1 Ardmore Area Temporary Parking Plan January 14, 2015

2 Township, Ardmore Initiative (A.I.), and Dranoff developed plans for temporary parking; Township, Dranoff, A.I. and community will have ongoing coordination; Plan is dynamic and can be adjusted as needed during project construction

3 Overview of Parking Plan Existing and proposed parking accommodation (metered and un-metered) on Cricket Avenue, Cricket Terrace, Athens Ave, and E. Athens Avenue; TOWNSHIP PARKING Lot # Name 1 PUBLIC SAFETY BUILDING 19 SPACES - 2 HR METERS 11 SPACES OPEN* 2 ATHENSVILLE 28 SPACES - 2 HR METERS 28 SPACES OPEN** 3 ARDMORE POST OFFICE LOT 28 SPACES - 2 HR METERS 73 SPACES - PERMIT 4 CRICKET LOT (During Construction) 25 SPACES METERED (Available) 150 SPACES METERED (Unavailable) 5 CRICKET TERRACE LOT 22 SPACES PERMIT CONVERTED TO 2-HR METERS 6 SCHAUFFELE PLAZA LOT WILL CONVERT HR METERS TO 2-HR METERS, ALL 73 SPACES WILL BE 2-HR METERS 16 ARDMORE WEST LOT 14 SPACES - PERMIT 63 SPACES - 2 HR METERS 10 SPACES 12 HR METERS 20 ATHENS NORTH (TROLLEY WAY) WILL CONVERT 32 SPACES FROM PERMIT TO 2-HR METERS 21 ATHENS SOUTH (TROLLEY WAY) 47 SPACES - PERMIT 23 CRICKET AVENUE SOUTH LOT 5 SPACES - 2 HR METERS 52 SPACES - PERMIT TAB BERNICKER LOT 40 SPACES OPEN*** * Open to Public after 4pm on weekdays and all weekend ** Open to Public after 4pm on Thursday and Friday and all weekend *** Open to Public after 4pm on weekdays and all weekend, up to 40 spaces can be provided for additional times if necessary

4 Parking Lot Options Proposed 1. Relocate LMT Police Vehicles out of Athensville Lot (Thursday/Friday after 4pm, Saturday/Sunday all day) Now in Operation; Provides 28 additional public spaces;

5 Parking Lot Options Proposed 2. Change Some Permit Spaces to Meter Spaces in Existing Lots Provides meters in areas convenient to businesses;

6 Parking Lot Options Proposed 4. Convert 12-hour meters to 2-hour meters in Schauffele Plaza

7 Existing vs Proposed Temporary Parking (Lots) Existing Proposed (Temporary Parking) Lot # Lot Name Meters Permits Total Spaces Peak Demand Meters Open Permits Total Spaces 1 Public Safety Building 19 (2 hr.) (2 hr.) 11* Athensville 28 (2 hr.) (2 hr.) 28 (+28)** Ardmore Post Office (2 hr.) (+28) 0 73 (-28) Cricket Lot 136 (2 hr.) 39 (12 hr.) (2 hr.) (-150) Cricket Terr (2 hr.) (+22) 0 0 (-22) 22 6 Schauffele 42 (2 hr.) 31 (12 hr.) (2 hr.) Ardmore West 63 (2 hr.) 10 (12 hr.) (2 hr.) 10 (12 hr.) Athens North (Trolley Way) Athens South (Trolley Way) ( 2 hr.) (+32) 0 0 (-32) Cricket Ave South (2 hr.) (+5) 0 52 (-5) 57 Total Off- Street Lots 288 (2 hr.) 80 (12 hr.) (2 hr.) 10 (12 hr.) *** * Open to public after 4pm on weekdays and all weekend ** Open to public after 4pm on Thursday and Friday and all weekend *** Bernicker Lot (Township Administration Building) can also provide up to 40 additional spaces if needed

8 On-Street Options Proposed 5. Change two meters to short-term (30 min) on Cricket Avenue (north) Enables customers to conveniently drop-off/pick-up;

9 On-Street Options Proposed 6. Change location of loading zone on Cricket Avenue (north) Existing loading zone will allow for addition of metered parking spaces;

10 Options Proposed 7. Additional Enforcement of Parking Regulations Implemented throughout area;

11 On-Street Options Proposed 8. Cricket Avenue Parallel Parking Emergency vehicle access through construction area will prevent any new spaces between Cricket Terrace and W. Athens Avenue;

12 On-Street Options Proposed 9. Additional Street Parking on Cricket Terrace 11 existing on-street parking spaces; SEPTA bus-stop/lay-by area will remain; Add 3 parallel spaces while maintaining 2-way operation:

13 Summary of On-Street Parking Current Parking Proposed Parking Net Increase In Spaces Metered Non-Metered Metered Non-Metered Cricket Ave between Lancaster and Cricket Terrace Cricket Ave between School Lane and Cricket Terrace Cricket Ave between Spring Ave and Sheldon Lane Cricket Terrace between Cricket Avenue and Rittenhouse Place E Athens Avenue between Rittenhouse Place and Simpson Road West Side No change East Side West Side 6 11 (time restricted)* * East Side No change West Side No change East Side No change South Side No Change North Side South Side N/A N/A N/A N/A No Change North Side No Change Totals * Currently available after 6 PM on weekdays and Saturday and all day on Sunday

