1 The following documentation is an electronicallysubmitted vendor response to an advertised solicitation from the West Virginia Purchasing Bulletin within the Vendor Self Service portal at wvoasis.gov. As part of the State of West Virginia s procurement process, and to maintain the transparency of the bid opening process, this documentation submitted online is publicly posted by the West Virginia Purchasing Division at WVPurchasing.gov with any other vendor responses to this solicitation submitted to the Purchasing Division in hard copy format.

2

3 Purchasing Division 2019 Washington Street East Post Office Box Charleston, WV State of West Virginia Solicitation Response Date issued Proc Folder : Solicitation Description : Addendum 01 Broad Run Portals Reclamation Project Proc Type : Central Purchase Order Solicitation Closes Solicitation No Version :30:00 SR 0313 ESR VENDOR EASTERN ARROW CORP INC FOR INFORMATION CONTACT THE BUYER Beth Collins (304) beth.a.collins@wv.gov Signature X FEIN # DATE All offers subject to all terms and conditions contained in this solicitation Page : 1 FORM ID : WV-PRC-SR-001

4 1 1.0 Mobilization & Demobilization LS $1, $1, (Cannot be more than 10% of Total Amount Bid) Construction Layout LS $1, $1, (Cannot be more than 5% of Total Amount Bid) Quality Control LS $1, $1, (Cannot be more than 3% of Total Amount Bid) Site Preparation LS $25, $25, (Cannot be more than 10% of Total Amount Bid) Page : 2

5 5 5.1 Silt Fence LF $ $ Silt Fence Stabilized Construction Entrances, per ton installed TON $ $7, Stabilized Construction Entrances, per ton installed Temporary Stone Check Dam EA $ $ Temporary Stone Check Dam Revegetation LS $1, $1, Revegetation Page : 3

6 ' Vee Ditch, Rock Riprap LF $ $7, ' Vee Ditch, Rock Riprap ' Flat Bottom Ditch, Vegetated LF $ $5, ' Flat Bottom Ditch, Vegetated ' Flat Bottom Ditch, Rock Riprap LF $ $12, ' Flat Bottom Ditch, Rock Riprap ' Flat Bottom Ditch, Rock Riprap LF $ $3, ' Flat Bottom Ditch, Rock Riprap Page : 4

7 Temporary 36' Culvert Crossing EA $5, $5, Temporary 36' Culvert Crossing " HDPE Culvert LF $ $8, " HDPE Culvert Dry Mine Seal EA $5, $15, Dry Mine Seal Wet/Modified Mine Seal EA $10, $60, Wet/Modified Mine Seal Page : 5

8 Dry Mine Seal with bat gate Type I EA $11, $22, Dry Mine Seal with bat gate Type I Dry Mine Seal with bat gate, Type II EA $10, $20, Dry Mine Seal with bat gate, Type II Wet Mine Seal with bat gate EA $11, $22, Wet Mine Seal with bat gate Standard Bat Gate EA $10, $10, Standard Bat Gate Page : 6

9 Mine Water Outlet Drain EA $5, $5, Mine Water Outlet Drain Soda Ash Briquettes, per 50 pound bag BAG $ $ Soda Ash Briquettes, per 50 pound bag No. 1 Stone TON $ $10, No. 1 Stone Crusher Run Stone TON $ $10, Crusher Run Stone Page : 7

10 Structure Demolition LS $4, $4, Structure Demolition Page : 8

11

12

13

14

15

16

17

18

19

20

21

The following documentation is an electronicallysubmitted vendor response to an advertised solicitation from the West Virginia Purchasing Bulletin

The following documentation is an electronicallysubmitted vendor response to an advertised solicitation from the West Virginia Purchasing Bulletin The following documentation is an electronicallysubmitted vendor response to an advertised solicitation from the West Virginia Purchasing Bulletin within the Vendor Self Service portal at wvoasis.gov.

More information

The following documentation is an electronicallysubmitted vendor response to an advertised solicitation from the West Virginia Purchasing Bulletin

The following documentation is an electronicallysubmitted vendor response to an advertised solicitation from the West Virginia Purchasing Bulletin The following documentation is an electronicallysubmitted vendor response to an advertised solicitation from the West Virginia Purchasing Bulletin within the Vendor Self Service portal at wvoasis.gov.

More information

Riverside County Transportation Department Summary of Bids Project BOS Approval: July 25, 2017 (Agenda Item No. 3.60)

Riverside County Transportation Department Summary of Bids Project BOS Approval: July 25, 2017 (Agenda Item No. 3.60) Company Name Base Bid Schedule A Base Bid Schedule B Total COUNTY'S ESTIMATE 367,150.00 328,300.00 $695,450.00 1 All American Asphalt 481,360.00 108,180.00 $589,540.00 2 PTM General Eng Services, Inc.

More information

Suitable Applications Check dams may be appropriate in the following situations: To promote sedimentation behind the dam.

Suitable Applications Check dams may be appropriate in the following situations: To promote sedimentation behind the dam. Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Category

More information

FINAL REPORT. Yonkers Creek Migration Barrier Removal Project Wonderstump Road Del Norte County. Submitted By:

FINAL REPORT. Yonkers Creek Migration Barrier Removal Project Wonderstump Road Del Norte County. Submitted By: FINAL REPORT Yonkers Creek Migration Barrier Removal Project Wonderstump Road Del Norte County Submitted By: Del Norte County Community Development Department Yonkers Creek Migration Barrier Removal Project

More information

FENCE RENTAL, PURCHASE, INSTALLATION, SUPPLIES & SERVICE - REQUIREMENTS CONTRACT INVITATION FOR BID PRICE SHEET ATTACHMENT E

FENCE RENTAL, PURCHASE, INSTALLATION, SUPPLIES & SERVICE - REQUIREMENTS CONTRACT INVITATION FOR BID PRICE SHEET ATTACHMENT E IT IS NOT ANTICIPATED THAT ONE COMPANY CAN PROVIDE ALL GROUPS, PLEASE PROVIDE PRICING ONLY ON THE GROUPS YOU CAN PROVIDE SERVICES FOR. This document is to be used by the Bidder to specify proposed Rates.

