Project update for the Boones Ferry Road Improvement Project Phase 1, Work Order 183.

Size: px
Start display at page:

Download "Project update for the Boones Ferry Road Improvement Project Phase 1, Work Order 183."

Transcription

1 5.1 TO: FROM: SUBJECT: Kent Studebaker, Mayor Members of the City Council Crystal M. Shum, PE, Project Lead Boones Ferry Road Project Engineering Department Project update for the Boones Ferry Road Improvement Project Phase 1, Work Order 183. DATE: January 5, 2018 MEETING DATE: January 16, 2018 ACTION No action is requested. This agenda item is to brief Council on the status of the Boones Ferry Road Improvement Phase 1 Project. INTRODUCTION/BACKGROUND The design portion of the Boones Ferry Road Improvement Project is approaching 95% completion. The project includes the area of Boones Ferry Road from just south of Madrona Street to just north of Lanewood Street. The proposed improvements will enhance the streetscape, make the street safer, and improve access to businesses and nearby residences. Right-of-Way Acquisition Process Right-of-Way acquisition has been taking longer than anticipated. In total, there are 44 acquisition files for 50 properties, of which: Three have been signed off and closed, 23 have agreed to a settlement and most of these are in the process of being signed, 18 are unresolved. Staff is striving to resolve the 18 remaining acquisitions as soon as possible. However the City may need to move forward with condemnation of a few of the remaining properties. Final acquisitions are not anticipated to be closed for another three to six months A Avenue PO BOX 369 Lake Oswego, OR

2 Page 2 Design The Boones Ferry Road Improvement Project is the cornerstone project of the Lake Grove Village Center Plan. It will define the character of Lake Grove through its design and will greatly enhance the safety and overall aesthetics of the corridor. The following elements have been included in the project design: Undergrounding overhead utilities, Bike lanes on both sides of the street, New sidewalks with street trees, street lighting, street furnishings and landscaping, Expanded sidewalk areas, waysides New signalized intersections with pedestrian crossings at Madrona Street, the McDonald s Driveway, and Lanewood Street, Two new mid-block pedestrian crossings, Landscaped medians with left turn lanes, New Stormwater treatment facilities that greatly improve water quality. The design of this project is complex which has led to many challenges, resulting in the final design taking longer than anticipated. Project Advisory Committee The Project Advisory Committee (PAC) is an eight person citizen committee comprised of property and business owners on Boones Ferry Road and neighbors from the Waluga, Lake Forest and Lake Grove neighborhoods. The PAC was formed early in the project, to advise and make community-based recommendations to the Project Team on the design of the streetscape elements. Many PAC members also participated in the Lake Grove Village Center planning effort and previous stages of the Boones Ferry Road process. PAC meetings have been ongoing since the start of design in The PAC s vision has been to make Boones Ferry Road a great street by creating it into a userfriendly, multi-modal gathering area that serves as the centerpiece of Lake Grove for the entire community. Members have collaborated and been involved in selecting streetscape and aesthetic design elements in the public right-of-way including: Street lighting, Street trees, Sidewalks and expanded sidewalk areas (waysides), Landscaping and stormwater facilities, Medians, Intersections, Crosswalks, Street furniture (including water fountains, benches, bike racks), Public art, Public signage (including street names) A Avenue PO BOX 369 Lake Oswego, OR

3 Page 3 Attachment 1 illustrates some of the elements the PAC has assessed. The PAC has also worked to incorporate art/history components into the design that correspond to Lake Grove s identity. They coordinated with the Arts Council to promote and choose symbolic art work, establishing the overarching theme of community with flora, fauna and family along the corridor. Staging Concepts As part of their pre-construction contract, the City tasked Otak, Inc. with developing construction staging concepts using the following construction goals and constraints: Construction Goals: Ensure constructability for the contractor, Maximize safety for workers and public, Minimize business impacts, Minimize traffic impacts, Minimize neighborhood impacts, Maintain pedestrian mobility/ada accessibility, Minimize utility relocation impacts, Minimize overall project schedule/duration, Constrain overall project budget. Constraints: Contractor has the ability to provide a staging plan concept after award of bid based on specified constraints for review and approval by the City. Maintain a minimum of three lanes of traffic, to the extent practical. Maintain existing left turn movements to businesses during construction, to the extent practical. Maintain driveway access for businesses open during construction hours. Maintain ADA pedestrian access and mobility. Comply with specific Temporary Construction Easement (TCE) requirements. Allow for reduction to two travel lanes/flagging during non-peak hours. Allow minor flagging to direct construction traffic into work zone. No designated traffic detours or haul routes permitted through adjacent neighborhoods. Temporary traffic signal configuration may allow lane alignment flexibility. No restrictions on work hours. TCE s can only be used for stated purpose or timeframe as agreed to in the TCE. Maintain utility services, including temporary services, throughout the project. Franchise utilities will be responsive to scheduling and contractor coordination. Maintain storm conveyance and treatment, as necessary. Adhere to: A Avenue PO BOX 369 Lake Oswego, OR

4 Page 4 o Specific school access impacts and construction window agreements o Migratory bird / clearing and grubbing timing o City of Lake Oswego Tree permit restrictions Schedule construction of Lanewood intersection to accommodate U turn, prior to impacting post office access. Using these goals and constraints as guidance, two staging concepts (strip and segment) were developed. The strip concept would have the contractor working on one side of the roadway until all the major improvements are built along the entire project limits. Then the contractor would flip to the other side of the roadway and complete all the major improvements. Once the work on both sides of the roadway is completed, then the median islands would be built. The segment concept would be similar in that the contractor would work on one side of the roadway, flip to the other side of the roadway, and then construct the median islands. However, the work would be confined to certain segments. Once the major work was completed in one segment, the contractor would move to the next segment. Both of these concepts have advantages and disadvantages which are outlined in the comparison chart in Attachment 2. Public Outreach The community-driven process to improve Boones Ferry Road began over a decade ago and has continued as a partnership between involved citizens, business owners and City staff throughout design of the project. The PAC and Project Team have taken a collaborative public participation approach to project design. Public input has also been considered throughout decision-making and included public meetings, website, and comments. The Project Team is now planning outreach efforts for the next phase of the project from final design through to the start of construction. The plan involves targeted outreach to different groups and individuals affected by construction. The main goal is to provide regular, clear, consistent information to keep businesses, residents and the general public informed about the project. This also includes proactively minimizing impacts and supporting businesses during construction. The following outreach efforts and activities are planned during the pre-construction phase: Presentation and update to Lake Grove Business Association provide an update on the project, schedule and outreach efforts planned for the businesses in the project area. Two rounds of comprehensive business canvassing the first round will be to gather current business contact information to develop a comprehensive list, provide project information, gather concerns about construction, confirm business hours of operation, and introduce the project team; the second round will occur prior to construction A Avenue PO BOX 369 Lake Oswego, OR