14 Existing vs Proposed Temporary Parking Existing Proposed (Temporary Parking) Lot # Lot Name Meters Permits Total Spaces Peak Demand Meters Open Permits Total Spaces 1 Public Safety Building 19 (2 hr.) (2 hr.) 11* Athensville 28 (2 hr.) (2 hr.) 28 (+28)** Ardmore Post Office (2 hr.) (+28) 0 73 (-28) Cricket Lot 136 (2 hr.) 39 (12 hr.) (2 hr.) (-150) Cricket Terrace (2 hr.) (+22) 0 0 (-22) 22 6 Schauffele 42 (2 hr.) 31 (12 hr.) (2 hr.) Ardmore West 63 (2 hr.) 10 (12 hr.) (2 hr.) 10 (12 hr.) Athens North (Trolley Way) (+32) ( 2 hr.) 0 0 (-32) Athens South (Trolley Way) Cricket Ave South (2 hr.) (+5) 0 52 (-5) 57 Total Off-Street Lots 288 (2 hr.) 80 (12 hr.) 368 Total (2 hr.) 10 (12 hr.) 305 Total Total On-Street Parking N/A Total Parking N/A *** * Open to public after 4pm on weekdays and all weekend ** Open to public after 4pm on Thursday and Friday and all weekend *** Bernicker Lot (Township Administration Building) can also provide up to 40 additional spaces if needed

15 Summary of Proposed Temporary Parking Lot # Lot Name Total Spaces 1 Public Safety Building 30 2 Athensville 56 3 Ardmore Post Office Cricket Lot 25 5 Cricket Terr Schauffele Ardmore West Athens North (Trolley Way) Athens South (Trolley Way) Cricket Ave South 57 Total Off-Street Lots 530 Total On-Street Parking 65 Total Parking 595* * Bernicker Lot (Township Administration Building) can also provide up to 40 additional spaces if needed

16 Summary of Rejected Temporary On-Street Parking Areas Location Description # of Potential Spaces Cricket Avenue Cricket Avenue School Lane E. Athens Avenue One-Way between W. Athens and School Lane One-Way between School Lane and W. Spring Avenue One-Way between Cricket Avenue and Ardmore Avenue Install meters between Rittenhouse Place and Simpson Road Total of Rejected On-Street Parking Spaces 61

17 Questions?

Ardmore Area Temporary Parking Plan. March 22, 2017

Ardmore Area Temporary Parking Plan. March 22, 2017 Ardmore Area Temporary Parking Plan March 22, 2017 Overview of Parking Plan Existing and proposed parking (metered and un-metered) on Cricket Avenue, Cricket Terrace, Athens Ave, and E. Athens Avenue;

More information

Cincinnati Dayton Rd Widening

Cincinnati Dayton Rd Widening Cincinnati Dayton Rd Widening Project Overview Widening of Cincinnati Dayton Rd to four lanes - providing a center turn lane and an additional northbound lane Realignment of Station Rd Widening of bridge

More information

Next Steps Staff report to Council on October 2, 2018 to present the Whistler 2018 Transportation Action Plan Final Draft

Next Steps Staff report to Council on October 2, 2018 to present the Whistler 2018 Transportation Action Plan Final Draft Whistler 2028 Transportation Action Plan Information Session September 18, 2018 Agenda 4:00 4:45 Transportation Information Session Gallery walk 4:45 5:00 Presentation of transportation outcomes and long-term

More information

Upper Market Street Bike Lane Project

Upper Market Street Bike Lane Project Upper Market Street Bike Lane Project 17th Street to Octavia Boulevard 6 30 2010 SAN FRANCISCO, CALIFORNIA Agenda San Francisco & Sustainable Transportation Project Goals Outreach & Coordination Project

More information

TRANSPORT CHICAGO: STRATEGIC PUBLIC TRANSIT BUS RELIABILITY IMPROVEMENTS

TRANSPORT CHICAGO: STRATEGIC PUBLIC TRANSIT BUS RELIABILITY IMPROVEMENTS TRANSPORT CHICAGO: STRATEGIC PUBLIC TRANSIT BUS RELIABILITY IMPROVEMENTS Presented by David VanderZee and Jack Chalabian Monday, June 02, 2014 Overview of Strategic Route Management CTA Strategic Route

More information

Tunnel Reconstruction South 5 th Street Association October 16, 2018

Tunnel Reconstruction South 5 th Street Association October 16, 2018 Tunnel Reconstruction South 5 th Street Association October 16, 2018 Reconstructing the Tunnel 2 Service During Tunnel Reconstruction April 2019 through July 2020 3 Projected Cross River Travel Paths of

More information

Welcome. 53 Avenue Overpass over Whitemud Drive Rehabilitation. Public Information Session. Wednesday, March 9, :30-8:00 p.m.

Welcome. 53 Avenue Overpass over Whitemud Drive Rehabilitation. Public Information Session. Wednesday, March 9, :30-8:00 p.m. BRIDGE REHABILITATION Welcome 53 Avenue Overpass over Whitemud Drive Rehabilitation Public Information Session Wednesday, March 9, 2016 4:30-8:00 p.m. Tonight you can: Learn about the 53 Avenue Overpass

More information

Downtown Grand Rapids Bicycle Parking Working Group Short Term Implementation Strategies

Downtown Grand Rapids Bicycle Parking Working Group Short Term Implementation Strategies Downtown Grand Rapids Bicycle Parking Working Group Short Term Implementation Strategies area. Goal: To provide cyclist with both short and long-term bicycle parking options in the downtown Objective #1:

More information

Appendix C. NORTH METRO STATION AREA TRAFFIC IMPACT STATEMENT 88th Avenue Station

Appendix C. NORTH METRO STATION AREA TRAFFIC IMPACT STATEMENT 88th Avenue Station Appendix C NORTH METRO STATION AREA TRAFFIC IMPACT STATEMENT 88th Avenue Station Prepared for: Regional Transportation Department and URS Corporation as part of the North Metro EIS David Evans and Associates,

More information

Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018

Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018 Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018 What s Happening The City plans to mill and resurface Dr. M.L.