More information

EUROFLO CULVERT PIPE. Fittings / Pipes

EUROFLO CULVERT PIPE. Fittings / Pipes EUROFLO CULVERT PIPE Fittings / Pipes F EUROFLO FITTINGS RUBBERS SIZE CODE COMMENT 250 OD 315 OD 400 OD 500 OD 630 OD 800 OD 1000 OD 1200 OD 520-250-RBR 520-315-RBR 520-400-RBR 520-500-RBR 520-630-RBR

More information

Annual CCR Landfill Inspection OML Existing Landfill OML Expansion Phase 1

Annual CCR Landfill Inspection OML Existing Landfill OML Expansion Phase 1 Annual CCR Landfill Inspection OML Existing Landfill OML Expansion Phase 1 Ottumwa-Midland Landfill Prepared for: Ottumwa-Midland Landfill 15300 130 th Street Ottumwa, Iowa 52501 Prepared by: SCS ENGINEERS

More information

CASE STUDY #1 - TROUT POND

CASE STUDY #1 - TROUT POND CASE STUDY #1 - TROUT POND Headlines from the Dominion Post, Morgantown, WV for 8/30/2002 The Trout Pond Recreational Area is located in Hardy County, West Virginia. The Recreational Area lies within the

More information

T E N D E R Tender # T SCOTT SCBA AIR PACKS AND ACCESSORIES SAINT JOHN FIRE DEPARTMENT

T E N D E R Tender # T SCOTT SCBA AIR PACKS AND ACCESSORIES SAINT JOHN FIRE DEPARTMENT T E N D E R Tender # 2011-424002T SCOTT SCBA AIR PACKS AND ACCESSORIES SAINT JOHN FIRE DEPARTMENT Sealed tenders addressed to the Purchasing Agent, c/o Materials and Fleet Management, 2 nd Floor, 175 Rothesay

More information

OLIVE AVENUE CLASS 2 BIKE LANES HSIP, CIP PROJECT NO CONSTRUCTION CONTRACT AWARD

OLIVE AVENUE CLASS 2 BIKE LANES HSIP, CIP PROJECT NO CONSTRUCTION CONTRACT AWARD STAFF REPORT MEETING DATE: June 7, 2016 TO: FROM: City Council Russ Thompson, Public Works Director Gosia Woodfin, Assistant Engineer 922 Machin Avenue Novato, CA 94945 415/ 899-8900 FAX 415/ 899-8213

More information

ELKTON COMMUNITY LITTLE LEAGUE P.O. BOX 75 ELKTON, MD FEIN: Field Signs Advertisement Fund Raiser

ELKTON COMMUNITY LITTLE LEAGUE P.O. BOX 75 ELKTON, MD FEIN: Field Signs Advertisement Fund Raiser ELKTON COMMUNITY LITTLE LEAGUE P.O. BOX 75 ELKTON, MD 21922 FEIN: 23-1049837 2019 Field Signs Advertisement Fund Raiser ELKTON COMMUNITY LITTLE LEAGUE P.O. BOX 75 ELKTON, MD 21922 FEIN: 23-1049837 RE:

More information

Riverside County Transportation Department Summary of Bids

Riverside County Transportation Department Summary of Bids COUNTY'S ESTIMATE R. J. Noble Company Orange, CA 92856 ITEM NO. ITEM CODE CONTRACT ITEM UNITS QUANTITY UNIT PRICE ENG ESTIMATE BID AMOUNT 1 190101 ROADWAY EXCAVATION CY 8,500 16.00 136,000.00 9.50 80,750.00

More information

CITY OF WESTERVILLE STREET LIGHTING POLE AND TRAFFIC SIGNAL POLE PAINTING PROJECT Project No (WED)

CITY OF WESTERVILLE STREET LIGHTING POLE AND TRAFFIC SIGNAL POLE PAINTING PROJECT Project No (WED) CITY OF WESTERVILLE STREET LIGHTING POLE AND TRAFFIC SIGNAL POLE PAINTING PROJECT Project No. 2016 003 (WED) Sealed bids for the construction of the Street Lighting Pole and Traffic Signal Pole Painting

More information

CITY OF MEMPHIS, TENNESSEE

CITY OF MEMPHIS, TENNESSEE CITY OF MEMPHIS, TENNESSEE SEWER ASSESSMENT & REHABILITATION PROGRAM (SAR OLD LOOSAHATCHIE SANITARY SEWER INTERCEPTOR DIVERS 61 51 ELVIS PRESLEY BLVD. 240 JACKSON AVE. LAMAR AVE. 385 51 14 SUMMER AVE.

