1 Hale iwa Improvement District Project Hale iwa, North Shore, O ahu October 10, 2017 Public Informational Meeting Environmental Impact Statement Preparation Notice Waialua Elementary School Waialua Beach Road Waialua, HI Department of Design and Construction City and County of Honolulu
2 Meeting Purpose / Desired Outcomes 2 Community and landowners understand the alternatives, issues and process. Obtain community and landowner input on the ID alternatives and on environmental, social and technical issues for evaluation in the EIS. Answer questions about the project, the ID and the EIS process.
3 Introductions 3 City and County of Honolulu Robert Kroning, P.E., DDC Director Ann Shimatsu, P.E., DDC Project Manager, Civil Division Bob Sarae, P.E., DDC Civil Division Harrison Rue, DPP, Community Building and TOD Administrator R. M. Towill Corporation Jimmy Yamamoto, P.E., Vice President Jim Niermann, AICP LEED AP, Principal Planner Gordon Ring, P.E., LEED AP, Principal Engineer Michele Leong, Planner
4 Opening Remarks 4
5 Housekeeping 5 Sign-in Sheet Meeting Documentation Comment Forms & Box Refreshments Restrooms
6 Meeting Agenda 6 Presentation by the Project Team. Project Update Conceptual Alternatives for EIS EISPN Comment Period Full-group Discussion / Q & A
7 Ground Rules 7 Stick to the agenda. Save questions for the end. Reference slide #. Listen respectfully. Respond to ideas and issues, not individuals.
8 Hale iwa Improvement District Project Area 8
9 Improvement District 9 City Council Resolution , CD1 1. Walkways 2. Landscaping 3. Undergrounding Utilities ROH Chapter 14, Articles 23 to 29 Establishes Improvement District Process
10 Improvement District Process 10 Costs shared by the City and adjacent landowners. Utility companies share a portion of utility costs. Basis for cost assessment may include: Street frontage / lot area Land use Type of improvements Assessed value of property The intent is to make it work.
11 Complete Streets Ordinance 11 Requires the City to employ a multi-modal approach to roadway projects. Goal is to balance needs of pedestrians, bicycles, transit and motor vehicles. Requires multi-modal traffic study. ROH Section 14-33
12 Community Involvement / EIS Process 12 Community Involvement, Agency Consultation Background Research Special Studies Community Interviews Agency Consultation Site Conditions Analysis Engineering Analysis Preliminary Design Concepts Workshops #1 & #2 Prelim. Alternatives Multi modal Study Design Meetings EIS Prep Notice Pre Draft EIS Meeting(s) Alternatives Review Draft EIS Draft EIS Meeting(s) Public Review Period Final EIS Preparation Pre Final EIS Meeting ID Alternative Final EIS / ROD
13 Current Status 13 EISPN Comment Period Conceptual Alternatives Multi-modal Traffic Study in progress Agency Consultation ongoing Special Studies for EIS ongoing
14 Key Feedback So Far 14 Strong support for pedestrian improvements Preserve rural character and human scale Keep the ID improvements simple Preference to keep the road as-is, no left-turn lanes No strong preference for overhead vs. underground utilities (except costs) Parking concern over loss of street frontage parking, support for centralized parking Concern about ID costs and allocation Concern about losing land to the project Construction impacts hard on small businesses
15 Hale iwa Improvement District 15
16 Hale iwa Improvement District 16
17 Existing Conditions 17 Two-lane, rural commercial street ROW width varies from 30 to 50 No existing walkways except in isolated locations. No bike lanes. Buildings located near roadway Accustomed street-front parking Trees and utilities located near roadway Bus service through town 13 bus stops Congested conditions during daytime (visitor traffic, busses) 60-foot road widening setback
18 Design Criteria 18 Low-Speed Road Drainage maintain exist. flow pattern Multi-modal design - improve experience for pedestrians, bicyclists and transit Consider Complete Streets features Dimension Guidelines 22 Roadway 6 Walkway (8 at bus stops and commercial core) 5 Bike lane (If Provided) 4 Buffer for landscaping, drainage and furniture Overhead and Underground Utilities
19 Design Summary 19 Conceptual Alternatives Alt ROW Alt 2 42 ROW Alt 3 52 to 56 Complete Streets Treatments Raised Crosswalk Bike Lanes Furniture zone / buffer Traffic Circles Parking perpendicular, parallel, angled