More information

Tunnel Reconstruction Brooklyn CB 1 August 14, 2018

Tunnel Reconstruction Brooklyn CB 1 August 14, 2018 Tunnel Reconstruction Brooklyn CB 1 August 14, 2018 Reconstructing the Tunnel 2 Service During Tunnel Reconstruction April 2019 through July 2020 3 Projected Cross River Travel Paths of Customers The Service

More information

Downtown Naples Mobility and Connectivity Study. Naples City Council Presentation January 2017

Downtown Naples Mobility and Connectivity Study. Naples City Council Presentation January 2017 Downtown Naples Mobility and Connectivity Study Naples City Council Presentation January 2017 Agenda 1. Introduction 2. Scope Review 3. Project Schedule 4. Existing Conditions 5. Public Charrette 6. Mobility

More information

WISCONSIN AVENUE EXTENSION SECOND PUBLIC INFORMATION MEETING. March 28, 2017

WISCONSIN AVENUE EXTENSION SECOND PUBLIC INFORMATION MEETING. March 28, 2017 WISCONSIN AVENUE EXTENSION SECOND PUBLIC INFORMATION MEETING March 28, 2017 STUDY AREA N MEETING AGENDA Introductions Study Background Alternatives Studied Recommended Alternative Discussion STUDY BACKGROUND

More information

CITY OF OTTAWA ROADWAY MODIFICATION APPROVAL UNDER DELEGATED AUTHORITY

CITY OF OTTAWA ROADWAY MODIFICATION APPROVAL UNDER DELEGATED AUTHORITY RMA-2015-ATM-038 CITY OF OTTAWA ROADWAY MODIFICATION APPROVAL UNDER DELEGATED AUTHORITY DATE: April 22, 2015 SUBJECT Approval of Roadway Modifications Recommended through an Area Traffic Management Study

More information

September 20, 2016 L Taraval Rapid Project SFMTA Board of Directors Meeting

September 20, 2016 L Taraval Rapid Project SFMTA Board of Directors Meeting September 20, 2016 L Taraval Rapid Project SFMTA Board of Directors Meeting WHY TARAVAL STREET L TARAVAL PROJECT GOALS 1. Improve state of good repair of our transit system Track and overhead replacement

More information

TRAFFIC STUDY. Birch Bluff Road / Pleasant Avenue 01/15/2018. City of Tonka Bay 4901 Manitou Road Tonka Bay, MN WSB PROJECT NO.

TRAFFIC STUDY. Birch Bluff Road / Pleasant Avenue 01/15/2018. City of Tonka Bay 4901 Manitou Road Tonka Bay, MN WSB PROJECT NO. TRAFFIC STUDY Birch Bluff Road / Pleasant Avenue 01/15/2018 City of Tonka Bay 4901 Manitou Road Tonka Bay, MN 55331 WSB PROJECT NO. 10805-000 Birch Bluff Road/ Pleasant Avenue Traffic Study For: City of

More information

Purpose + Need. Connect: Thrive: Develop: < Strengthen the spine of our regional transportation system

Purpose + Need. Connect: Thrive: Develop: < Strengthen the spine of our regional transportation system Purpose + Need I-29 NW Barry Road 64/68/72 MAIN STREET Connect: < Strengthen the spine of our regional transportation system Leavenworth Road Parallel Parkway State Avenue 18th Street Expressway Shawnee

More information

43 rd Avenue, Skillman Avenue Protected Bike Lanes

43 rd Avenue, Skillman Avenue Protected Bike Lanes 43 rd Avenue, Skillman Avenue Protected Bike Lanes Presented to Queens Community Board 2 Transportation Committee - November 6, 2017 43 rd Avenue, Skillman Avenue: Presentation Overview Background Project

More information

CITY OF HAMILTON PLANNING AND ECONOMIC DEVELOPMENT DEPARTMENT Transportation Planning and Parking Division

CITY OF HAMILTON PLANNING AND ECONOMIC DEVELOPMENT DEPARTMENT Transportation Planning and Parking Division CITY OF HAMILTON PLANNING AND ECONOMIC DEVELOPMENT DEPARTMENT Transportation Planning and Parking Division TO: Chair and Members Public Works Committee COMMITTEE DATE: June 18, 2018 SUBJECT/REPORT NO:

More information

Advancing Transportation Choices in Des Moines. MPO Environmental Roundtable January 9, 2018

Advancing Transportation Choices in Des Moines. MPO Environmental Roundtable January 9, 2018 Advancing Transportation Choices in Des Moines MPO Environmental Roundtable January 9, 2018 Presented by Jennifer McCoy, PE, PTOE City Traffic Engineer Agenda Des Moines Area Transportation Planning Connect

More information

Hennepin Avenue Reconstruction Washington Avenue to 12 th Street

Hennepin Avenue Reconstruction Washington Avenue to 12 th Street CITY OF MINNEAPOLIS Hennepin Avenue Reconstruction Washington Avenue to 12 th Street April 2016 1 Upcoming Opportunities Public Meeting #2 April 25, 2016 Minneapolis Central Library Doty Board Room Repeat

More information

EUCLID AVENUE PARKING STUDY CITY OF SYRACUSE, ONONDAGA COUNTY, NEW YORK

EUCLID AVENUE PARKING STUDY CITY OF SYRACUSE, ONONDAGA COUNTY, NEW YORK EUCLID AVENUE PARKING STUDY CITY OF SYRACUSE, ONONDAGA COUNTY, NEW YORK CITY OF SYRACUSE DEPARTMENT OF PUBLIC WORKS 1200 CANAL STREET EXTENSION SYRACUSE, NEW YORK 13210 DRAFT REPORT DATE: November 13,

More information

I-105 ExpressLanes Project

I-105 ExpressLanes Project I-105 ExpressLanes Project Public Scoping Meetings March 2018 Introduction to Scoping This process is your opportunity to give us your thoughts on: The purpose and need for the proposed improvements The

More information

Sebastopol Charter School Traffic Management Plan

Sebastopol Charter School Traffic Management Plan Sebastopol Charter School The serves as the working document in support of these essential goals: to ensure the safety and efficiency of student arrival to and departure from school to ensure the safety