More information

Mr. Michael Malone CPS Energy 145 Navarro Street, Mail Drop San Antonio, Texas Project No

Mr. Michael Malone CPS Energy 145 Navarro Street, Mail Drop San Antonio, Texas Project No October 17, 2016 Mr. Michael Malone CPS Energy 145 Navarro Street, Mail Drop 100406 San Antonio, Texas 78296 Project No. 0352436 Subject: Compilation of Construction History Calaveras Power Station San

More information

Bids DECEMBER 21, 2018 AT 2:00 P.M. (EASTERN) (Estimated Cost: $4,700,000.00)

Bids DECEMBER 21, 2018 AT 2:00 P.M. (EASTERN) (Estimated Cost: $4,700,000.00) General Info Number: PROJECT NO. 43-19-03 Description: BRIDGE DECK REPAIR AND REHABILITATION OHIO TURNPIKE RAMP OVER STATE ROUTE 420 M.P. 71.4, SOUTH BILLMAN ROAD OVER OHIO TURNPIKE M.P. 75.2, WOOD AND

More information

M EMORANDUM O CTOBER 6, 201 6

M EMORANDUM O CTOBER 6, 201 6 M EMORANDUM O CTOBER 6, 201 6 TO: FROM: SUBJECT: BOARD OF DIRECTORS ERIC KUHN, GENERAL MANAGER PETER FLEMING, ESQ. DON MEYER, P.E., RAY TENNEY, P.E. WOLFORD AND ELKHEAD RESERVOIR OPERATIONS This memo summarizes

More information

Northside School Class I Bike Path, Cool, CA Application Attachments

Northside School Class I Bike Path, Cool, CA Application Attachments PLHD Grant Application, 12/9/2011 County of El Dorado Department of Transportation Northside School Class I Bike Path, Cool, CA Application Attachments 1. Project Site Map 2. Auburn State Recreation Area

More information

Culvert Safety Inspection Report

Culvert Safety Inspection Report Culvert Safety Inspection Report Facility Federal Structure ID Inspector Name Agency/Consultant Inspection Date LEGEND Haggerty Rd (South) N/A RL/JF GLEG 1/26/2016 9 New Feature Latitude Longitude Struc

More information

EUROFLO CULVERT PIPE. Fittings / Pipes

EUROFLO CULVERT PIPE. Fittings / Pipes EUROFLO CULVERT PIPE Fittings / Pipes F EUROFLO FITTINGS RUBBERS SIZE CODE COMMENT 160 OD 200 OD 250 OD 315 OD 400 OD 500 OD 630 OD 800 OD 1000 OD 1200 OD 1550 OD 1750 OD 1950 OD 520-160-RBR 520-200-RBR

More information

ADDENDUM NO. 1 INVITATION FOR BIDS MAINTENANCE UNIFORM RENTAL SERVICES. IFB NO.: 2016-SP-15 Date Issued: October 6, 2016

ADDENDUM NO. 1 INVITATION FOR BIDS MAINTENANCE UNIFORM RENTAL SERVICES. IFB NO.: 2016-SP-15 Date Issued: October 6, 2016 602 N. Staples, Corpus Christi, Texas 78401 p. 361-289-2712 f. 361-903-3578 www.ccrta.org ADDENDUM NO. 1 INVITATION FOR BIDS MAINTENANCE UNIFORM RENTAL SERVICES IFB NO.: 2016-SP-15 Date Issued: October

More information

As temporary grade control facilities along waterways until final stabilization is established.

As temporary grade control facilities along waterways until final stabilization is established. Check Dams (CD) EC-12 Description Check dams are temporary grade control structures placed in drainage channels to limit the erosivity of stormwater by reducing flow velocity. Check dams are typically

More information

(304) WVPEBD (304) Manor Group (267)

(304) WVPEBD (304) Manor Group (267) SMS: Brin Storag Tanks - Fibrglass Catgory: Tanks Projct ID #: 1004161901 Strt Addrss: Multipl Locations Charlston WV Valu 25305 County: Kanawha Stag: SUBBIDS: ASAP Bid Dat: 10/13/2016, 01:30PM Architct:

More information

3 rd Annual Wounded Warriors Softball Tournament 2014

3 rd Annual Wounded Warriors Softball Tournament 2014 Wounded Warriors Softball Tournament 1625 Donna Dr., Ste. D Virginia Beach, VA 23451 Phone: 757-287-2821 WWST_Organization@live.com Dear Business Owner: Let me take this opportunity to introduce you to

More information

Atlantic Coast of Long Island, Jones Inlet to East Rockaway Inlet, Long Beach Island, NY Construction Update

Atlantic Coast of Long Island, Jones Inlet to East Rockaway Inlet, Long Beach Island, NY Construction Update Atlantic Coast of Long Island, Jones Inlet to East Rockaway Inlet, Long Beach Island, NY Construction Update June 2016 US Army Corps of Engineers Project Purpose Three specific damage mechanisms of coastal

More information

MILE POINT TRAINING WALL JACKSONVILLE, FL. Geotextile Tube Installation

MILE POINT TRAINING WALL JACKSONVILLE, FL. Geotextile Tube Installation MILE POINT TRAINING WALL JACKSONVILLE, FL Geotextile Tube Installation PROJECT DESIGN Remove portion of existing training wall Construct new eastern and western training walls Deepen new flow improvement

More information

Tabulation of Bids. Counties: Project(s):

Tabulation of Bids. Counties: Project(s): Page: 1 14 ROTE 94, ROTE 46 TO OLD COACH RD Quantity and nits nit Price nit Price nit Price 0001 151006M PERFORMANCE BOND AND PAYMENT BOND 0004 154003P MOBILIZATION 0007 157004M CONSTRCTION LAYOT 0012

More information

(Revised February,2005) CULVERTS, BRIDGES, AND FORDS

(Revised February,2005) CULVERTS, BRIDGES, AND FORDS GUIDE TO STREAM CROSSINGS (Revised February,2005) CULVERTS, BRIDGES, AND FORDS Culverts, bridges, and fords are all methods used to cross-streams. Culverts are the most common stream crossing structure.