20 Typical Road Sections 65 to 69 ROW 20 Dimensions may be modified in final design.
21 Typical Road Sections 42 ROW 21 Dimensions may be modified in final design.
22 Typical Road Sections 52 to 56 ROW 22 Dimensions may be modified in final design.
23 Alternative 1: 65 to 69 ROW 23
24 Alternative 1: 65 to 69 ROW 24
25 Alternative 2: 42 ROW 25
26 Alternative 2: 42 ROW 26
27 Alternative 3: 52 to 56 ROW 27
28 Alternative 3: 52 to 56 ROW 28
29 Complete Streets 29 The City is required by ordinance to consider complete streets principles in transportation project planning Improves mobility for all street users. Good for business. Features that might work in Hale iwa: Bicycle Facilities Raised Crosswalks Furniture Zone / Buffer Parklets Traffic Circles
30 Bicycle Facilities 30 5-ft. wide bike lane, separated from walkway Sharrows share the travel lane with motor vehicles Improve bicycling convenience and comfort to encourage less reliance on motor vehicles Connect to regional bike path system Equitable access for kids, teens, workers
31 Bicycle Facilities 31
32 Raised Crosswalks 32 Table-top crosswalk across travel lane. Raised intersection. Provides traffic calming (speed table). Improves visibility for drivers and pedestrians. Creates landmark.
33 Raised Crosswalks 33
34 Furniture Zone / Buffer 34 4-foot wide area to provide separation from travel way and pedestrian walkway. Used for: Landscaping Drainage Utilities Street Furniture (benches, signs, trash cans)
35 Furniture Zone / Buffer 35
36 Furniture Zone / Buffer 36
37 Furniture Zone / Buffer 37
38 Parklet 38 Parklet Seating, landscape features, shade/shelter. Provides social/respite space, creates a landmark. Can be customized to fit into available space, minimizing impacts to the adjacent area.
39 Parklet 39
40 Parklet 40
41 Traffic Circles 41 Eliminates stop-control, allows continuous flow. Alternative to left turn lanes. Allows cars to make a U-turn instead of left turns. Improves motor vehicle movement and pedestrian access into adjacent properties. Minimizes turn conflicts. Creates a landmark/entry feature.
42 Traffic Circles Hale`iwa Road 42
43 Traffic Circles Hale`iwa Road 43
44 Parking 44 Space availability ROW, physical constraints. Safety / integration of parking with walkway design. Convenience / business needs (customers, loading, deliveries). Design: Perpendicular Parallel Angled
45 Parking 45
46 Parking 46 Street frontage parking: Parallel parking. Pā ia, Maui Makawao, Maui
47 Parking 47 Street frontage parking: angled parking. Reverse angle safety parking Nose-in angle parking San Francisco, CA Makawao, Maui
48 Bus Stops Bus stops create breaks in traffic that facilitate left turns and pedestrian crossings. 3 bus stops are candidates for removal due to low ridership and proximity to adjacent bus stops. B B B B B B B B B B B B B
49 Alternatives Cost Comparison 49 Cost categories: Construction mobilization/demobilization Demolition Utility Relocation electrical/telcom, water, lighting Paving, Concrete Walkways & Driveways Drainage improvements Landscaping and street furnishings Land acquisition Tie-in to property frontage Building retrofit
50 Alternatives Cost Comparison Order of magnitude costs (subject to change pending design): 50 Cost Category Alternative 1 Alternative 2 Alternative 3 Construction Mob, Traffic Control $3,250,000 $1,710,000 $2,375,000 Travel way Construction $5,650,000 $1,500,000 $1,500,000 Bike Lane Construction $1,120,000 $0 $1,120,000 Walkway Construction $3,030,000 $2,440,000 $2,590,000 Furniture Zone landscaping & features $600,000 $300,000 $300,000 Utility Relocation $4,340,000 $1,990,000 $2,530,000 Drainage Improvements $6,425,000 $2,560,000 $3,000,000 Contingency (20%) $4,885,000 $2,100,000 $2,685,000 Total $29,300,000 $12,600,000 $16,100,000 Does not include costs for: Land / Easement Acquisition Building Upgrades / Retrofit Tie-ins to existing property frontage Undergrounding Electrical cost estimate = $14,200,000 Traffic Circle cost estimate = $600,000 (excluding land acquisition and property adjustments)