More information

Philadelphia Bus Network Choices Report

Philadelphia Bus Network Choices Report Philadelphia Bus Network Choices Report JUNE 2018 SEPTA Table of Contents Executive Summary...7 What if transit gave us more freedom?... 8 What is this report?... 8 The main conclusions... 9 What is happening

More information

The Bay Bridge Corridor Congestion Study

The Bay Bridge Corridor Congestion Study Bay Bridge Corridor Congestion Study Tony Bruzzone, Arup TJPA Board Nov 1, 2010 Funded by AC Transit/Federal Transit Administration (FTA) Contracted with the Transbay Joint Powers Authority (TJPA) Stakeholders:

More information

Transportation Impact Assessment

Transportation Impact Assessment Transportation Impact Assessment 1) Goals Assess Traffic Impacts for Evaluation by School Building Committee Understand Current Conditions Provide Recommendation for: - Safety for Children - Adequate Drop-Off/

More information

AGENDA ITEM G-2 Public Works

AGENDA ITEM G-2 Public Works AGENDA ITEM G-2 Public Works STAFF REPORT City Council Meeting Date: 12/6/2016 Staff Report Number: 16-214-CC Regular Business: Approve the Oak Grove University Crane Bike Improvement Concept Plan, authorize

More information

ITS-NY ANNUAL MEETING Bus Rapid Transit in New York City: Bus Lane Operations on One-Way Arterial Streets

ITS-NY ANNUAL MEETING Bus Rapid Transit in New York City: Bus Lane Operations on One-Way Arterial Streets ITS-NY ANNUAL MEETING Bus Rapid Transit in New York City: Bus Lane Operations on One-Way Arterial Streets June 9, 2011 Ted Orosz AICP, Director Long Range Bus Planning MTA New York City Transit 1 Overview

More information

Set of plans containing details for game day operations of the Ballpark. Plans set forth the responsibilities and the specific actions of:

Set of plans containing details for game day operations of the Ballpark. Plans set forth the responsibilities and the specific actions of: What is the TOPP? Set of plans containing details for game day operations of the Ballpark. Plans set forth the responsibilities and the specific actions of: Ballpark management, District Department of

More information

TRANSPORTATION IMPROVEMENT STRATEGY

TRANSPORTATION IMPROVEMENT STRATEGY TRANSPORTATION IMPROVEMENT STRATEGY A Vision for Staten Island North Shore November 2016 1 EXISTING CONDITIONS Transit Conditions MTA Bus Staten Island Railroad Peak Directional Traffic Volume (per hour)**:

More information

Cycling Network Plan Implementation in Thorncliffe Park and Flemingdon Park

Cycling Network Plan Implementation in Thorncliffe Park and Flemingdon Park PW28.13 REPORT FOR ACTION Cycling Network Plan Implementation in Thorncliffe Park and Flemingdon Park Date: March 26, 2018 To: Public Works and Infrastructure Committee From: General Manager, Transportation

More information

MASSACHUSETTS AVENUE BRIDGE REPLACEMENT PROJECT APRIL 25, 2018

MASSACHUSETTS AVENUE BRIDGE REPLACEMENT PROJECT APRIL 25, 2018 MASSACHUSETTS AVENUE BRIDGE REPLACEMENT PROJECT APRIL 25, 2018 AGENDA Introductions Project Benefits Progress to Date Schedule for Remaining Work Phase 3 Activities, Impacts & Traffic Detours Phase 4 Activities

More information

Water Street Promenade. Engineering and Design Services. Public Information Meeting No. 2. Education / Infrastructure / Innovation. Maplewood Avenue &

Water Street Promenade. Engineering and Design Services. Public Information Meeting No. 2. Education / Infrastructure / Innovation. Maplewood Avenue & Public Information Meeting No. 2 Water Street Promenade Maplewood Avenue & Engineering and Design Services Adjacent Areas July 16,2014Portsmouth, NH May 10, 2016 Education / Infrastructure / Innovation

More information

Queensboro Bridge Bus Priority Study: Summary of Recommendations. Presentation to Manhattan Community Board 8 May 4, 2011

Queensboro Bridge Bus Priority Study: Summary of Recommendations. Presentation to Manhattan Community Board 8 May 4, 2011 : Summary of Recommendations Presentation to Manhattan Community Board 8 May 4, 2011 1 Overview Study Goal: Identify cost-effective ways to improve bus speed and reliability for local and express buses

More information

Astoria Boulevard ADA and Station Renewal Track Improvements. February 19, 2019

Astoria Boulevard ADA and Station Renewal Track Improvements. February 19, 2019 Astoria Boulevard ADA and Station Renewal Track Improvements February 19, 2019 Major Scope of Work Replace Street and Platform Stairs Work Description Install Two Street-to-Mezzanine Elevators Install

More information

Attachment A: Traffic Mitigation Measures

Attachment A: Traffic Mitigation Measures Attachment A: Traffic Mitigation Measures Central Interceptor Main Project Works Watercare Services Limited This appendix outlines examples of detailed mitigation measures that could be implemented for

More information

ECONOMY PEOPLE ENVIRONMENT

ECONOMY PEOPLE ENVIRONMENT Report Back on Local Transit Improvements May 29, 2013 ECONOMY PEOPLE ENVIRONMENT Intro Council Requested Report Back Topics Progress on Planning for Broadway Subway False Creek Bridges Local Transit Improvements

More information

EXECUTIVE SUMMARY... vii 1 STUDY OVERVIEW Study Scope Study Area Study Objectives

EXECUTIVE SUMMARY... vii 1 STUDY OVERVIEW Study Scope Study Area Study Objectives Contents EXECUTIVE SUMMARY... vii 1 STUDY OVERVIEW... 1-1 1.1 Study Scope... 1-1 1.2 Study Area... 1-1 1.3 Study Objectives... 1-3 2 EXISTING CONDITIONS... 2-1 2.1 Existing Freeway Conditions... 2-4 2.1.1

More information

Protected Bike Lanes in San Francisco Mike Sallaberry SFMTA NACTO Workshop - Chicago IL