More information

GDOT Fiscal 2015 Year 2017 GDOT PowerPoint. Title Page

GDOT Fiscal 2015 Year 2017 GDOT PowerPoint. Title Page GDOT Fiscal 2015 Year 2017 GDOT PowerPoint Savannah Post SAME Title Page Annual Programs Review Sub Titles K. Joe Carpenter, Jr., P.E. Body Text Director Division of P3/Program Delivery June 15, 2016 Transportation

More information

Smith Ranch Okeechobee, Florida Saint Lucie & Okeechobee Counties

Smith Ranch Okeechobee, Florida Saint Lucie & Okeechobee Counties Smith Ranch Okeechobee, Florida Saint Lucie & Okeechobee Counties 8,768 +/- Acres Cattle Operation and Exotic Game Preserve Smith Ranch Okeechobee, Florida Saint Lucie & Okeechobee Counties Cattle Operations

More information

Information for File #MVP MVM

Information for File #MVP MVM Information for File #MVP-2018-00168-MVM Applicant: City of Lino Lakes Corps Contact: Marissa Merriman Address: 180 Fifth Street East, Suite 700, St. Paul, Minnesota 55101-1678 E-Mail: Marissa.V.Merriman@usace.army.mil

More information

Culvert Design for Low and High Gradient Streams in the Midwest. Dale Higgins, Hydrologist Chequamegon-Nicolet National Forest

Culvert Design for Low and High Gradient Streams in the Midwest. Dale Higgins, Hydrologist Chequamegon-Nicolet National Forest Culvert Design for Low and High Gradient Streams in the Midwest Dale Higgins, Hydrologist Chequamegon-Nicolet National Forest Overview Culvert Design Considerations Hydraulic Terms Culvert Impacts Low

More information

STEP-4-CP-O-WD-3. Contract under execution. Post Review STEP-26-NCB-B-GD-3.2. Contract under execution Post Review STEP-22-NCB-B-GD-1.

STEP-4-CP-O-WD-3. Contract under execution. Post Review STEP-26-NCB-B-GD-3.2. Contract under execution Post Review STEP-22-NCB-B-GD-1. Public Disclosure Authorized Project name: Skills and Training Enhancement Project Loan: 4764-BD Procurement Plan Version: 2015-1 Status: Approved Date of Last Change of Status: 30/04/2015 Public Disclosure

More information

H/FFA YOUTH SWINE SHOW & SALE

H/FFA YOUTH SWINE SHOW & SALE 2018 4-H/FFA YOUTH SWINE SHOW & SALE SUPERINTENDENT: Tom Waugh (Boss Hog) Assistant Superintendent: Chris Bacon All Swine must go to slaughter after exhibition. MANDATORY SWINE MEETING: MANDATORY TAG-IN:

More information

January, same manner that stirring a fire hastens its burning.

January, same manner that stirring a fire hastens its burning. January, 1932 9 Checking Gully Erosion on Golf Courses By R. E. Uhland Superintendent, Soil Erosion Experiment Station, Bethany, Mo. No one will deny that good greens and fairways are essential to a good

More information

VWP CONSTRUCTION INSPECTION REPORT. Project Name: Berkmar Drive Extension Locality: Albemarle County Inspector: ERM

VWP CONSTRUCTION INSPECTION REPORT. Project Name: Berkmar Drive Extension Locality: Albemarle County Inspector: ERM VWP CONSTRUCTION INSPECTION REPORT Inspection Date: August 22, 2016 VWP Permit No. 15-1268 SPGP RO Project Name: Berkmar Drive Extension Locality: Albemarle County Inspector: ERM Impacts: PFO PEM PSS POW

More information

CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 01/27/16 HIGHWAY: COUNTY: 12/02/2014 ESTIMATE PAID: AWARD DATE: 12/18/2014 ESTIMATE PERIOD:

CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 01/27/16 HIGHWAY: COUNTY: 12/02/2014 ESTIMATE PAID: AWARD DATE: 12/18/2014 ESTIMATE PERIOD: 565,853.54 CONTRACTOR'S ESTIMATE PACKAGE REPORT DATE: 1/27/16 62 CONTRACT ID: 6277661 : RMC - 6277661 CONTRACT: 121449 AWARD : $4,436,834.21 ED : $4,436,834.21 ADJ. ED : $5,2,687.75 CONTRACT: CONTRACTOR:

More information

ADDENDUM NO. 1. The following changes shall be made to the TECHNICAL SPECIFICATIONS:

ADDENDUM NO. 1. The following changes shall be made to the TECHNICAL SPECIFICATIONS: Capital Projects Contract Administration 3015 SW Western Blvd, Corvallis, Oregon 97333 T 541-737-0922 F 541-737-4810 September 11, 2015 Capital Projects Contract Administration Gill Coliseum 1st Floor

More information

APPENDIX A STRUCTURE DESCRIPTIONS AND RATING CURVES

APPENDIX A STRUCTURE DESCRIPTIONS AND RATING CURVES 3 4 5 6 7 8 9 0 3 APPENDIX A STRUCTURE DESCRIPTIONS AND RATING CURVES Kissimmee River Vol December 005 Version Draft 4 3 4 5 6 7 8 9 0 3 4 5 6 7 8 9 0 3 4 5 6 7 8 9 30 3 3 33 34 35 36 37 38 39 40 4 4 43

More information

Township of North Huntingdon Application for Permit

Township of North Huntingdon Application for Permit Township of North Huntingdon Application for Permit 11279 Center Highway, North Huntingdon, PA 15642 724-863-3806 ext. 126 / www.nhtpa.us 1. Swimming Pool Permit Request TYPE OF STRUCTURE: SWIMMING POOL

More information

COTTER MILL SITE SUMMARY - RML

COTTER MILL SITE SUMMARY - RML COTTER MILL SITE SUMMARY - RML NRC Code Totals Estimated Cost Reference/ Index Table No. in table N/A GRAND TOTAL RML SURETY RML TOTAL $20,401,841 N/A N/A N/A GRAND TOTAL RAP SURETY RAP TOTAL $2,891,319