51 Basis for ID Cost Allocation 51 Street frontage / lot area Land use / zoning Type of improvements Value of existing, impacted improvements Assessed market value of property Utility company cost-share
52 Project Schedule 52 Key Project Milestones: Complete Project Alternative Designs for Inclusion in EIS Summer 2018 Complete EIS Summer 2019 Complete Preliminary ID Report Fall 2020 Council Action on the Preliminary ID Report 2021
53 Q & A 53 Listen respectfully. Respond to ideas and issues, not individuals One person speaks at a time. Allow everyone to speak once before speaking a second time. Keep comments and discussion concise and to the point.
54 Q & A 54
55 What s Next? 55 EISPN Comment Period October 23, 2017 Finalize multi-modal study and alternatives. Prepare Draft EIS for publication Fall Work with City agencies to review alternatives. Next community meeting summer 2018.
56 56 EISPN Comments Due: October 23, 2017 Ms. Ann Shimatsu, P.E., Project Manager Department of Design and Construction City and County of Honolulu 650 South King Street, 15 th Floor Honolulu, HI 96813
57 Contact: 57 James Niermann, AICP, LEED AP Planning Project Coordinator Phone: (808) R. M. Towill Corporation 2024 North King Street Suite 200 Honolulu, Hawaii 96819
58 Department of Design and Construction City and County of Honolulu MAHALO
Chapter 2: Standards for Access, Non-Motorized, and Transit
Standards for Access, Non-Motorized, and Transit Chapter 2: Standards for Access, Non-Motorized, and Transit The Washtenaw County Access Management Plan was developed based on the analysis of existing
More informationCity of Wilsonville 5 th Street to Kinsman Road Extension Project
City of Wilsonville 5 th Street to Kinsman Road Walking Tour & Neighborhood Workshop Summary Report Public Outreach Overview On July 18 th, 2017, the City of Wilsonville hosted a neighborhood walking tour
More informationActive Transportation Facility Glossary
Active Transportation Facility Glossary This document defines different active transportation facilities and suggests appropriate corridor types. Click on a facility type to jump to its definition. Bike
More informationAGENDA ITEM SUMMARY SPECIAL AGENDA ITEM NO. _1A_
AGENDA ITEM SUMMARY AGENCY: City Council MEETING DATE: June 25, 2012 DEPARTMENT: Community Dev PREPARED BY: T Spade DEPT. DIR. APPROVAL: MJ CITY MGR. APPROVAL: LR PRESENTED BY: T Spade TITLE: RECEIVE REPORT
More informationHARRISON STREET/OAKLAND AVENUE COMMUNITY TRANSPORTATION PLAN
HARRISON STREET/OAKLAND AVENUE Community Workshop #4: Draft Plan Review December 3, 2009 D E S I G N, C O M M U N I T Y & E N V I R O N M E N T INTRODUCTIONS Key Project Staff: Alisa Shen, Project Manager,
More informationApplication of a Complete Street
Application of a Complete Street Southbend to Prima Vista Update May 14, 2018 Meeting Agenda Perspective and History Public input received Typical sections being considered Presentation of the 2-lane master
More informationWest Dimond Blvd Upgrade Jodhpur Street to Sand Lake Road
West Dimond Blvd Jodhpur St to Sand Lake CSS Transportation Project Summary Municipality of Anchorage Project # 05 005 Project Manager: John Smith, P.E. (MOA PM&E) Project Administrator: Julie Makela,