5 Page 5 starting and provides a follow-up opportunity to collect contact information for businesses who may have been missed in the first round, keep businesses informed about what to expect during construction and build relationships. Community meeting/open house to present the final design to the community. Share information about the project, schedule, what to expect. Neighborhood association meeting updates presentations to the Waluga, Lake Grove, Lake Forest neighborhoods. Walking tour of the project area to show the project improvements. Held prior to construction starting. Meet the Contractor community meeting held prior to construction starting. Introduce the community to the contractor and learn about what to expect during construction. Develop informative materials and tools, some including: o updating and refreshing the project website and listserv, o an update in the Hello LO for early 2018, o establishing a project specific address, contact number and social media hashtag to follow on the city s social media accounts, o creating a factsheet with project information and business canvassing materials, o creating a video about the project, o creating a map of businesses along the corridor. Schedule As previously mentioned, the 95% Plans, Specifications, and Estimate (PS&E) is scheduled to be delivered by the end of this month. Once the 95% PS&E is delivered, ODOT must review the documents. The project cannot continue to advertisement without approval from ODOT. As part of that approval, the City must have all right-of-way acquired and all utility agreements in place. Staff is still working on resolving both of these issues. With the work that still needs to be completed, we anticipate construction could begin in late fall 2018, at the earliest. Construction is expected to take two years to complete. Budget and Estimated Cost The design work for this project is being funded by a $4 million Oregon Department of Transportation (ODOT) Federal Grant, $5 million in proceeds from the City s General Obligation Bond, and $122,000 in City Transportation System Development Charges (SDC). These funding sources are expected to cover costs associated with final design and right-of-way acquisition. Construction will be primarily funded using proceeds from urban renewal bonds from the Lake Grove Village Center Urban Renewal District with some additional SDC funding A Avenue PO BOX 369 Lake Oswego, OR

6 Page 6 95% Design Original Budget Estimate Design, Engineering, and Environmental $2,460, $4,542, Property Acquisition $4,300, $3,500, Construction $17,840, $19,545, Construction Management $1,050, $2,858, Project Management and Administration $1,800, $1,800, Total $27,450, $32,245, RECOMMENDED ACTION No formal action is necessary at this time. Staff is seeking feedback from Council, if there are any concerns with the project as planned. ATTACHMENTS 1. Roadway and Wayside Design 2. Staging Plan Comparison A Avenue PO BOX 369 Lake Oswego, OR

7 I coni c Tr ee Se at wa l l Attachment 1 I coni c Tr ee 3ADABenches Tr ashcan Bi ke Rack Mi dbl ockcr ossi ng Bi ke Rack 7Bi ke Racks Tr ash Can Seat wal l I coni c Tr ee 3ADABenchesand Dr i nki ngfount ai n

8 ATTACHMENT 1 VIC S

9 OLEARY + LGSS ATTACHMENT 1

10 NEW INTERSECTION ATTACHMENT 1

11 RICCARDO S + GUBANC S ATTACHMENT 1

12 ATTACHMENT 1 AARON BROS. + LAVANG ALBERTSON S

13 Staging Plan Comparison Introduction Otak has prepared preliminary staging concepts for the City and utility companies to consider for the construction of the Boones Ferry Road Project. While both options will meet the constraints outlined in the presentation, it is staffs opinion that the segmented approach would have positive outcomes when compared to the proposed project goals for construction. It is important to note that the segmented approach will require buy-in from the franchise utilities. Staff is in discussion with the utilities for their input on the staging options presented. As part of any construction project, the contractor may submit a traffic control and staging plan for the City to consider based on the specification constraints outlined in the bid documents. The contractor proposal may be different from the presented staging options. This emphasizes the importance of identifying the constraints and making them part of the project specifications. Travel lane discussion Maintaining traffic mobility, business access and ensuring an adequate and safe area to construct the project in a timely and cost effective manner is paramount to a successful project. Staff considered three options; 4 travel lanes significantly limits work zone area increasing project duration and cost. 3 lanes, one travel lane each way with a center turn lane provides minimal but adequate work zone area and allows for turn movements into businesses. 2 travel lanes provides additional construction work zone but significantly impacts business access and traffic mobility. Based on constructability and traffic impacts the City will allow reduction to a three lane section during peak hours (6 am to 8 pm). Night time work (8 pm to 6 am) can reduce travel to a two lane section to provide a safe night time work environment for the contractor. The Strip Option would construct the project by completing one side of the project corridor at a time. After both sides are complete the middle section of the roadway would be constructed. The Segment Option would be similar to the strip option but would break the project up into specific segments and would complete major construction one segment at a time, minimizing the impacts to the remainder of the corridor. Staging Concept Matrix Constructability/Flexibility Business Impacts Strip 3 lane travel (+) Allows contractor to work linearly throughout project (-) Limits contractor flexibility to one side to maintain 3 lanes of travel (-) Impacts businesses along entire frontage for extended period Segment 3 lane travel (+) Allows for some flexibility in segment locations and ability to work in one or more areas along the corridor while maintaining 3 lane travel (+) Limits business impacts for shorter time frame during major improvements Traffic Impacts (+) Provides consistency for vehicular traffic (+)Maintains minimum 3 lanes of travel throughout the majority of the project. (-)Provides longer construction zone for vehicles to navigate (+) Maintains minimum 3 lanes of travel through limited work zone, for the majority of project (-) Possible additional lane configuration changes Pedestrian Mobility Neighborhood Impacts Safety (+) Positive attribute (-) Negative attribute (+) Limits ADA mobility considerations to one side of corridor (-) Will require major effort/cost to maintain ADA/Ped mobility along the entire frontage (+) Traffic flow consistency (-) Due to perceived length of construction, may create additional bypass trips through neighborhoods (+) Consistency of traffic control (-) Requires maintenance of traffic control and business access along one side of the entire corridor (+) Limits area required to provide temporary access. Likely reduces overall project cost (+) Due to compact length of construction may mitigate bypass trips through neighborhoods (-) Possible traffic revisions reduces traffic flow consistency which may increase temptation to detour (+) Limits major construction impacts to smaller work zone