More information

QUEENS LIBRARY BUILDINGS AND GROUNDS COMMITTEE THURSDAY, APRIL 27, Central Library Merrick Blvd., Jamaica, NY AGENDA

QUEENS LIBRARY BUILDINGS AND GROUNDS COMMITTEE THURSDAY, APRIL 27, Central Library Merrick Blvd., Jamaica, NY AGENDA QUEENS LIBRARY BUILDINGS AND GROUNDS COMMITTEE THURSDAY, APRIL 27, 2017 Central Library 89-11 Merrick Blvd., Jamaica, NY 11432 AGENDA 6:00 PM BUILDINGS AND GROUNDS COMMITTEE REGULAR MEETING I. Call to

More information

Annual CCR Landfill Inspection. Lansing Landfill. Interstate Power and Light Company. Prepared for:

Annual CCR Landfill Inspection. Lansing Landfill. Interstate Power and Light Company. Prepared for: Annual CCR Landfill Inspection Lansing Landfill Prepared for: Interstate Power and Light Company Lansing Generating Station 2320 Power Plant Drive Lansing, Iowa 52151 Prepared by: SCS ENGINEERS 2830 Dairy

More information

APPENDIX E Activity Defect Assignment

APPENDIX E Activity Defect Assignment APPENDIX E Activity Defect Assignment Activity Defect Pct Applicable 2010-ML - SHALLOW PATCHING (STN - 2010-TL - SHALLOW PATCHING (STN - 2020-ML - DEEP PATCHING (STN - 2020-TL - DEEP PATCHING (STN - 2030-ML

More information

CITY OF FERNANDINA BEACH, FLORIDA

CITY OF FERNANDINA BEACH, FLORIDA CITY OF FERNANDINA BEACH, FLORIDA ADDENDUM ONE FOR INVITATION TO BID ITB #16-02 EGANS CREEK FISHING PIER AND KAYAK LAUNCH Prepared By: City of Fernandina Beach 204 Ash Street Fernandina Beach, FL 32034

More information

Appendix B Harris County Standard Operating Procedure for Determining In Situ Hydraulic Performance of High Flow Rate Bioretention Media

Appendix B Harris County Standard Operating Procedure for Determining In Situ Hydraulic Performance of High Flow Rate Bioretention Media Objective Appendix B Harris County Standard Operating Procedure for Determining In Situ Hydraulic Performance of High Flow Rate Bioretention Media Provide as-built confirmation of proper installation and

More information

Kansas Department of Transportation. Tabulation of Bids

Kansas Department of Transportation. Tabulation of Bids Page 1 of 17 SECTION: 1 COMMON ITEMS 1 025323 MOBILIZATION 2 070626 MOBILIZATION (DBE) 3 020100 CONTRACTOR CONSTRUCTION STAKING 4 025600 FIELD OFFICE AND LABORATORY (TYPE A) 5 071554 CONCRETE FOR SEAL

More information

October 30, Subject: Solicitation Number: ITB Printing of Florida Class E Driver License Handbook

October 30, Subject: Solicitation Number: ITB Printing of Florida Class E Driver License Handbook October 30, 2015 To: Prospective Vendor Subject: Solicitation Number: ITB 008-16 Printing of Florida Class E Driver License Handbook Addendum No. 1 The enclosed information has been provided for consideration

More information

2014 Capital Improvement Program Current Year Projects for:

2014 Capital Improvement Program Current Year Projects for: 2014 Capital Improvement Program Current Year Projects for: West Slope Road/Bridge Capital Improvement Program Tahoe Environmental Improvement Program Airport Capital Improvement Program Transportation

More information

SUMMARY COSTS: (Please attach a detailed budget including all sources of recipient funding)

SUMMARY COSTS: (Please attach a detailed budget including all sources of recipient funding) VIRGINIA SALTWATER RECREATIONAL FISHING DEVELOPMENT FUND SUMMARY PROJECT APPLICATION Please complete all fields. This page should be used as a coversheet for a detailed application. NAME AND ADDRESS OF

More information

Information for File # SEW

Information for File # SEW Information for File #2014-02744-SEW Applicant: Minnesota Department of Transportation (MnDOT), District 3; c/o Mr. Robert Nibbe Corps Contact: Sarah Wingert, U.S. Army Corps of Engineers, 180 5 th Street

More information

Schedule of Events. subject to change

Schedule of Events. subject to change PRCA NATIONAL CONVENTION Schedule of Events subject to change Monday, December 4 12:00 p.m. - 4:00 p.m. Early Registration & Trade Show Set-Up 4:00 p.m. - 5:00 p.m. Contract Personnel Reception 6:00 p.m.

More information

Technical Report Culvert A Hydraulic Analysis

Technical Report Culvert A Hydraulic Analysis DATE: November 3, 2011 Technical Report Culvert A Hydraulic Analysis TO: FROM: RE: Jim Reiser, P.E. Project Manager Parsons Brinckerhoff, Inc. Kurt Killian, P.E., CFM Parsons Brinckerhoff, Inc. Design

More information

Swamp Road Residents Study

Swamp Road Residents Study Swamp Road Residents Study SRRG Meeting with PennDot and Elected Officials Newtown and Wrightstown, PA April 25, 2008 Newtown Township Section of Swamp Road Limited Public Funds No reconstruction of a

More information

Tabulation of Bids. Counties:

Tabulation of Bids. Counties: Page 1 of 16 0001 151006M PERFORMANCE BOND AND PAYMENT BOND 0004 153003P PROGRESS SCHEDLE 0005 153005M PROGRESS SCHEDLE PDATE 0006 153011M TRAINEES 0007 154003P MOBILIZATION 0010 157004M CONSTRCTION LAYOT