More informationCyclists and Bikeways: What s your match? A guide to bikeway options for a variety of cyclists
Cyclists and Bikeways: What s your match? guide to bikeway options for a variety of cyclists The workshop and this resource were made possible by funding from the Province of Ontario via the Ministry of
More informationItem to be Addressed Checklist Consideration YES NO N/A Required Description Complete Streets Guidelines
Passaic County Complete Streets Checklist - Concept Development Project Name Item to be Addressed Checklist Consideration YES NO N/A Required Description Complete Streets Guidelines Existing Plans Have
More informationTelegraph Avenue Complete Streets DRAFT Recommendations. Oakland Public Works Department September 11 and 13, 2014 Open Houses
Telegraph Avenue Complete Streets DRAFT Recommendations Oakland Public Works Department September 11 and 13, 2014 Open Houses Presentation Overview What are complete streets? What problem are we trying
More informationExhibit 1 PLANNING COMMISSION AGENDA ITEM
Exhibit 1 PLANNING COMMISSION AGENDA ITEM Project Name: Grand Junction Circulation Plan Grand Junction Complete Streets Policy Applicant: City of Grand Junction Representative: David Thornton Address:
More informationCONNECTIVITY PLAN. Adopted December 5, 2017 City of Virginia Beach
CONNECTIVITY PLAN Adopted December 5, 2017 City of Virginia Beach CONTENTS 1.0 Background & Purpose... 2 2.0 Existing Inventory & Analysis... 3 ViBe District Existing Walking Conditions... 4 3.0 ViBe District
More informationOcean Park Boulevard Streetscape Improvement Project Alternatives & Trade Offs
City Council Study Session January 27, 2009 Ocean Park Boulevard Streetscape Improvement Project Alternatives & Trade Offs Scope of Work Purpose of Tonight s Meeting Review work to date and direct staff
More informationAPPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016
APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 Complete Streets Checklist MetroPlan Orlando s Complete Streets Checklist is an internal planning tool for staff to further implementation of
More informationComplete Streets. Complete Streets and other City Initiatives. City & County Initiatives. Honolulu Complete Streets Program
City & County Initiatives Complete Streets and other City Initiatives Health and the Built Environment Hawaii Public Health Conference Mark Garrity Department of Transportation Services City & County of
More informationBicycle and Pedestrian Advisory Committee (BPAC) November 21, 2013
Bicycle and Pedestrian Advisory Committee (BPAC) November 21, 2013 OVERALL LAND USE CONCEPT Overall Broadway Valdez District: 95.5 acres (35.1 acres right-of ways + 60.4 acres developable land) Plan Subareas:
More informationMultimodal Through Corridors and Placemaking Corridors
68 Multimodal Through Corridors and Placemaking Corridors Corridors have different functions in a region. Some corridors are used to get smoothly and rapidly through a region or to get quickly to major
More informationREGIONAL BICYCLE AND PEDESTRIAN DESIGN GUIDELINES
REGIONAL BICYCLE AND PEDESTRIAN DESIGN GUIDELINES November 16, 2011 Deb Humphreys North Central Texas Council of Governments Bicycle and Pedestrian Advisory Committee Snapshot of the Guide 1. Introduction
More informationRoadway Classification Design Standards and Policies. Pueblo, Colorado November, 2004
Roadway Classification Design Standards and Policies Pueblo, Colorado November, 2004 Table of Contents Page Chapter 1. General Provisions 1.1 Jurisdiction 3 1.2 Purpose and Intent 3 1.3 Modification 3
More informationTonight is for you. Learn everything you can. Share all your ideas.