Third Street Bridge & Corridor Project

Third Street Bridge & Corridor Project Third Street Bridge & Corridor Project Preparation for the FY2018 budget to commence October 1, 2017, includes funding to address a project that has been considered since 1994. The Third Street bridge

More information

City of Wilsonville 5 th Street to Kinsman Road Extension Project

City of Wilsonville 5 th Street to Kinsman Road Extension Project City of Wilsonville 5 th Street to Kinsman Road Walking Tour & Neighborhood Workshop Summary Report Public Outreach Overview On July 18 th, 2017, the City of Wilsonville hosted a neighborhood walking tour

More information

Proposed. City of Grand Junction Complete Streets Policy. Exhibit 10

Proposed. City of Grand Junction Complete Streets Policy. Exhibit 10 Proposed City of Grand Junction Complete Streets Policy Exhibit 10 1 City of Grand Junction Complete Streets Policy Vision: The Complete Streets Vision is to develop a safe, efficient, and reliable travel

More information

Exhibit 1 PLANNING COMMISSION AGENDA ITEM

Exhibit 1 PLANNING COMMISSION AGENDA ITEM Exhibit 1 PLANNING COMMISSION AGENDA ITEM Project Name: Grand Junction Circulation Plan Grand Junction Complete Streets Policy Applicant: City of Grand Junction Representative: David Thornton Address:

More information

Vision: Traditional hamlet with an attractive business/pedestrian friendly main street connected to adjacent walkable neighborhoods

Vision: Traditional hamlet with an attractive business/pedestrian friendly main street connected to adjacent walkable neighborhoods N D. Focus Area II Vision: Traditional hamlet with an attractive business/pedestrian friendly main street connected to adjacent walkable neighborhoods Transit Road Focus Area II is located in the Hamlet

More information

THE ALAMEDA CONCEPT DESIGN COMMUNITY MEETING 3. A Plan for The Beautiful Way JANUARY 28, 2010

THE ALAMEDA CONCEPT DESIGN COMMUNITY MEETING 3. A Plan for The Beautiful Way JANUARY 28, 2010 CONCEPT DESIGN COMMUNITY MEETING 3 JANUARY 28, 2010 AGENDA INTRODUCTION COMMUNITY INPUT ROADWAY STUDIES STREETSCAPE DESIGN STATIONS DISCUSSION SUMMARY AND DISCUSSION NEXT STEPS CLOSE INTRODUCTION SCHEDULE

More information

Item to be Addressed Checklist Consideration YES NO N/A Required Description Complete Streets Guidelines

Item to be Addressed Checklist Consideration YES NO N/A Required Description Complete Streets Guidelines Passaic County Complete Streets Checklist - Concept Development Project Name Item to be Addressed Checklist Consideration YES NO N/A Required Description Complete Streets Guidelines Existing Plans Have

More information

Atwood Avenue Fair Oaks Avenue Cottage Grove Road

Atwood Avenue Fair Oaks Avenue Cottage Grove Road Atwood Avenue Fair Oaks Avenue Cottage Grove Road Agenda Purpose Review project scope & goals Present design alternatives Gather feedback Answer Questions Format Open House Presentation Q&A Open House

More information

A CHANGING CITY. of Edmonton, it is essential that it reflects the long-term vision of the City.

A CHANGING CITY. of Edmonton, it is essential that it reflects the long-term vision of the City. A CHANGING CITY By the year 2040, Edmonton will be home to more than 1 million people. To accommodate growth and support a healthy and compact city, we need a new approach to development/redevelopment

More information

Borough of Danville, PA Traffic Calming Program Guidelines

Borough of Danville, PA Traffic Calming Program Guidelines Borough of Danville, PA Traffic Calming Program Guidelines Adopted by Borough Council on 1 INTRODUCTION Speeding Traffic is a major concern in the Borough of Danville because of its detrimental impacts

More information

Make Lincoln Highway an economically vibrant corridor that is safe, efficient, and beautiful for local residents and visitors.

Make Lincoln Highway an economically vibrant corridor that is safe, efficient, and beautiful for local residents and visitors. Lincoln Highway Streetscape Plan Stakeholder Workshop #2 Handout Contents Introduction and Project Vision Planning Principles Specific Recommendations including a Proposed Typical Roadway Section Renderings

More information

BETHEL ROAD AND SEDGWICK ROAD CORRIDOR STUDY

BETHEL ROAD AND SEDGWICK ROAD CORRIDOR STUDY DRAFT PLAN City Council Meeting August 14, 2017 STUDY AREA Sedgwick Corridor State Route 160, principal arterial with Class 3 access management designation, commuter and freight route, connection to SR

More information

Omaha s Complete Streets Policy

Omaha s Complete Streets Policy Omaha s Complete Streets Policy (Adopted August 2015) VISION To create great places and enhance our quality of life, the City of Omaha will provide safe, accessible streets for all users. Complete Streets

More information

Community Task Force November 15, 2017

Community Task Force November 15, 2017 Community Task Force November 15, 2017 Welcome and Introductions Project Partners Regional Transportation District (RTD) Colorado Department of Transportation (CDOT) Denver Regional Council of Governments