More information

NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 DATED 10/05/2005

NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 DATED 10/05/2005 TIFICATION OF ADDENDUM ADDENDUM. 2 DATED 10/05/2005 Control Project Highway County 0049-09-064, ETC. CPM 49-9-64, ETC. BS 6-R, ETC. BRAZOS, ETC. Ladies/Gentlemen: Attached please find an addendum on the

More information

Tabulation of Bids. Counties:

Tabulation of Bids. Counties: Page 1 of 27 0001 151006M PERFORMANCE BOND AND PAYMENT BOND 0004 153003P PROGRESS SCHEDLE 0005 153005M PROGRESS SCHEDLE PDATE 0006 154003P MOBILIZATION 0009 157004M CONSTRCTION LAYOT 0010 157006M MONMENT

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH 133 OVER A DITCH ST. LOUIS COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH 133 OVER A DITCH ST. LOUIS COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 7780 CSAH 133 OVER A DITCH ST. LOUIS COUNTY SEPTEMBER 27, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS, INC. JOB NO.

More information

APPENDIX C VEGETATED EMERGENCY SPILLWAY. VERSION 1.0 March 1, 2011

APPENDIX C VEGETATED EMERGENCY SPILLWAY. VERSION 1.0 March 1, 2011 APPENDIX C VEGETATED EMERGENCY SPILLWAY VERSION 1.0 March 1, 2011 [NOTE: Could use a better photo more clearly showing the emergency spillway in the context of the dam.] SECTION C-1: DESCRIPTION OF PRACTICE

More information

TABLE OF CONTENTS LEGAL NOTICE

TABLE OF CONTENTS LEGAL NOTICE Closure Plan for Existing CCR Revision: 1 Surface Impoundments Page No. i TABLE OF CONTENTS 1. INTRODUCTION... 1 2. PROPOSED CCR IMPOUNDMENT CLOSURE PROCEDURE... 3 3. PROPOSED COVER SYSTEM... 4 4. ESTIMATED

More information

INTERSECTION IMPROVEMENTS

INTERSECTION IMPROVEMENTS MCHENRY COUNTY DIVISION OF TRANSPORTATION SEPTEMBER 2012 RIVER ROAD AT DOWELL ROAD INTERSECTION IMPROVEMENTS INSIDE: Public Meeting #1 Summary 1 Public Meeting #2 Summary 1 Key Issues Raised at Public

More information

TABLE OF CONTENTS LEGAL NOTICE

TABLE OF CONTENTS LEGAL NOTICE Surface Impoundments Page No. i TABLE OF CONTENTS 1. INTRODUCTION... 1 2. PROPOSED CCR IMPOUNDMENT CLOSURE PROCEDURE... 3 3. PROPOSED COVER SYSTEM... 4 4. ESTIMATED MAXIMUM INVENTORY OF CCR... 4 5. ESTIMATED

More information

JAP Additional Information Sheet

JAP Additional Information Sheet JAP Additional Information Sheet Block 15: Purpose and Need The USACE purpose of the project is to provide a safe and reliable whitewater park for the recreational public in a city park, which will provide

More information

MEMORANDUM. Date: April 25, Town Commission. Dave Bullock, Town Manager

MEMORANDUM. Date: April 25, Town Commission. Dave Bullock, Town Manager MEMORANDUM Date: April 25, 2017 TO: FROM: Town Commission Dave Bullock, Town Manager SUBJECT: Resolution 2017-12, Waiver of Procurement Provisions Fiber Conduit Installation Project in Conjunction with

More information

Federal Project No.: STP-007-8(154)

Federal Project No.: STP-007-8(154) Schedule of Items Page: 2 Oversight/State Project : (NFO)0616-007-450, M501 Federal Project : STP-007-8(154) 0010 513 00100 0020 517 00101 MOBILIZATION CONSTRUCTION SURVEYING (CONSTRUCTION) 0030 301 00110

More information

PIP My Ride-Basics of Program Management

PIP My Ride-Basics of Program Management PIP My Ride-Basics of Program Management Paul Worley, CPM - Rail Division Director North Carolina Department of Transportation Brian Speight, P.E. - Sr. Project Manager Hatch Mott MacDonald Webinar, May

More information

Kansas Department of Transportation DISTRICT 1. Project(s): Max: Min:

Kansas Department of Transportation DISTRICT 1. Project(s): Max: Min: Page 1 of 10 SECTION: 01 COMMON ITEMS Cat Alt Set: Cat Alt Member: LCC: 1 025323 MOBILIZATION 2 070626 MOBILIZATION (DBE) 3 070580 FLAGGER (SET PRICE) (1) LS (1) LS 1.000 HOUR 86,800.00000 86,800.00 3,375.50000

More information

ALTERNATIVES FOR COASTAL STORM DAMAGE MITIGATION

ALTERNATIVES FOR COASTAL STORM DAMAGE MITIGATION ALTERNATIVES FOR COASTAL STORM DAMAGE MITIGATION Dave Basco Old Dominion University, Norfolk, Virginia, USA National Park Service Photo STRUCTURAL (changes to natural, physical system) hardening (seawalls,

More information

PeopleSoft Page No: 1 Report ID: AUCCYCLE Sourcing Event Cycle Time Analysis Run Date: 26-JUL :11:25

PeopleSoft Page No: 1 Report ID: AUCCYCLE Sourcing Event Cycle Time Analysis Run Date: 26-JUL :11:25 PeopleSoft Page No: 1 Report ID: AUCCYCLE Sourcing Event Cycle Time Analysis Run Date: 26-JUL-2012 11:11:25 Selection Criteria Business Unit Department Event Creator From Date Through Date Event Statuses

More information

11.2 Detailed Checklists CHECKLIST 1: FEASIBILITY STAGE AUDIT. 1.1 General topics Scope of project; function; traffic mix

11.2 Detailed Checklists CHECKLIST 1: FEASIBILITY STAGE AUDIT. 1.1 General topics Scope of project; function; traffic mix 11.2 Detailed Checklists CHECKLIST 1: FEASIBILITY STAGE AUDIT 1.1 General topics 1.1.1 Scope of project; function; traffic mix What is the intended function of the scheme? Is the design consistent with

More information

INDIANA REGIONAL GENERAL CONDITIONS FOR THE STATE OF INDIANA

INDIANA REGIONAL GENERAL CONDITIONS FOR THE STATE OF INDIANA INDIANA REGIONAL GENERAL CONDITIONS FOR THE STATE OF INDIANA These regional conditions are in addition to but do not supersede the requirements in the Federal Register (Volume 82 No. 4 of January 6, 2017).

