 100% Engineering Design - Progress Report UPC 70762 Locally Administered PE Phase VDOT Administered CN Phase 4/6/17 1 Project
More informationHospital Link Project Project Update September 2017
Hospital Link Project Project Update September 2017 General The project provides a link from Riverside Drive and the Transitway to the Hospital Link Road. Construction is well underway. Read on for important
More informationCommitted to Service. Development Services. February 21, ACHD Commission. Mindy Wallace, AICP
Committed to Service Sara M. Baker, President Rebecca W. Arnold, Vice President Jim D. Hansen, Commissioner Kent Goldthorpe, Commissioner Paul Woods, Commissioner February 21, 2018 Development Services
More informationPROJECT FACT SHEET March 21, 2018
SITE CHALLENGES & PROJECT BACKGROUND In 2014, the City of Aspen identified the Castle Creek Bridge and Hallam Street corridor as a deficient link in Aspen s bicycle and pedestrian network. Safe and efficient
More informationSan Antonio Creek Spreading Grounds Rehabilitation Project Ojai Valley, CA
Ventura County Watershed Protection District San Antonio Creek Spreading Grounds Rehabilitation Project Ojai Valley, CA Presentation to Ventura River Watershed Council Project Funding Proposition 50 Integrated
More informationPaul Huston, P.E., Design-Build Coordinator Chuck Gonderinger, HDR Engineering. Minnesota Department of Transportation (the Department)
To: From: Paul Huston, P.E., Design-Build Coordinator Chuck Gonderinger, HDR Engineering Date: March 20, 2001 Subject: Roadway Geometric Design Criteria Project: TH 14/218 Design-Build Project, SP 7408-29,
More informationFollow this and additional works at:
University of Massachusetts Amherst ScholarWorks@UMass Amherst International Conference on Engineering and Ecohydrology for Fish Passage International Conference on Engineering and Ecohydrology for Fish
More informationFDOT Treasure Coast Traffic Impact Report April 7 through April 14, 2017
April 7, 2017 Chuck McGinness, 954 777 4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report April 7 through April 14, 2017 TREASURE COAST Construction and maintenance related
More informationBluffdale/ UDOT South High-T Intersection Project Type Operations
Bluffdale/ UDOT 14600 South High-T Intersection Project Type Operations 14600 South and Redwood Road $ 600,000 $ 550,000 This project is to install a new High-T intersection at Redwood Road and 14600 South
More informationPEABODY SQUARE RECONSTRUCTION PROJECT
FINAL DESIGN PRESENTATION HEARING Thursday April 23, 2015 with Peabody City Council Peabody, Massachusetts 6:00 PM PEABODY SQUARE RECONSTRUCTION PROJECT 239 LITTLETON ROAD, SUITE 3, WESTFORD, MA 01886
More informationTwinning Hwy 11/17 Thunder Bay to Nipigon
Twinning Hwy 11/17 Thunder Bay to Nipigon 55 th Annual Engineering and Technology Conference Lakehead Chapter PEO November 4, 2016 Presented by: Bruce Caldwell, P. Eng., MBA Manager Program Planning Ministry
More informationLeague City Parkway at Brittany Lakes/Fennigan Intersection Evaluation/ Traffic Study. Second Public Meeting February 6, 2018
League City Parkway at Brittany Lakes/Fennigan Intersection Evaluation/ Traffic Study Second Public Meeting February 6, 2018 City Project Information League City Parkway and Brittany Lakes Dr./ Fennigan
More informationDouglas Park Playground Replacement
Douglas Park Playground Replacement Construction Contract Park Board Committee Meeting Monday, February 19, 2018 Purpose of this Presentation To seek approval from the Board to enter into a contract with
More informationCOUNTY OF SAN MATEO Parks Department
Agenda Item 5.B COUNTY OF SAN MATEO Parks Department DATE: March 16, 2015 COMMISSION MEETING DATE: April 9, 2015 TO: FROM: Parks and Recreation Commission Cecily Harris, Development Consultant SUBJECT:
More informationto the Public Information Centre for the Downtown Traffic Study
to the Public Information Centre for the Downtown Traffic Study City of Sault Ste. Marie July 25, 2018 Purpose of Study Determine if changes to one-way corridors can enhance downtown s character and spaces
More informationJohnwoods Street Closure Summary Response
Johnwoods Street Closure Summary Response The following provides a summary of the major questions asked at the Public Information Meeting on May 4 th, 2016 and the responses. 1. What was the Approval Process