More information

Lincoln Highway Streetscape Plan Concept Plan

Lincoln Highway Streetscape Plan Concept Plan Lincoln Highway Streetscape Plan Concept Plan November 14, 2014 Introduction This report provides a summary of conceptual transportation, land use, and design recommendations in the Lincoln Highway Streetscape

More information

Diamond Springs Parkway Project

Diamond Springs Parkway Project Diamond Springs Parkway Project Public Information Meeting, Monday, March 18, 2013 330 Fair Lane, Building A, Placerville County Board of Supervisors Meeting Room, 6:30 8:00 p.m. PRESENTED BY: County of

More information

PROJECT OBJECTIVES. Improve vehicle capacity for the intersection. Improve pedestrian and bicycle access

PROJECT OBJECTIVES. Improve vehicle capacity for the intersection. Improve pedestrian and bicycle access COMMUNITY MEETING Project Update March 15, 2010 Purcellville, Virginia OVERVIEW Project need / objectives Project recap Design elements Proposed improvements Summary of project benefits / next steps PROJECT

More information

CONNECTIVITY PLAN. Adopted December 5, 2017 City of Virginia Beach

CONNECTIVITY PLAN. Adopted December 5, 2017 City of Virginia Beach CONNECTIVITY PLAN Adopted December 5, 2017 City of Virginia Beach CONTENTS 1.0 Background & Purpose... 2 2.0 Existing Inventory & Analysis... 3 ViBe District Existing Walking Conditions... 4 3.0 ViBe District

More information

CITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN. Section VIII Mobility Element Goals, Objectives, and Policies

CITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN. Section VIII Mobility Element Goals, Objectives, and Policies CITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN Section VIII Mobility Element Goals, Objectives, and Policies Adopted August 6, 2015 by Ordinance No. 1591 VIII MOBILITY ELEMENT Table of Contents Page Number

More information

Ocean Park Boulevard Green Street Project Alternatives & Trade Offs

Ocean Park Boulevard Green Street Project Alternatives & Trade Offs Planning Commission March 4, 2009 Ocean Park Boulevard Green Street Project Alternatives & Trade Offs Purpose of Tonight s Meeting Review concept plans and options Provide input on alternatives and trade-offs

More information

BOONES FERRY ROAD IMPROVEMENT PROJECT PHASE 1

BOONES FERRY ROAD IMPROVEMENT PROJECT PHASE 1 BOONES FERRY ROAD IMPROVEMENT PROJECT PHASE 1 Project Advisory Committee Meeting Summary Lake Oswego City Hall Council Chambers August 16, 2016-9:00 a.m. to 11:00 a.m. PAC Members in Attendance: Bruce

More information

Executive Summary Route 30 Corridor Master Plan

Executive Summary Route 30 Corridor Master Plan Route Corridor Master Plan Project Overview The Route Corridor Master Plan is a coordinated multimodal transportation and land use plan for the entire stretch of Route through East Whiteland Township,

More information

Technical Working Group November 15, 2017

Technical Working Group November 15, 2017 Technical Working Group November 15, 2017 Welcome and Introductions Project Partners Regional Transportation District (RTD) Colorado Department of Transportation (CDOT) Denver Regional Council of Governments

More information

Basalt Creek Transportation Refinement Plan Recommendations

Basalt Creek Transportation Refinement Plan Recommendations Basalt Creek Transportation Refinement Plan Recommendations Introduction The Basalt Creek transportation planning effort analyzed future transportation conditions and evaluated alternative strategies for

More information

City of Sammamish. Welcome. Issaquah-Fall City Road Improvements Project Phase I Design: 242nd Avenue SE to Klahanie Drive SE

City of Sammamish. Welcome. Issaquah-Fall City Road Improvements Project Phase I Design: 242nd Avenue SE to Klahanie Drive SE Welcome Welcome to the third community meeting for the Issaquah-Fall City Road Improvements Project. AGENDA 6:00 p.m. Welcome and sign-in 6:10 p.m. Presentation 6:50 p.m. Open house Learn about the roadway

More information

Why invest in the 1 Street S.W. Corridor?

Why invest in the 1 Street S.W. Corridor? Why invest in the 1 Street S.W. Corridor? This project is an investment in the Beltline Community and Calgary s economy. It is anticipated that The City s investment along this corridor will help with

More information

Chapter 3 BUS IMPROVEMENT CONCEPTS

Chapter 3 BUS IMPROVEMENT CONCEPTS Chapter 3 BUS IMPROVEMENT CONCEPTS The purpose of this chapter is to describe potential bus improvement strategies and potential impacts or implications associated with BRT implementation within the existing

More information

5.0 Roadway System Plan

5.0 Roadway System Plan Southwest Boise Transportation Study Page 16 5.0 Roadway System Plan The Roadway System Plan outlines roadway improvements in the Initial Study Area. It forecasts future deficiencies on the arterial system,

More information

Ocean Park Boulevard Green Street Project Community Workshop

Ocean Park Boulevard Green Street Project Community Workshop Ocean Park Boulevard Green Street Project Community Workshop 2.2.10 Project Objectives Community Priority: reclaim OPB for public open space. Build upon LUCE principles; neighborhood enhancement, connectivity,

More information

Application of a Complete Street

Application of a Complete Street Application of a Complete Street Southbend to Prima Vista Update May 14, 2018 Meeting Agenda Perspective and History Public input received Typical sections being considered Presentation of the 2-lane master

More information

Southbend to Prima Vista. October 30, Floresta Corridor Master Plan

Southbend to Prima Vista. October 30, Floresta Corridor Master Plan Application of a Complete Street initiative and how it might function operationally 8 8 Southbend to Prima Vista October 30, 2017 Presentation Agenda 2 Perspective and History Traffic projections, Levels

More information

University of Victoria Campus Cycling Plan Terms of Reference. 1.0 Project Description

University of Victoria Campus Cycling Plan Terms of Reference. 1.0 Project Description University of Victoria Campus Cycling Plan Terms of Reference 1.0 Project Description The Campus Cycling Plan, a first for the University, will provide a comprehensive and coordinated approach to support

More information

Adopt Resolution to declare the intent of the City Council to vacate Worthington Street to allow for the widening of Laurel Street.