More information

Ruth Heggen. Florida Fish and Wildlife Conservation Commission DATE: MARCH 21, 2017 ADDENDUM NO.: 1 BID NO.: FWC 16/17-96

Ruth Heggen. Florida Fish and Wildlife Conservation Commission DATE: MARCH 21, 2017 ADDENDUM NO.: 1 BID NO.: FWC 16/17-96 DATE: MARCH 21, 2017 Florida Fish and Wildlife Conservation Commission Commissioners Brian Yablonski Chairman Tallahassee Aliese P. Liesa Priddy Vice Chairman Immokalee Ronald M. Bergeron Fort Lauderdale

More information

FUGITIVE DUST CONTROL PLAN

FUGITIVE DUST CONTROL PLAN FUGITIVE DUST CONTROL PLAN PLEASANTS LANDFILL Willow Island, WV Allegheny Energy Supply Company, LLC A FirstEnergy Company October 19, 2015 CONTENTS Introduction 1 CCR Unit Description 1 CCR Fugitive Dust

More information

Great Lakes Stream Crossing Inventory Instructions

Great Lakes Stream Crossing Inventory Instructions Great Lakes Stream Crossing Inventory Instructions This document is a guide to completing the Stream Crossing Data Sheet (2/28/11 version). Careful attention to this guidance will ensure consistent crossing

More information

Private Swimming Pool Permit Application

Private Swimming Pool Permit Application Private Swimming Pool Permit Application Pool Address: Legal: Lot: Block: Plan: Subdivision: Applicant Information: Are you also the primary contact? Yes No Name: Address: Postal Code: Phone: Email Address:

More information

FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION

FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION ORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION MARJORY STONEMAN DOUGLAS BUILDING 3900 COMMONWEALTH BOULEVARD TALLAHASSEE, ORIDA 32399-3000 RICK SCOTT GOVERNOR CARLOS LOPEZ-CANTERA LT. GOVERNOR HERSCHEL T.

More information

Macleod Park Facility Audit

Macleod Park Facility Audit Macleod Park Facility Audit Document number 000219 Client / Site Location Auditor Tennis Victoria Aberdeen Road Macleod VIC 3085 Andrew Sodomaco Audit date 11 Sep 2015 Site summary Total number of enclosures

More information

Design Criteria. Design Criteria

Design Criteria. Design Criteria F Design Criteria Design Criteria Ministry of Transportation Ministère des Transports DESIGN CRITERIA Page: 1 of 13 WORK PROJECT NO. N/A GO Bloomington Station TYPE OF PROJECT LOCATION Bloomington Road

More information

11 CHECKLISTS Master Checklists All Stages CHECKLIST 1 FEASIBILITY STAGE AUDIT

11 CHECKLISTS Master Checklists All Stages CHECKLIST 1 FEASIBILITY STAGE AUDIT 11 CHECKLISTS 11.1 Master Checklists All Stages CHECKLIST 1 FEASIBILITY STAGE AUDIT 1.1 General topics 1. Scope of project; function; traffic mix 2. Type and degree of access to property and developments

More information

ATHLETIC FACILITY September 30, 2010

ATHLETIC FACILITY September 30, 2010 ATHLETIC FACILITY September 30, 2010 I. PROGRAM REQUIREMENTS Refer to the project-specific Schedule of Spaces for student stations, square footage, and for any requirements that may differ from the prototype

More information

DESIGN OF BELL-MOUTH SPILLWAY AT BARVI DAM

DESIGN OF BELL-MOUTH SPILLWAY AT BARVI DAM DESIGN OF BELL-MOUTH SPILLWAY AT BARVI DAM Akshay Haldankar 1, Mahesh Bhadra 2, Rahul Harad 3, Darpan Kapre 4, Dipali Patil 5 1,2,3,4 Under graduate,dept. of Civil Engineering, DRIEMS Neral. 5Assistant

More information

+)) Lower Churchill Project RIPRAP DESIGN FOR WIND-GENERATED WAVES SNC LAVALIN. SLI Document No HER

+)) Lower Churchill Project RIPRAP DESIGN FOR WIND-GENERATED WAVES SNC LAVALIN. SLI Document No HER +)) SNC LAVALIN Lower Churchill Project RIPRAP DESIGN FOR SLI Document No. 505573-3001-4HER-0011-00 Nalcor Reference No. MFA-SN-CD-0000-CV-RP-0006-01 Rev. 81 Date: 07 -Dec-2012 Prepared by: Checked by:

More information

GOAL: Collect product flowing over Onalaska spillway to protect downstream resources C&C 250 Y Y. Looking upstream at spillway

GOAL: Collect product flowing over Onalaska spillway to protect downstream resources C&C 250 Y Y. Looking upstream at spillway GOAL: Collect product flowing over Onalaska spillway to protect downstream resources BR5 Black n/a Onalaska Spillway Carry- In C&C 250 Y Y Looking upstream at spillway Implementation (Go to Aerial View)