Protected Bike Lanes in San Francisco Mike Sallaberry SFMTA NACTO Workshop - Chicago IL Protected Bike Lanes in San Francisco Mike Sallaberry SFMTA 10 14 2011 NACTO Workshop - Chicago IL San Francisco 2 nd Highest Density in the U.S. 47 square miles Mild Climate Market Population ~810,000

More information

M14A/D Select Bus Service

M14A/D Select Bus Service M14A/D Select Bus Service Manhattan Community Board 6: April 1, 2019 New York City Transit 2 Background M14 Select Bus Service M14 was identified as a critical future SBS corridor in past BRT studies as

More information

Dallas Trail Safety Initiatives. Quality of Life Committee February 14, 2011 Park and Recreation Department

Dallas Trail Safety Initiatives. Quality of Life Committee February 14, 2011 Park and Recreation Department Dallas Trail Safety Initiatives Quality of Life Committee February 14, 2011 Park and Recreation Department Purpose of Briefing Provide brief overview of the City s trail network Provide information on

More information

June 3, Attention: David Hogan City of San Mateo 330 W. 2oth Avenue San Mateo, CA 94403

June 3, Attention: David Hogan City of San Mateo 330 W. 2oth Avenue San Mateo, CA 94403 June 3, 2015 Attention: David Hogan City of San Mateo 330 W. 2oth Avenue San Mateo, CA 94403 Regarding: PA # 15-030, Bridgepointe Shopping Center 2202 Bridgepointe Parkway, APN 035-466-10 Dear David: Enclosed

More information

BUSINESS OF THE CITY COUNCIL CITY OF MERCER ISLAND, WA

BUSINESS OF THE CITY COUNCIL CITY OF MERCER ISLAND, WA BUSINESS OF THE CITY COUNCIL CITY OF MERCER ISLAND, WA AB 4087 May 1, 2006 Regular Business PEAK PROJECT UPDATE - CITY RELATED ISSUES Proposed Council Action: Receive update. No action required. DEPARTMENT

More information

11,000. P.M. Peak Hour Vehicles/Hour 10,000 9,000 8,000. Year

11,000. P.M. Peak Hour Vehicles/Hour 10,000 9,000 8,000. Year CONGESTION RELIEF TASK FORCE The problem today With traffic levels hampering downtown circulation, and long delays in west Salem, policy makers are evaluating potential transportation infrastructure, programs,

More information

Exhibit 964B Traffic Management Pianj. (no change) Daily Start/End Schedule Grades K-5th: Grades K-5th: >Start: 7:55 AM

Exhibit 964B Traffic Management Pianj. (no change) Daily Start/End Schedule Grades K-5th: Grades K-5th: >Start: 7:55 AM Exhibit 964B 30115 1 6 10 15 Traffic Management Pianj Traffic Management Plan A Traffic Management Plan (TMP) is important to safely achieve an optimum level of traffic flow and circulation during peak

More information

MEDICAL/OFFICE BUILDING 1637 BANK STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW. Prepared for:

MEDICAL/OFFICE BUILDING 1637 BANK STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW. Prepared for: MEDICAL/OFFICE BUILDING 1637 BANK STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW Prepared for: 2434984 Ontario Inc. 13-5510 Canotek Road Ottawa, Ontario K1J 9J5 June 4, 2015 115-613 Report_2.doc D. J.

More information

US 41 COMPLETE STREETS CORRIDOR PLANNING STUDY from University Parkway to Whitfield Avenue

US 41 COMPLETE STREETS CORRIDOR PLANNING STUDY from University Parkway to Whitfield Avenue 41 US 41 COMPLETE STREETS CORRIDOR PLANNING STUDY from University Parkway to Whitfield Avenue EXECUTIVE SUMMARY DRAFT FEBRUARY 2019 Project Overview The US 41 Complete Streets Corridor Planning Study,

More information

MPO Staff Report Technical Advisory Committee: May 10, 2017 MPO Executive Board: May 17, 2017

MPO Staff Report Technical Advisory Committee: May 10, 2017 MPO Executive Board: May 17, 2017 MPO Staff Report Technical Advisory Committee: May 10, 2017 MPO Executive Board: May 17, 2017 RECOMMENDED ACTION: Update on the NDDOT US Business 2 Project Programmed for 2019 Matter of the NDDOT US Business

More information

Chapter 3 BUS IMPROVEMENT CONCEPTS

Chapter 3 BUS IMPROVEMENT CONCEPTS Chapter 3 BUS IMPROVEMENT CONCEPTS The purpose of this chapter is to describe potential bus improvement strategies and potential impacts or implications associated with BRT implementation within the existing

More information

Summary: Mercer County Princeton Avenue & Spruce Street Study January 2009

Summary: Mercer County Princeton Avenue & Spruce Street Study January 2009 Summary: Several recent studies have assessed potential development and redevelopment opportunities in the Mercer Crossing area of Trenton, Ewing, and Lawrence. This Princeton Avenue and Spruce Street

More information

MBTA Key Bus Route Improvement Program. Community Meeting Route 1 - Boston

MBTA Key Bus Route Improvement Program. Community Meeting Route 1 - Boston MBTA Key Bus Route Improvement Program Community Meeting Route 1 - Boston January 24, 2011 USES, 566 Columbus Ave., Boston Agenda Welcome and introductions Safety briefing/accommodations Key Bus Route

More information

W.T. WHITE HIGH SCHOOL

W.T. WHITE HIGH SCHOOL Z156-137 TRAFFIC MANAGEMENT PLAN FOR W.T. WHITE HIGH SCHOOL DALLAS, TEXAS DeShazo Project No. 15191 Prepared for: Masterplan 900 Jackson Street, Suite 640 Dallas, Texas 75202 Prepared by: 35 Years of Excellence!