Adopt Resolution to declare the intent of the City Council to vacate Worthington Street to allow for the widening of Laurel Street. TO: FROM: SUBJECT: Kent Studebaker, Mayor Members of the City Council Erica Rooney, PE, City Engineer Engineering Department Resolution 15 05 Declaring the City s intent to Vacate Worthington Street, Dedicate

More information

Traffic Calming Policy

Traffic Calming Policy Article I. Purpose and Goal. The purpose of this policy is to establish criteria and procedures the City will use to evaluate requests for, and if appropriate, implement traffic calming measures. Neighborhood

More information

o n - m o t o r i z e d transportation is an overlooked element that can greatly enhance the overall quality of life for the community s residents.

o n - m o t o r i z e d transportation is an overlooked element that can greatly enhance the overall quality of life for the community s residents. N o n - m o t o r i z e d transportation is an overlooked element that can greatly enhance the overall quality of life for the community s residents. 84 Transportation CHAPTER 11 INTRODUCTION Transportation

More information

Caltrans Sloat Boulevard Pedestrian Safety Project Response to Community Questions, Comments & Concerns

Caltrans Sloat Boulevard Pedestrian Safety Project Response to Community Questions, Comments & Concerns Caltrans Sloat Boulevard Pedestrian Safety Project Response to Community Questions, Comments & Concerns Revised: May 10, 2016 The California Department of Transportation (Caltrans) is planning various

More information

Tonight is for you. Learn everything you can. Share all your ideas.

Tonight is for you. Learn everything you can. Share all your ideas. Strathcona Neighbourhood Renewal Draft Concept Design Tonight is for you. Learn everything you can. Share all your ideas. What is Neighbourhood Renewal? Creating a design with you for your neighbourhood.

More information

NJDOT Complete Streets Checklist

NJDOT Complete Streets Checklist Background The New Jersey Department of Transportation s Complete Streets Policy promotes a comprehensive, integrated, connected multi-modal network by providing connections to bicycling and walking trip

More information

East Burke Transportation, Safety and Capacity Improvements

East Burke Transportation, Safety and Capacity Improvements East Burke Transportation, Safety and Capacity Improvements The purpose of this project is to increase mobility and improve safety for pedestrians, cyclists, and motor vehicles along VT Route 114 in the

More information

City of Turlock Traffic Calming Program

City of Turlock Traffic Calming Program Table of Contents Introduction... 3 Definitions... 3 Purpose... 3 Goals and Objectives... 3 Policy Statements... 4 Minimum Qualifying Criteria... 6 Traffic Calming Request Process... 7 Step No. 1: Complete

More information

Welcome to the Quebec Alternatives Analysis Public Meeting

Welcome to the Quebec Alternatives Analysis Public Meeting Welcome to the Public Meeting Please sign in. Public Comment Please fill out a comment card and tell us what you think. Check back or comment any time at: www.quebecalternatives.com Project Area Technical

More information

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF OCTOBER 30, 2012

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF OCTOBER 30, 2012 CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF OCTOBER 30, 2012 Item 31, Report No. 39, of the Committee of the Whole, which was adopted without amendment by the Council of the City of Vaughan

More information

Pennsylvania Avenue (CR 484) Design Alternatives Study

Pennsylvania Avenue (CR 484) Design Alternatives Study MEMORANDUM Pennsylvania Avenue (CR 484) Design Alternatives Study Prepared for: APRIL 2016 Prepared By TABLE OF CONTENTS Project Background... 2 Previous Concept... 2 Existing Conditions... 4 New Alternatives...

More information

PROJECT FACT SHEET May 25, 2018

PROJECT FACT SHEET May 25, 2018 SITE CHALLENGES & PROJECT BACKGROUND In 2014, the City of Aspen identified the Castle Creek Bridge and Hallam Street corridor as a deficient link in Aspen s bicycle and pedestrian network. Safe and efficient

More information

Ann Arbor Downtown Street Plan

Ann Arbor Downtown Street Plan 1 Ann Arbor Downtown Street Plan Public Workshop #1 We know that. 2 Public right-of-way (streets, sidewalks, and alleys) make up 30% of the total District area of downtown. Streets need to provide mobility

More information

Saskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening

Saskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening Saskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening We are here today to present the draft plan for the Saskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening project

More information

Lee s Summit Road Improvement Study Public Open House June 7, 2007 Summary of Comment Card Responses

Lee s Summit Road Improvement Study Public Open House June 7, 2007 Summary of Comment Card Responses Lee s Summit Road Improvement Study Public Open House June 7, 2007 Summary of Comment Card Responses Introduction At the Lee s Summit Road Improvement Study Public Open House held Thursday, June 7, 2007

More information

MAG Town of Cave Creek Bike Study Task 6 Executive Summary and Regional Significance Report

MAG Town of Cave Creek Bike Study Task 6 Executive Summary and Regional Significance Report Page 1 MAG Town of Cave Creek Bike Study Task 6 Executive Summary and Regional Significance Report August 1, 2012 MAG Project #481 Page 2 Task 6 Executive Summary and Regional Significance Report Introduction

More information

Information on display. Inside this handout. Triangle Area revisions. Project need displays. Preferred alternative on aerial maps

Information on display. Inside this handout. Triangle Area revisions. Project need displays. Preferred alternative on aerial maps Public information meeting #4 4 to 7 p.m., September 30, 2009 Hales Corners Welcome Thank you for attending this public information meeting for the WIS 100 Corridor Study. Your interest and comments are

More information

Report Purpose To seek Council s approval of the Wye Road Functional Planning Study (January 2015).