Strathcona Neighbourhood Renewal Draft Concept Design Tonight is for you. Learn everything you can. Share all your ideas. What is Neighbourhood Renewal? Creating a design with you for your neighbourhood.
More informationEXECUTIVE SUMMARY. Vision
Vision Walking and bicycling in Salt Lake City will be safe, convenient, comfortable, and viable transportation options that connect people to places, foster recreational and economic development opportunities,
More informationBROOKLAND Multi-Modal Transportation & Streetscape Study* NE Washington, DC
BROOKLAND Multi-Modal Transportation & Streetscape Study* NE Washington, DC The study s goal is to create a multi-modal transportation and streetscape design plan to increase transportation efficiency,
More informationOrg Chart. Steering. Committee. Project Advisory. Committee. Nicole Losch, PTP Senior Transportation. Bryan Davis, AICP Senior Transportation
1 Org Chart Project Advisory Committee Steering Committee Nicole Losch, PTP Senior Transportation Planner Bryan Davis, AICP Senior Transportation Planner Jonathan Slason, PE Project Manager Diane Meyerhoff
More informationMalabar Road (SR 514) PD&E. Town of Malabar Briefing (July 17, 2017)
Malabar Road (SR 514) PD&E Town of Malabar Briefing (July 17, 2017) 1 Agenda Project limits and briefing focus PD&E process and project status Public and agency project comments Review Recommended Alternatives:
More informationRZC Appendix 8A Marymoor Subarea Street Requirements
RZC Appendix 8A Marymoor Subarea Street Requirements For additional design details for Marymoor Subarea infrastructure, refer to the 2017 Marymoor Subarea Infrastructure Planning Report. STREET REQUIREMENTS
More informationCURBSIDE ACTIVITY DESIGN
5 CURBSIDE ACTIVITY DESIGN This chapter provides design guidance for separated bike lanes adjacent to curbside activities including parking, loading and bus stops. Typical configurations are presented
More informationComplete Streets. Designing Streets for Everyone. Sarnia
Complete Streets Designing Streets for Everyone Sarnia Complete Streets ~ Sarnia ~ 2018 Introduction Our City is made up of a network of streets that we use to go for a walk, cycle to work, drive to the
More informationPennDOT Access Management Model Ordinances Training
PennDOT Access s Training Trainers: Chad Dixson, AICP, TPD Angela Watson, PB Objective of Today Assist Pennsylvania s municipalities and transportation professionals in better understanding the benefits
More informationItem No. 14 Town of Atherton
Item No. 14 Town of Atherton CITY COUNCIL STAFF REPORT CONSENT AGENDA TO: THROUGH: FROM: HONORABLE MAYOR AND CITY COUNCIL GEORGE RODERICKS, CITY MANAGER MICHAEL KASHIWAGI, COMMUNITY SERVICES DIRECTOR MARTY
More informationOcean Park Boulevard Green Street Project Alternatives & Trade Offs
Planning Commission March 4, 2009 Ocean Park Boulevard Green Street Project Alternatives & Trade Offs Purpose of Tonight s Meeting Review concept plans and options Provide input on alternatives and trade-offs
More informationOmaha s Complete Streets Policy
Omaha s Complete Streets Policy (Adopted August 2015) VISION To create great places and enhance our quality of life, the City of Omaha will provide safe, accessible streets for all users. Complete Streets
More informationExecutive Summary Route 30 Corridor Master Plan
Route Corridor Master Plan Project Overview The Route Corridor Master Plan is a coordinated multimodal transportation and land use plan for the entire stretch of Route through East Whiteland Township,
More informationMeade Street Bridge Design Alternative Study
Meade Street Bridge Design Alternative Study Preferred Alternative Presentation Stakeholder Meeting #3 June 23, 2011 Presented by: Dan Biggs, RLA Meeting Agenda Purpose: 1. Review Meeting #2 Feedback 2.