More information

AMENDMENT OF SOLICITATION

AMENDMENT OF SOLICITATION PROCUREMENT AND CONTRACTS DEPT. AMENDMENT OF SOLICITATION PAGE 1 Metropolitan Washington Airports Authority 1A. AMENDMENT OF SOLICITATION NO. 1B. DATED Procurement and Contracts Dept., MA-440 1-12-C004

More information

Developments in Longwall Ventilation

Developments in Longwall Ventilation 7 Developments in Longwall Ventilation Jiirgen F. Brune, Joseph P. Aman, and Mike Kotch CONSOL Inc., 18 Washington Road, Pittburgh, P A 15241 ABSTRACT Rapid development in longwall mining technology has

More information

Access Management Standards

Access Management Standards Access Management Standards Section 1: Application of Access Standards This chapter describes the Department's access management standards for access connections on the county roadway system. The standards

More information

EQUIPMENT, AND SUPPLIES. Delivering Environmental, Industrial, and Emergency Solutions

EQUIPMENT, AND SUPPLIES. Delivering Environmental, Industrial, and Emergency Solutions BASIC SPILL PREPAREDNESS, EQUIPMENT, AND SUPPLIES Delivering Environmental, Industrial, and Emergency Solutions Training Objectives Response Strategies before Help Arrives What potential receptors surround

More information

Fish Passage Planning and Design

Fish Passage Planning and Design Fish Passage Planning and Design Culvert Fishway Planning and Design Guidelines Part I Design Drawings for Fishway Projects Ross Kapitzke James Cook University School of Engineering and Physical Sciences

More information

Designing and Benchmarking Mine Roads for Safe and Efficient Haulage. Roger Thompson Alex Visser

Designing and Benchmarking Mine Roads for Safe and Efficient Haulage. Roger Thompson Alex Visser Designing and Benchmarking Mine Roads for Safe and Efficient Haulage Roger Thompson Alex Visser Departments of Mining and Civil & Bio-systems Engineering University of Pretoria, South Africa Aim of Presentation

More information

Initial Annual CCR Landfill Inspection OML Existing Landfill OML Expansion Phase 1

Initial Annual CCR Landfill Inspection OML Existing Landfill OML Expansion Phase 1 Initial Annual CCR Landfill Inspection OML Existing Landfill OML Expansion Phase 1 Ottumwa-Midland Landfill Prepared for: Ottumwa-Midland Landfill 15300 130 th Street Ottumwa, Iowa 52501 Prepared by: SCS

More information

SECTION PRESSURE TESTING OF PIPING

SECTION PRESSURE TESTING OF PIPING SECTION 15044 PRESSURE TESTING OF PIPING PART 1 - GENERAL 1.01 DESCRIPTION A. Scope of Work: This section specifies the leakage and pressure testing of piping. B. Testing Records: PART 2 - PRODUCTS 2.01

More information

2016 VENDOR INFORMATION PACKET

2016 VENDOR INFORMATION PACKET 2016 VENDOR INFORMATION PACKET The Gold Prospectors Association of America is proud to announce our 2016 Spring Schedule, and I am excited to work with all of our vendors on their participation! Without

More information

The Van Ness Campus. Weekly Construction Bulletin #238

The Van Ness Campus. Weekly Construction Bulletin #238 The Van Ness Campus Weekly Construction Bulletin #238 Construction Update Week of April 23, 2018 The Van Ness Campus Weekly Bulletins are intended to help inform members of the community about upcoming

More information

Give Purpose to Your Game!

Give Purpose to Your Game! MONDAY, MAY 20, 2013 CREIGHTON FARMS GOLF CLUB 22616 James Monroe Highway Aldie, Virginia 20105 Give Purpose to Your Game! Please join us on Monday, May 20, 2013 at the beautiful Creighton Farms Golf Club

More information

L21S/SR/ST Glass Level Gauges

L21S/SR/ST Glass Level Gauges L21S/SR/ST Glass Level Gauges Doc. no.: 150, en_cat_l21s/sr/st, 12/2014 Type of code Example: L21ST/1450/AANSI 3/4 150Lb RF/Large chamber Code 1 Basic type L21 2 Type of gauge S Tubular level gauge SR

More information

Tennis Courts A Construction And Maintenance Manual (2012)

Tennis Courts A Construction And Maintenance Manual (2012) Tennis Courts A Construction And Maintenance Manual (2012) claycourts Goddard Tennis Facility (click to visit). GTC has 8 Har-Tru and 2 Reference: "Tennis Courts, A Construction and Maintenance Manual"

More information

GENERAL LEGEND 12"CMP

GENERAL LEGEND 12CMP PLANS FOR X-REFS: west branch_ci FILE PATH: Z:\WEST BRANCH 36863 SIDEWALK IMPROVEMENTS 212 - SRTS - OLIPHANT\DRAWINGS\_PRODUCTION DRAWINGS\A.1 COVER PLOTTED: Monday, July 23, 212 2:44:13 PM OLIPHANT STREET

More information

Bainbridge Decatur County Recreation Authority P.O. Box 7520 Bainbridge, GA December 19, 2018 INVITATION TO BID

Bainbridge Decatur County Recreation Authority P.O. Box 7520 Bainbridge, GA December 19, 2018 INVITATION TO BID Bainbridge Decatur County Recreation Authority P.O. Box 7520 Bainbridge, GA 39818 December 19, 2018 INVITATION TO BID The will receive sealed bids for Baseball and Softball Supplies as described in the

More information

Coal Combustion Residuals Closure Plan

Coal Combustion Residuals Closure Plan Virginia Electric and Power Company Chesterfield Power Station Upper (East) Pond Chesterfield County, Virginia GAI Project Number: C150035.00 October 2016 Prepared by: GAI Consultants, Inc. Richmond Office

More information