Report Purpose To seek Council s approval of the Wye Road Functional Planning Study (January 2015). COUNCIL MEETING Meeting Date: March 10, 2015 Agenda Item #: 13.1 Wye Road Functional Planning Study (January 2015) Report Purpose To seek Council s approval of the Wye Road Functional Planning Study (January

More information

APPENDIX G: INTERSECTION NEEDS AT OKEECHOBEE BOULEVARD

APPENDIX G: INTERSECTION NEEDS AT OKEECHOBEE BOULEVARD APPENDIX G: INTERSECTION NEEDS AT OKEECHOBEE BOULEVARD INTERSECTION NEEDS AT SR 7 and OKEECHOBEE BOULEVARD SR 7 Extension Project Development and Environment (PD&E) Study From Okeechobee Boulevard (SR

More information

Commercial-Vista Corridor Plan Project Management Team. Judith Johnduff, AICP, Associate Transportation Planner Public Works Department

Commercial-Vista Corridor Plan Project Management Team. Judith Johnduff, AICP, Associate Transportation Planner Public Works Department MEMO TO: Commercial-Vista Corridor Plan Project Management Team FROM: DATE: June 1, 2015 Judith Johnduff, AICP, Associate Transportation Planner Public Works Department SUBJECT: Public Events #2 - Summary

More information

PEABODY SQUARE RECONSTRUCTION PROJECT

PEABODY SQUARE RECONSTRUCTION PROJECT FINAL DESIGN PRESENTATION HEARING Thursday April 23, 2015 with Peabody City Council Peabody, Massachusetts 6:00 PM PEABODY SQUARE RECONSTRUCTION PROJECT 239 LITTLETON ROAD, SUITE 3, WESTFORD, MA 01886

More information

CONTENTS EXECUTIVE SUMMARY 1

CONTENTS EXECUTIVE SUMMARY 1 CONTENTS CHAPTER PAGE EXECUTIVE SUMMARY 1 1 ISSUES AND PURPOSE OF THE ANALYSIS 2 1.1 Background 2 1.2 Analysis Area 2 1.3 Issues and Observations 3 1.4 Project and Public Meetings 3 2 LIST OF PREFERRED

More information

City of Seattle Edward B. Murray, Mayor

City of Seattle Edward B. Murray, Mayor City of Seattle Edward B. Murray, Mayor Department of Transportation Scott Kubly, Director Eastlake Community Council 117 E Louisa St. #1 Seattle, WA 98102-3278 January 28, 2016 RE: Roosevelt to Downtown

More information

TOWN OF PORTLAND, CONNECTICUT COMPLETE STREETS POLICY

TOWN OF PORTLAND, CONNECTICUT COMPLETE STREETS POLICY TOWN OF PORTLAND, CONNECTICUT COMPLETE STREETS POLICY I. VISION, GOALS & PRINCIPLES VISION To improve the streets of Portland making them safer and more accessible for all users including pedestrians,

More information

BD RESOLUTION NO RESOLUTION ADOPTING THE VISION ZERO RAMP INTERSECTION STUDY PHASE 1

BD RESOLUTION NO RESOLUTION ADOPTING THE VISION ZERO RAMP INTERSECTION STUDY PHASE 1 BD00 RESOLUTION NO. - RESOLUTION ADOPTING THE VISION ZERO RAMP INTERSECTION STUDY PHASE [NTIP PLANNING] FINAL REPORT WHEREAS, The Vision Zero Ramp Intersection Study Phase was recommended by Commissioner

More information

Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I. OPEN HOUSE June 20, 2017

Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I. OPEN HOUSE June 20, 2017 Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I OPEN HOUSE June 20, 2017 Brooklyn Boulevard (County Road 152) Phase I Project Partners Project Lead Other Project Partners include Brooklyn

More information

North Shore Transportation Improvement Strategy

North Shore Transportation Improvement Strategy North Shore Transportation Improvement Strategy Preliminary, Near-term Recommendation 2016 April Transportation Improvement Strategy (TIS) Comprehensive and Analytical A multi-modal transportation strategy

More information

Mineral Avenue Corridor Assessment. ITE 2017 Western District Annual Meeting San Diego, CA June 21 st

Mineral Avenue Corridor Assessment. ITE 2017 Western District Annual Meeting San Diego, CA June 21 st Mineral Avenue Corridor Assessment ITE 2017 Western District Annual Meeting San Diego, CA June 21 st Biography - Aaron Heumann, PE, PTOE Currently City of Littleton Transportation Engineering Manager 24

More information

RED BANK CORRIDOR. Community Partners Committee Meeting Madisonville Recreation Center. May 21,

RED BANK CORRIDOR. Community Partners Committee Meeting Madisonville Recreation Center. May 21, RED BANK CORRIDOR Community Partners Committee Meeting Madisonville Recreation Center May 21, 2013 RED BANK CORRIDOR PROJECT Create a balance of mobility and access to better serve local communities, businesses

More information

Clackamas County Comprehensive Plan

Clackamas County Comprehensive Plan ROADWAYS The County s road system permits the movement of goods and people between communities and regions, using any of a variety of modes of travel. Roads provide access to virtually all property. They

More information

Improve the livability of our streets by

Improve the livability of our streets by Pedestrian and Traffic Calming Policy March 2018 2 of 6 Neighborhood Traffic Calming Policy The City of Aspen continually strives to protect multimodal function while maintaining a high standard of safety.

More information

June 29, Dear Mr. Walter:

June 29, Dear Mr. Walter: From: CountyBoard@arlingtonva.us To: chickandsandy@msn.com Subject: County Board Response Regarding the Arlington Ridge Road Improvement Project (Intranet Quorum IMA00252707) Date: Wed, 29 Jun 2011 08:09:53-0400

More information

Comments EXECUTIVE SUMMARY

Comments EXECUTIVE SUMMARY Comments 1. Under any Alternatives, MCDOT should provide better at-grade pedestrian crossing of Georgia Avenue and Forest Glen Road, including improved crosswalks with wider medians and adequate signal

More information

Bicycle Master Plan Goals, Strategies, and Policies

Bicycle Master Plan Goals, Strategies, and Policies Bicycle Master Plan Goals, Strategies, and Policies Mobilizing 5 This chapter outlines the overarching goals, action statements, and action items Long Beach will take in order to achieve its vision of

More information

Raymond Avenue: Rightsizing Improved Safety and Pedestrian Experience

Raymond Avenue: Rightsizing Improved Safety and Pedestrian Experience Page 1 of 5 Work With Us Free Newsletter Stay Connected Home About Services Training Projects Placemaking Blog Resources Reference Store Great Public Spaces Image Collection Raymond Avenue: Rightsizing