More information

Transportation Impact Study for Abington Terrace

Transportation Impact Study for Abington Terrace Transportation Impact Study for Abington Terrace Abington Township, Montgomery County, PA Sandy A. Koza, P.E., PTOE PA PE License Number PE059911 Prepared by McMahon Associates, Inc. 425 Commerce Drive,

More information

Traffic Impact Memorandum. May 22, 2018

Traffic Impact Memorandum. May 22, 2018 BISHOP PROFESSIONAL DEVELOPMENT BUILDING Proposed Land-use Change & Parking Modification 3601 SW 31st Street Topeka, Kansas 66614 CFS Project No. 185077 Traffic Impact Memorandum May 22, 2018 Prepared

More information

Executive Summary Route 30 Corridor Master Plan

Executive Summary Route 30 Corridor Master Plan Route Corridor Master Plan Project Overview The Route Corridor Master Plan is a coordinated multimodal transportation and land use plan for the entire stretch of Route through East Whiteland Township,

More information

Scarlett Road Bridge & Road Improvements Lambton Park Community School - Gymnasium Tuesday November 28 th, 2017

Scarlett Road Bridge & Road Improvements Lambton Park Community School - Gymnasium Tuesday November 28 th, 2017 Scarlett Road Bridge & Road Improvements Lambton Park Community School - Gymnasium Tuesday November 28 th, 2017 PROJECT LOCATION 2 SCARLETT ROAD BRIDGE Constructed in 1912, the bridge carries 4 active

More information

Key objectives of the survey were to gain a better understanding of:

Key objectives of the survey were to gain a better understanding of: 3 COMMUNITY INPUT Community input is an essential part of corridor studies. For the SR 87 corridor study, VTA staff conducted an extensive online survey of people living and commuting along the corridor.

More information

Transportation 6. A. Transit Center Circulation and Access. 1. Transit Center Circulation

Transportation 6. A. Transit Center Circulation and Access. 1. Transit Center Circulation Transportation 6 This chapter describes the transportation system in and around the Hillsdale Station Area, with a focus on the Transit Center at the relocated Hillsdale Caltrain Station. The transportation

More information

Traffic Circulation & Pedestrian Safety Study

Traffic Circulation & Pedestrian Safety Study Lyons Township High School North Campus La Grange, Illinois Parking Lot Vaughan Building N Main Building Prepared for: Prepared by: July 23, 2015 Contents List of Figures, iii 1. Introduction...1 2. Existing

More information

About the Wilmington Downtown Circulation Study

About the Wilmington Downtown Circulation Study About the Wilmington Downtown Circulation Study Part of the Wilmington i Initiatives partnership Wilmington Area Planning Council City of Wilmington Delaware Department of Transportation Delaware Transit

More information

CITY OF OAKLAND. 27th Street Bikeway Feasibility and Design. Final Report (v3) March 23, Kimley-Horn and Associates, Inc.

CITY OF OAKLAND. 27th Street Bikeway Feasibility and Design. Final Report (v3) March 23, Kimley-Horn and Associates, Inc. CITY OF OAKLAND 27th Street Bikeway Feasibility and Design Final Report (v3) March 23, 2007 PREPARED BY: Kimley-Horn and Associates, Inc. Table of Contents 1. Introduction 3 2. 27 th Street/Bay Place Corridor

More information

Fisher Ave and Snoqualmie Parkway Signal

Fisher Ave and Snoqualmie Parkway Signal Fisher Ave and Snoqualmie Parkway Signal Topics How does the City assess roadway conditions? What is the City s standard? What has occurred at Snoqualmie Parkway and Fisher Ave.? What are we currently

More information

Comment cards and s were received and compiled. Major Concerns/Comments

Comment cards and  s were received and compiled. Major Concerns/Comments Renew Atlanta hosted a business stakeholder open house to discuss the Marietta Street Resurfacing project at. Councilmembers Cleta Winslow and Ivory Lee Young attended the open house, where over 30 businesses

More information

TEMPORARY OCCUPANCY PERMITS. Street Space, Additional Street Space and Temporary Occupancy Permits PUBLIC WORKS CODE : ARTICLE 15, SEC.

TEMPORARY OCCUPANCY PERMITS. Street Space, Additional Street Space and Temporary Occupancy Permits PUBLIC WORKS CODE : ARTICLE 15, SEC. TEMPORARY OCCUPANCY PERMITS Street Space, Additional Street Space and Temporary Occupancy Permits PUBLIC WORKS CODE : ARTICLE 15, SEC. 724 Difference between the 3 permits. Who would apply for the permit?

More information

METHODOLOGY. Signalized Intersection Average Control Delay (sec/veh)

METHODOLOGY. Signalized Intersection Average Control Delay (sec/veh) Chapter 5 Traffic Analysis 5.1 SUMMARY US /West 6 th Street assumes a unique role in the Lawrence Douglas County transportation system. This principal arterial street currently conveys commuter traffic

More information

Transform 66 Project February 4, 2016 Partnering Conference Michigan Department of Transportation American Council of Engineering Companies

Transform 66 Project February 4, 2016 Partnering Conference Michigan Department of Transportation American Council of Engineering Companies Transform 66 Project February 4, 2016 Partnering Conference Michigan Department of Transportation American Council of Engineering Companies Susan Shaw, PE, CCM, DBIA Megaprojects Director Northern Virginia

More information

Paoli Road Improvement Feasibility Study

Paoli Road Improvement Feasibility Study Paoli Road Improvement Feasibility Study & Public Participation Project March 24, 2015 Prepared for: Tredyffrin Township Prepared by: McMahon Associates, Inc. with Town Planning Partnership, LLC Glackin

More information

Southwest Bus Rapid Transit (SW BRT) Functional Planning Study - Executive Summary January 19 LPT ATTACHMENT 2.