More informationDISTRICT BICYCLE PROGRAM
DISTRICT BICYCLE PROGRAM TxDOT Fort Worth District Public Hearing Bicycle Use on the State Highway System Public Hearing Agenda 1 2 3 4 5 6 Introduction Susan Howard TxDOT Public Involvement Specialist
More informationCURB EXTENSIONS BULB OUTS DPS 201 NECKDOWNS
CURB EXTENSIONS BULB OUTS DPS 201 NECKDOWNS WHY WHEN & WHERE When Limited Sight Distance Pedestrians & Vehicles Vehicles and Signs Want to put two curb ramps in Discourage High speed turning High number
More informationCity of Charlottesville Bicycle and Pedestrian Master Plan Update
City of Charlottesville Bicycle and Pedestrian Master Plan Update September 17, 2014 I. Welcome and meeting overview II. Project status update III. Network overview IV. Break-out groups Pedestrian Network
More informationCommitted to Service
Committed to Service Paul Woods, President Rebecca W. Arnold, Vice President Sara M. Baker, Commissioner Jim D. Hansen, Commissioner Kent Goldthorpe, Commissioner March 14, 2017 Planning and Programming
More informationDesigning Complete Streets: What you need to know
Designing Complete Streets: What you need to know Getting from this to this. Continuous sidewalk Buffer w/trees Bicycle lane Raised median Buildings close to the street Flexibility in design Design and
More informationSouthbend to Prima Vista. October 30, Floresta Corridor Master Plan
Application of a Complete Street initiative and how it might function operationally 8 8 Southbend to Prima Vista October 30, 2017 Presentation Agenda 2 Perspective and History Traffic projections, Levels
More informationCity of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County
City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County Public Involvement Meeting Thursday, April 28, 2016 6 to 8 P.M. Lapham Elementary School 1045 E. Dayton
More informationHenderson Ave. Complete Streets Project
Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to proceeding with preliminary engineering www.dallascompletestreets.wordpress.com MeetingAgenda
More informationAGENDA ITEM G-2 Public Works
AGENDA ITEM G-2 Public Works STAFF REPORT City Council Meeting Date: 12/6/2016 Staff Report Number: 16-214-CC Regular Business: Approve the Oak Grove University Crane Bike Improvement Concept Plan, authorize
More informationBETHEL ROAD AND SEDGWICK ROAD CORRIDOR STUDY
DRAFT PLAN City Council Meeting August 14, 2017 STUDY AREA Sedgwick Corridor State Route 160, principal arterial with Class 3 access management designation, commuter and freight route, connection to SR
More informationCommercial-Vista Corridor Plan Project Management Team. Judith Johnduff, AICP, Associate Transportation Planner Public Works Department
MEMO TO: Commercial-Vista Corridor Plan Project Management Team FROM: DATE: June 1, 2015 Judith Johnduff, AICP, Associate Transportation Planner Public Works Department SUBJECT: Public Events #2 - Summary
More informationProject Overview. Rolling Road Widening Fairfax County. Get Involved. Design Public Hearing. Contact Information
Get Involved VDOT representatives will review and evaluate information received as a result of this meeting. Please fill out the comment sheet provided in this brochure if you have any comments or questions.
More informationAccess Management in the Vicinity of Intersections
Access Management in the Vicinity of Intersections FHWA-SA-10-002 Technical Summary Photo: Ralph Bentley (used with permission) 0 Access Management is: The design, implementation and management of entry
More informationWELCOME. Traffic & Parking Commission Special Meeting May 30, Iteris, Inc. All rights reserved.