More information

4APNOIPF Vh, YII PTC CITY COUNCIL AGENDA REPORT. Honorable Mayor and City Council Members. 8K TH 63 River Crossing Bridge Replacement Project

4APNOIPF Vh, YII PTC CITY COUNCIL AGENDA REPORT. Honorable Mayor and City Council Members. 8K TH 63 River Crossing Bridge Replacement Project City of RE 4APNOIPF Vh, X` W\ YII PTC ING, CITY COUNCIL AGENDA REPORT Council Meeting Date: September 26, 2016 To: From: Agenda Item: Honorable Mayor and City Council Members Ron Rosenthal, Engineering

More information

Hale iwa Improvement District Project

Hale iwa Improvement District Project Hale iwa Improvement District Project Hale iwa, North Shore, O ahu October 10, 2017 Public Informational Meeting Environmental Impact Statement Preparation Notice Waialua Elementary School 67-020 Waialua

More information

DRAFT - CITY OF MEDFORD TRANSPORTATION SYSTEM PLAN Roadway Cross-Sections

DRAFT - CITY OF MEDFORD TRANSPORTATION SYSTEM PLAN Roadway Cross-Sections Roadway Cross-Sections Medford s roadway cross-section standards apply to new and reconstructed roads. The crosssections take into consideration roadway function and operational characteristics, including

More information

City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County

City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County Public Involvement Meeting Thursday, November 10, 2016 5:30 to 7 P.M. Festival Foods 810 E. Washington

More information

Southview Blvd & 3 rd Avenue Improvement Project. Public Open House December 4, to 7pm

Southview Blvd & 3 rd Avenue Improvement Project. Public Open House December 4, to 7pm Southview Blvd & 3 rd Avenue Improvement Project Public Open House December 4, 2014 5 to 7pm Southview Blvd & 3 rd Avenue Public Information Meeting Agenda Presentation 5:30 to 6:15 pm Purpose of Project

More information

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 Complete Streets Checklist MetroPlan Orlando s Complete Streets Checklist is an internal planning tool for staff to further implementation of

More information

Chapter 3: Multi-Modal Circulation and Streetscapes

Chapter 3: Multi-Modal Circulation and Streetscapes CHAPTER 3: MULTI-MODAL CIRCULATION AND STREETSCAPES Chapter 3: Multi-Modal Circulation and Streetscapes Overview Streetscape improvements have already been completed for Depot Street between Main Avenue

More information

Project Update May 2018

Project Update May 2018 Project Update May 2018 Dakota County, in cooperation with the City of Lakeville, is planning to reconstruct 202 nd Street West (County Road 50) from Holyoke Avenue to Cedar Avenue (County Road 23). 202

More information

REGIONAL BICYCLE AND PEDESTRIAN DESIGN GUIDELINES

REGIONAL BICYCLE AND PEDESTRIAN DESIGN GUIDELINES REGIONAL BICYCLE AND PEDESTRIAN DESIGN GUIDELINES November 16, 2011 Deb Humphreys North Central Texas Council of Governments Bicycle and Pedestrian Advisory Committee Snapshot of the Guide 1. Introduction

More information

REPORT OF MEETING DOWNTOWN CROSSING PHASE 2 PUBLIC INFORMATION MEETING. Ives Main Library 133 Elm Street, New Haven, Connecticut September 29, 2014

REPORT OF MEETING DOWNTOWN CROSSING PHASE 2 PUBLIC INFORMATION MEETING. Ives Main Library 133 Elm Street, New Haven, Connecticut September 29, 2014 REPORT OF MEETING DOWNTOWN CROSSING PHASE 2 PUBLIC INFORMATION MEETING Ives Main Library 133 Elm Street, New Haven, Connecticut September 29, 2014 Technical Teams City of New Haven Honorable Toni M. Harp,

More information

Governance and Priorities Committee Report For the July 2, 2015 Meeting

Governance and Priorities Committee Report For the July 2, 2015 Meeting CITY OF VICTORIA For the July 2, 2015 Meeting To: Governance and Priorities Committee Date: From: Subject: Brad Dellebuur, A/Assistant Director, Transportation and Parking Services Executive Summary The

More information

5 CIRCULATION AND STREET DESIGN

5 CIRCULATION AND STREET DESIGN 5 CIRCULATION AND STREET DESIGN This chapter describes circulation and streetscape improvements proposed for the Northwest Chico Specific Plan Area. It includes detailed design specifications for existing

More information

Road Diets FDOT Process

Road Diets FDOT Process Florida Department of TRANSPORTATION Road Diets FDOT Process Humberto Castillero, PE, PTOE Roadway Design Office Purpose of Guide Develop a statewide lane elimination review process Balance state & local

More information

Ocean Park Boulevard Streetscape Improvement Project Alternatives & Trade Offs

Ocean Park Boulevard Streetscape Improvement Project Alternatives & Trade Offs City Council Study Session January 27, 2009 Ocean Park Boulevard Streetscape Improvement Project Alternatives & Trade Offs Scope of Work Purpose of Tonight s Meeting Review work to date and direct staff

More information

Project Overview. Rolling Road Widening Fairfax County. Get Involved. Design Public Hearing. Contact Information

Project Overview. Rolling Road Widening Fairfax County. Get Involved. Design Public Hearing. Contact Information Get Involved VDOT representatives will review and evaluate information received as a result of this meeting. Please fill out the comment sheet provided in this brochure if you have any comments or questions.

More information

Citizen Advisory Group Meeting #8 May 5, Welcome. Today s meeting will focus on: Land Use & Transportation CHARLOTTEPLANNING.