Southwest Bus Rapid Transit (SW BRT) Functional Planning Study - Executive Summary January 19 LPT ATTACHMENT 2. Southwest Bus Rapid Transit (SW BRT) Functional Planning Study - Executive Summary 2011 January 19 1 of 19 Introduction This executive summary presents the results of the Southwest Bus Rapid Transit (SW

More information

CastleGlenn Consultants Inc.

CastleGlenn Consultants Inc. February 1 st, 2010 CastleGlenn Consultants Inc. Engineers, Project Managers & Planners Mr. Kevin Yemm Planning and Land Development Richraft Ltd. 2280 St. Laurent Boulevard Suite 201 Ottawa, Ontario (Tel:

More information

MBTA Key Bus Route. Community Meeting Route 1 - Cambridge

MBTA Key Bus Route. Community Meeting Route 1 - Cambridge MBTA Key Bus Route Improvement Program Community Meeting Route 1 - Cambridge Cambridge Senior Center, Central Square Agenda Welcome and introductions Safety briefing/accommodations Key Bus Route Program

More information

February 4, Community Meeting August 2, :30 6:10 Presentation

February 4, Community Meeting August 2, :30 6:10 Presentation 5:30 6:10 Presentation OSU-Cascades Long Range Development Plan Bend, Oregon Community Meeting August 2, 2016 6:10 6:55 Group Exercise 6:55 7:10 Report Back 7:10-7:25 Public Comment 7:25-7:30 Next Steps

More information

North Berwick Parking Survey, Thursday 29th September (07:00-19:00): Duration of Stay - 1 Hour Beat

North Berwick Parking Survey, Thursday 29th September (07:00-19:00): Duration of Stay - 1 Hour Beat North Berwick Parking Survey, Thursday 29th September (7: - 19:): Duration of Stay - 1 Hour Beat 7 Vehicles 6 5 4 3 North Berwick Wday 2: Duration of stay (hrs) by Arrival Time 12 11 1 9 8 7 6 5 4 2 3

More information

Public Hearing Tarrant County. October 11 th, 2012

Public Hearing Tarrant County. October 11 th, 2012 Public Hearing Tarrant County October 11 th, 2012 Public Hearing Agenda Welcome and Project Overview Ms. Maribel P. Chavez, P.E. District Engineer Texas Department of Transportation Fort Worth District

More information

THE LANDMARK AT TALBOT PARK

THE LANDMARK AT TALBOT PARK TRAFFIC IMPACT STUDY FOR THE LANDMARK AT TALBOT PARK IN NORFOLK, VA INTERMODAL ENGINEERING, P.C. OCTOBER, 200 The Landmark at Talbot Park is a proposed redevelopment of the existing apartments along the

More information

Sound Transit Permit Parking Program

Sound Transit Permit Parking Program Sound Transit Permit Parking Program Purpose The purposes of the proposed permit parking program are to increase the number of transit customers accommodated per parking space provided, to improve the

More information

Safe Routes to School Travel Plan 2011

Safe Routes to School Travel Plan 2011 Safe Routes to School Travel Plan 2011 Barley Sheaf Elementary School Barley Sheaf School 80 Barley Sheaf Road Flemington, NJ 08822 Grades: K-4 Introduction Barley Sheaf School is a K-4 elementary school

More information

University Avenue & Farley Avenue/University Bay Drive Area Scenario Base Conditions Multiple concerns

University Avenue & Farley Avenue/University Bay Drive Area Scenario Base Conditions Multiple concerns ped at signalized East of U-Bay North of Campus on Farley Ave./ U-Bay & Westbound Campus North of on Farley Ave./ U-Bay Near VA on MB1: Dual Eastbound Left-Turn Lanes Generally compatible with BRT and

More information

ATTACHMENT 4 - TDM Checklist. TDM Checklist Overview

ATTACHMENT 4 - TDM Checklist. TDM Checklist Overview ATTACHMENT 4 - TDM Checklist TDM Checklist Overview The proposed checklist rates developments on the degree to which they are TDM and transit supportive. Points are assigned based on the level of transit

More information

Wilshire Boulevard Bus Rapid Transit Project

Wilshire Boulevard Bus Rapid Transit Project Los Angeles County Metropolitan Transportation Authority Wilshire Boulevard Bus Rapid Transit Project COMMUNITY MEETINGS November 2008 Agenda Introduction Proposed Project Overview Participating Agencies

More information

Colchester/Riverside/Barrett/ Mill Intersection Study. PAC Meeting #3 September 22, 2016

Colchester/Riverside/Barrett/ Mill Intersection Study. PAC Meeting #3 September 22, 2016 Colchester/Riverside/Barrett/ Mill Intersection Study PAC Meeting #3 September 22, 2016 Tonight s Agenda Review Project Purpose and Need Describe short term and long improvements and changes since public

More information

Washington DC Section of ITE Project Briefing

Washington DC Section of ITE Project Briefing Washington DC Section of ITE Project Briefing November 5, 2015 Renée Hamilton, VDOT, Deputy District Administrator I-66 Outside the Beltway Improvement Area Project Location Virginia 2 Purpose and Need

More information

Clyde Brown Elementary School Millis, MA

Clyde Brown Elementary School Millis, MA Clyde Brown Elementary School Millis, MA Transportation Assessment August 8, 2017 Prepared for: Tappe Architects Six Edgerly Place Boston, MA 02116 Submitted by: Nitsch Engineering 2 Center Plaza, Suite

More information

and older adults and people with disabilities still face barriers when using the pedestrian network and public transportation.

and older adults and people with disabilities still face barriers when using the pedestrian network and public transportation. Background Afterthe1980Olympics,theLakePlacid/NorthElbacommunityadoptedaneconomicstrategy ofdevelopingandmarketingeventstoincreaseareatourism.thisstrategyhasbeenvery successful.overrecentyearsthevolumeofvisitorshasincreased,andthelengthofthe

More information

Presentation of Staff Draft March 18, 2013 COUNTYWIDE TRANSIT CORRIDORS FUNCTIONAL MASTER PLAN