More informationPublic Information Meeting
Richmond Highway (U.S. Route 1) Corridor Improvements Public Information Meeting Tuesday, April 18, 2017 Mount Vernon High School 8515 Old Mt. Vernon Road, Alexandria, VA 22309 Amanda Baxter, VDOT, Special
More informationStoke Mandeville Parish Council 17 April 2018
Stoke Mandeville Parish Council 17 April 2018 Stoke Mandeville Parish Council 1 Introductions 2 Construction Approach 3 MWCC in Stoke Mandeville 4 Future Engagement Introduction HS2 Phase One Delivery
More informationDRAFT. System Components. Greenway Trails. Introduction. Trail Types. Zebulon Greenway Master Plan
5 System Components Wakefield Street Photo Simulation showing Sharrows Introduction The Master Plan identifies various system components that, together, create a comprehensive greenway system. These components
More informationFocus. Cumberland Whitewater Park. Cumberland Whitewater Park. Read 20 point Comic Sans MS from rear of room. A free flowing natural artificial course
Cumberland Whitewater Park Cumberland Whitewater Park Focus Read 20 point Comic Sans MS from rear of room 1 Cumberland Whitewater Park by Robert B. Kauffman, Ph.D. Proposed site A free flowing natural
More informationBelvedere Heights Streetlights & Sidewalks Improvements Project
Westgate/Belvedere Homes Community Redevelopment Agency Belvedere Heights Streetlights & Sidewalks Improvements Project Phase I MPO 2017 Transportation Alternatives Program (TAP) BTPAC Special Workshop
More informationFDOT Treasure Coast Traffic Impact Report
September 29, 2017 Chuck McGinness, 954 777 4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report September 29 through October 6, 2017 TREASURE COAST Construction and maintenance
More informationDRAFT. Malibu Bluffs Park Skate Park Facility Site Assessment. Prepared For: The City of Malibu Parks and Recreation Department
Malibu Bluffs Park Skate Park Facility Site Assessment Prepared For: The City of Malibu Parks and Recreation Department Prepared on February 28, 2013 By: 1 INTRODUCTION AND PROJECT BACKGROUND For more
More informationFOUR CORNERS POWER PLANT CLOSURE PLAN (b) UPPER RETENTION SUMP FC_ClosPlan_011_
FOUR CORNERS POWER PLANT CLOSURE PLAN 257.102(b) UPPER RETENTION SUMP FC_ClosPlan_011_20161017 Closure Plan Contents 257.102(b)(1) The owner or operator of a CCR unit must prepare a written closure plan
More informationProject Team. Refined Pedestrian Crossing Toolbox. Problem Statement. Aerial of Study Corridor. Crossing Accommodations and Pedestrian Fatalities
Project Team Refined Pedestrian Crossing Toolbox Treatments on Wide, High Speed Urban Roadways Developed as Part of the Springfield Main Street (OR 126) Safety Study Consultants Scott Mansur, P.E., P.T.O.E.
More informationWith Unmatched Amenities
A Planned Gated Residential and Commercial Development In Manvel, Texas With Unmatched Amenities Developed by Joe Watson AXIS POINT DEVELOPERS, LLC Investment Builders and Developers 281 932 4143 JWatson@APDllc.net
More informationBUILDING DEPARTMENT VALUATION AND FEES MONTHLY REPORT
MAY BUILDING DEPARTMENT VALUATION AND FEES MONTHLY REPORT $8,000,000 $7,000,000 $6,000,000 $5,000,000 $4,000,000 $3,000,000 $2,000,000 $1,000,000 $0 $7,337,794 Valuation $1,957,965 UP 74.7% May-2015 May-2014
More informationCITY OF WOODINVILLE ONGOING CAPITAL IMPROVEMENT PROJECT UPDATES
CITY OF WOODINVILLE ONGOING CAPITAL IMPROVEMENT PROJECT UPDATES PROJECT LOCATION MAP (1) DEYOUNG PARK IMPROVEMENTS Project Description - DeYoung Park Improvements include treehouse deck, play area, new
More informationFairview and Main Local Streets Improvement Plan
PIM#2 Summary Report Meeting Format Date & Time: Location: Address: Prepared By: Community Open House August 11, 2016 5:30 p.m. 7:30 p.m. Red Lion Hotel 1800 W. Fairview Avenue, Boise Stephanie Borders,
More informationTransportation Alternatives Set-Aside Program. June 28, 2017
Transportation Alternatives Set-Aside Program June 28, 2017 What is Transportation Alternatives Set- Aside Program (TASA)? Enhancement program (combined separated programs; old TAP) Not a grant program
More informationInterlake Tunnel WRA Board Workshop. August 25, 2014
Interlake Tunnel WRA Board Workshop August 25, 2014 1 Agenda Introduction Project Description Background Concept of tunnel operations Engineering and analysis performed to date Preliminary modeling results