Citizen Advisory Group Meeting #8 May 5, Welcome. Today s meeting will focus on: Land Use & Transportation CHARLOTTEPLANNING. Citizen Advisory Group Meeting #8 May 5, 2010 Welcome. Today s meeting will focus on: Land Use & Transportation CHARLOTTEPLANNING.ORG Meeting Agenda Handouts: o Meeting Agenda o Summary of East Seventh

More information

NEIGHBORHOOD TRAFFIC CALMING POLICY

NEIGHBORHOOD TRAFFIC CALMING POLICY NEIGHBORHOOD TRAFFIC CALMING POLICY I. PURPOSE The City of Kent continually strives to strengthen and protect its neighborhoods by improving the quality of life in residential areas. Traffic conditions

More information

ARLINGTON COUNTY, VIRGINIA

ARLINGTON COUNTY, VIRGINIA ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of October 15, 2016 DATE: October 7, 2016 SUBJECT: Adoption of amendments to the Master Transportation Plan (MTP) to create a new Pedestrian

More information

San Jose Transportation Policy

San Jose Transportation Policy San Jose Transportation Policy Protected Intersections in LOS Policies to Support Smart Growth Presented by: Manuel Pineda City of San Jose Department of Transportation Bay Area Map San Francisco Oakland

More information

PROPOSED BICYCLE AND PEDESTRIAN FACILITY Vicinity of Route 123/I-495 Interchange Tysons, Fairfax County, Virginia

PROPOSED BICYCLE AND PEDESTRIAN FACILITY Vicinity of Route 123/I-495 Interchange Tysons, Fairfax County, Virginia PROPOSED BICYCLE AND PEDESTRIAN FACILITY Vicinity of Route 123/I-495 Interchange Tysons, Fairfax County, Virginia PRELIMINARY ENGINEERING REPORT Prepared for: Prepared by: July 2017 Table of Contents 1

More information

Derby Street. Project Updates. Salem, Massachusetts

Derby Street. Project Updates. Salem, Massachusetts Derby Street Project Updates Salem, Massachusetts September 13, 2017 Project Limits Derby Street Project Objectives 1. Improve complete streets elements on Derby Street 2. Improve sidewalks on finger streets

More information

Broad Street Bicycle Boulevard Design Guidelines

Broad Street Bicycle Boulevard Design Guidelines Broad Street Bicycle Boulevard Design Guidelines Building from the strategies introduced in the 2013 Bicycle Transportation Plan and community input received thus far, City Transportation Staff have identified

More information

CITY OF BLOOMINGTON COMPLETE STREETS POLICY

CITY OF BLOOMINGTON COMPLETE STREETS POLICY CITY OF BLOOMINGTON COMPLETE STREETS POLICY POLICY OBJECTIVE: The City of Bloomington will enhance safety, mobility, accessibility and convenience for transportation network users of all ages and abilities,

More information

WHITE STREET/ ENGLISH PLAZA STREETSCAPE IMPROVEMENT PROJECT

WHITE STREET/ ENGLISH PLAZA STREETSCAPE IMPROVEMENT PROJECT WHITE STREET/ ENGLISH PLAZA STREETSCAPE IMPROVEMENT PROJECT 1 Project Goals 1 Improved Safety: Lighting, Multi-Modal Circulation, Emergency Access, Tripping Hazards; Stormwater 4 Environmental Performance:

More information

Complete Streets Initiative Update

Complete Streets Initiative Update Complete Streets Initiative Update UrbanAdvantage Council Transportation and Environment Committee April 23, 2012 Presentation Purpose Update the Council Committee on community workshops results and preliminary

More information

Owl Canyon Corridor Project Overview and Summary

Owl Canyon Corridor Project Overview and Summary Owl Canyon Corridor Project Overview and Summary December 22, 2008 The Owl Canyon corridor (generally the connection between the I-25 / Larimer County Road 70 interchange and the US 287 / Larimer County

More information

CURBSIDE ACTIVITY DESIGN

CURBSIDE ACTIVITY DESIGN 5 CURBSIDE ACTIVITY DESIGN This chapter provides design guidance for separated bike lanes adjacent to curbside activities including parking, loading and bus stops. Typical configurations are presented

More information

PROJECT FACT SHEET March 21, 2018

PROJECT FACT SHEET March 21, 2018 SITE CHALLENGES & PROJECT BACKGROUND In 2014, the City of Aspen identified the Castle Creek Bridge and Hallam Street corridor as a deficient link in Aspen s bicycle and pedestrian network. Safe and efficient

More information

El Camino Real Specific Plan. TAC/CAC Meeting #2 Aug 1, 2018

El Camino Real Specific Plan. TAC/CAC Meeting #2 Aug 1, 2018 El Camino Real Specific Plan TAC/CAC Meeting #2 Aug 1, 2018 Land Use Alternatives Goals and Tradeoffs Parks & open space Housing Retail & services Civic spaces Parking Community gathering spaces 3 Alternatives

More information

In station areas, new pedestrian links can increase network connectivity and provide direct access to stations.

In station areas, new pedestrian links can increase network connectivity and provide direct access to stations. The Last Mile Planning for Pedestrians Planning around stations will put pedestrians first. Making walking to stations safe and easy is important; walking will be a part of every rapid transit Accessible

More information

Corpus Christi Metropolitan Transportation Plan Fiscal Year Introduction:

Corpus Christi Metropolitan Transportation Plan Fiscal Year Introduction: Introduction: The Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA-LU) has continued the efforts started through the Intermodal Surface Transportation Efficiency

More information

TLC GRANT K / WATER STREETSCAPE ENHANCEMENTS WILL HANDSFIELD, AICP TRANSPORTATION DIR, GEORGETOWN BID

TLC GRANT K / WATER STREETSCAPE ENHANCEMENTS WILL HANDSFIELD, AICP TRANSPORTATION DIR, GEORGETOWN BID TLC GRANT K / WATER STREETSCAPE ENHANCEMENTS Applied Fall 15 Awarded Winter 15/ 16 Notice to Proceed Spring 16 Completion Summer 16 Community Outreach Ongoing WILL HANDSFIELD, AICP TRANSPORTATION DIR,

More information

Chapter 2: Standards for Access, Non-Motorized, and Transit

Chapter 2: Standards for Access, Non-Motorized, and Transit Standards for Access, Non-Motorized, and Transit Chapter 2: Standards for Access, Non-Motorized, and Transit The Washtenaw County Access Management Plan was developed based on the analysis of existing

More information