WELCOME Traffic & Parking Commission Special Meeting May 30, 2018 WORKSHOP #2 CONCEPTS FOR IMPROVEMENT MAY 30, 2018 Agenda 1. Welcome 10 min 2. Project Presentation 25 min 3. Roundtable Dialogue 50 min
More informationComplete Streets Policy DAVID CRONIN, P.E., CITY ENGINEER
Complete Streets Policy DAVID CRONIN, P.E., CITY ENGINEER Complete Streets City Commission adopted a Complete Streets policy in 2012 Complete Streets are road networks that are designed for all users:
More informationSTEERING COMMITTEE MEETING June 17, Streetscape Overview Burlington Comprehensive Master Plan
STEERING COMMITTEE MEETING June 17, 2015 Streetscape Overview Burlington Comprehensive Master Plan 1 Introduction Slide This slide show was presented to the Burlington Steering Committee on June 17, 2015
More informationOcean Park Boulevard Green Street Project Community Workshop
Ocean Park Boulevard Green Street Project Community Workshop 2.2.10 Project Objectives Community Priority: reclaim OPB for public open space. Build upon LUCE principles; neighborhood enhancement, connectivity,
More information2014/2015 BIKE ROUTE PLAN 83 AVENUE PROTECTED BIKE LANE
About the Project 2014/2015 BIKE ROUTE PLAN The City of Edmonton is planning a major bike route on the south side of Edmonton. This bike route is one part of a plan to provide citizens with transportation
More informationPublic Works Committee Meeting Richard E. Mastrangelo Council Chamber November 20, 2017
Public Works Committee Meeting Richard E. Mastrangelo Council Chamber November 20, 2017 Purpose of Meeting Why are we here? Project Recap/Updates Project Limits/Segments Road Diet Concept Lessons Learned
More informationProject Description Form 8AA
Project Description Form 8AA Basic Project Information Submitting Jurisdiction/Agency: Fairfax County Project Title: Route 1 Widening: Mount Vernon Memorial Highway to Napper Road Project Location: US
More informationAnn Arbor Downtown Street Plan
1 Ann Arbor Downtown Street Plan Public Workshop #1 We know that. 2 Public right-of-way (streets, sidewalks, and alleys) make up 30% of the total District area of downtown. Streets need to provide mobility
More informationRoad Diets FDOT Process
Florida Department of TRANSPORTATION Road Diets FDOT Process Humberto Castillero, PE, PTOE Roadway Design Office Purpose of Guide Develop a statewide lane elimination review process Balance state & local
More informationNJDOT Complete Streets Checklist
Background The New Jersey Department of Transportation s Complete Streets Policy promotes a comprehensive, integrated, connected multi-modal network by providing connections to bicycling and walking trip
More informationPublic Information Meeting #1. Pā ia Community Center 5:30 PM 8:00 PM
Public Information Meeting #1 Pā ia Community Center 5:30 PM 8:00 PM October 22, 2008 Overview of Tonight s Meeting Pā ia Mini Bypass Pā ia Relief Route Project Description and Study Area Context t Sensitive
More informationFinal Sidewalk Feasibility Study
Garfield Drive From Anastasia Drive to Elizabeth Place City of South Daytona July 23, 2009 Final Sidewalk Feasibility Study Prepared for: Prepared by: Final Sidewalk Feasibility Study Garfield Drive 2
More informationChapter 3: Multi-Modal Circulation and Streetscapes
CHAPTER 3: MULTI-MODAL CIRCULATION AND STREETSCAPES Chapter 3: Multi-Modal Circulation and Streetscapes Overview Streetscape improvements have already been completed for Depot Street between Main Avenue
More informationSchool Traffic Concerns?
Dealing with Texas-Sized Problems around Schools 2006 TexITE Summer Meeting June 25, 2006 Scott A. Cooner, P.E. Associate Research Engineer Texas Transportation Institute School Traffic Concerns? Parents
More informationMASTER BICYCLE AND PEDESTRIAN PLAN
VILLAGE OF NORTHBROOK MASTER BICYCLE AND PEDESTRIAN PLAN DRAFT PLAN OPEN HOUSE May 2, 2018 AGENDA 1. Community Engagement 2. Vision and Goals 3. General Structure of Plan 4. Recommendations Overview 5.