Presentation of Staff Draft March 18, 2013 COUNTYWIDE TRANSIT CORRIDORS FUNCTIONAL MASTER PLAN Presentation of Staff Draft March 18, 2013 COUNTYWIDE TRANSIT CORRIDORS FUNCTIONAL MASTER PLAN Public Outreach Fall 2011: Two community meetings/open houses Fall 2012: Three community meetings/open houses

More information

Presentation to Media. February 27, 2008

Presentation to Media. February 27, 2008 Anacostia Waterfront Nationals Ballpark Transportation Management Plan Presentation to Media February 27, 2008 Overarching Goals of DDOT s Ballpark TMP Organize and manage traffic to ensure pedestrian

More information

Anglo-Chinese School (Barker Road) Anglo-Chinese School (Primary)

Anglo-Chinese School (Barker Road) Anglo-Chinese School (Primary) 5 April 2018 Dear Parents/Guardian, This is a joint letter from the Principals of ACS (Barker Road) and ACS (Primary) concerning road safety issues and the movement of vehicles in the vicinity. A. Road

More information

Welcome! San Jose Avenue Open House August 25, 2015

Welcome! San Jose Avenue Open House August 25, 2015 Welcome! San Jose Avenue Open House August 25, 2015 Vision Zero The City and County of San Francisco adopted Vision Zero San Francisco Vision Zero High Injury Network as a policy in 2014, committing an

More information

Arterial Transitway Corridors Study. Ave

Arterial Transitway Corridors Study. Ave Arterial Transitway Corridors Study Ave January 2012 Arterial Transitway Corridors Study Overview Corridor Features and Demographics 11 study corridors, 95 route miles 86,000 daily rides and half of existing

More information

CDOT s Transportation Plan for the Obama Presidential Center in Jackson Park

CDOT s Transportation Plan for the Obama Presidential Center in Jackson Park CDOT s Transportation lan for the Obama residential Center in Jackson ark May 10, 2018 repared for Jackson ark Watch JacksonarkWatch.org repared by at Hawley,.E. TOE rasmith 16745 West Bluemound Road Brookfield,

More information

THE NACTO MANUALS AND DESIGNING FOR VISION ZERO ZAKI MUSTAFA SHIRLEY ZAMORA

THE NACTO MANUALS AND DESIGNING FOR VISION ZERO ZAKI MUSTAFA SHIRLEY ZAMORA THE NACTO MANUALS AND DESIGNING FOR VISION ZERO ZAKI MUSTAFA SHIRLEY ZAMORA NACTO Design Guides 2 City of Los Angeles Vision Zero 3 Vision Zero Roscoe Boulevard Corridor SHIRLEY ZAMORA TRANSPORTATION ENGINEERING

More information

Fulton Market Streetscape

Fulton Market Streetscape Fulton Market Streetscape Ogden Avenue to Halsted Street Public Meeting Recommended Improvements December 10th, 2014 Meeting Purpose and Goals Present Existing Conditions Community Input and Charrette

More information

Belvedere Heights Streetlights & Sidewalks Improvements Project

Belvedere Heights Streetlights & Sidewalks Improvements Project Westgate/Belvedere Homes Community Redevelopment Agency Belvedere Heights Streetlights & Sidewalks Improvements Project Phase I MPO 2017 Transportation Alternatives Program (TAP) BTPAC Special Workshop

More information

TRAFFIC MANAGEMENT PLAN

TRAFFIC MANAGEMENT PLAN April 19, 018 PK# 415-17.387 TRAFFIC MANAGEMENT PLAN Project: In Dallas, Texas Prepared for: City of Dallas On behalf of: Dallas Independent School District Prepared by: Hunter W. Lemley, P.E. 7557 Rambler

More information

Status February Transportation Priority Projects in Chester County

Status February Transportation Priority Projects in Chester County Transportation Priority Projects in Chester County February 2018 Highway & Trail Projects # Project Scope Current /Phase 1 US 202 over Amtrak Major bridge rehabilitation 17.6 2017-2019 2 US 202 at PA 926

More information

14 TH STREET TRANSPORTATION & STREETSCAPE DESIGN STUDY PLAN B PLAN B TRANSPORTATION & STREETSCAPE RECOMMENDATIONS

14 TH STREET TRANSPORTATION & STREETSCAPE DESIGN STUDY PLAN B PLAN B TRANSPORTATION & STREETSCAPE RECOMMENDATIONS 14 TH STREET TRANSPORTATION & STREETSCAPE DESIGN STUDY PLAN B PLAN B TRANSPORTATION & STREETSCAPE RECOMMENDATIONS 141 Symbols Recommendations - Southern End of 14th Street Study Area Streetscape Each icon

More information

Road Diets FDOT Process

Road Diets FDOT Process Florida Department of TRANSPORTATION Road Diets FDOT Process Humberto Castillero, PE, PTOE Roadway Design Office Purpose of Guide Develop a statewide lane elimination review process Balance state & local

More information

Board of Supervisors February 27, 2017

Board of Supervisors February 27, 2017 : Traffic Analysis Results & Draft Conceptual Plan Board of Supervisors February 27, 2017 Transportation Solutions Building Better Communities Presentation Overview Background Summary of Traffic Analysis

More information

W Seattle Bridge / Duwamish Corridor

W Seattle Bridge / Duwamish Corridor W Seattle Bridge / Duwamish Corridor IDT and Action Report City Council Transportation Committee Mark Bandy, Bill LaBorde, Chisaki Muraki-Valdovinos September 22, 2015 Our mission, vision, and core values

More information

Service Development 1600 Franklin Street, Oakland CA 94612

Service Development 1600 Franklin Street, Oakland CA 94612 Service Development 1600 Franklin Street, Oakland CA 94612 January 11, 2018 Jeff Bond Community Development Director 1000 San Pablo Avenue Albany, CA 94706 Dear Mr. Bond, AC Transit is requesting that

More information