More informationProviding an Efficient and Multi-modal Transportation System
Providing an Efficient and Multi-modal Transportation System Welcome and Introductions The Plan Process Transportation Overview Workshop Discussions Report Out and Next Steps AGENDA Comprehensive Plan
More informationOn Road Bikeways Part 1: Bicycle Lane Design
On Road Bikeways Part 1: Bicycle Lane Design Presentation by: Nick Jackson Bill Schultheiss, P.E. September 04, 2012 FOLLOW THE CONVERSATION ON TWITTER Toole Design Group is live tweeting this webinar
More informationCity of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County
City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County Public Involvement Meeting Thursday, November 10, 2016 5:30 to 7 P.M. Festival Foods 810 E. Washington
More informationTRANSPORTATION COMMISSION Agenda Staff Report
TRANSPORTATION COMMISSION Agenda Staff Report Agenda Item No. 5.a DATE: JULY 31, 2014 TO: FROM: SUBJECT: TRANSPORTATION COMMISSION COMMUNITY DEVELOPMENT DEPARTMENT - PLANNING DRAFT OLYMPIC CORRIDOR PREFERRED
More informationKnox Street Complete Streets Project
Knox Street Complete Streets Project Meeting Purpose Get community feedback on two conceptual street design options Meeting Agenda Presentation (20 minutes) Project background and schedule Summary of preferences
More informationSection 7 Complete Green Street Guidelines DRAFT
Section 7 Complete Green Street Guidelines DRAFT 1 Section: 7.0 COMPLETE GREEN STREET GUIDELINES These guidelines serve as options to mitigate the environmental impact of a project as well as guide the
More informationALBERTA AVENUE WHAT WE HEARD REPORT BUILDING GREAT NEIGHBOURHOODS
ALBERTA AVENUE WHAT WE HEARD REPORT BUILDING GREAT NEIGHBOURHOODS FEBRUARY 2019 EXECUTIVE SUMMARY Starting in 2019, Alberta Avenue will see the replacement and enhancement of its aging collector and local
More informationReport. Typical Sections. City of Middleton, WI
Report Typical Sections City of Middleton, WI December 2006 Report for City of Middleton, Wisconsin Typical Sections repared by: Traffic Associates LLC and STRAND ASSOCIATES, INC. 910 West Wingra Drive
More informationBeach Cities Living Streets Design Manual and Aviation Boulevard Multimodal Corridor Plan
Beach Cities Living Streets Design Manual and Aviation Boulevard Multimodal Corridor Plan AGENDA 1 Introductions & Project Scope 2 Public Outreach Recap 3 Living Streets Design Manual 4 Aviation Boulevard
More informationAtwood Avenue Fair Oaks Avenue Cottage Grove Road
Atwood Avenue Fair Oaks Avenue Cottage Grove Road Agenda Purpose Review project scope & goals Present design alternatives Gather feedback Answer Questions Format Open House Presentation Q&A Open House
More informationSolana Beach Comprehensive Active Transportation Strategy (CATS)
Solana Beach Comprehensive Active Transportation Strategy (CATS) 3.0 Goals & Policies The Solana Beach CATS goals and objectives outlined below were largely drawn from the Solana Beach Circulation Element
More informationTRANSPORTATION NEEDS ASSESSMENT
TRANSPORTATION NEEDS ASSESSMENT A travel demand analysis was carried out to determine the operational issues and the potential benefit that adding traffic capacity would have on the road network. All the
More informationTypical Cross Section: DOWNTOWN (Observer Highway - 8th Street)
Typical Cross Section: DOWNTOWN (Observer Highway - 8th Street) DRAFT SEPTEMBER 23, 14 1 Washington Street Typical Block Downtown Typical Block: DOWNTOWN (Observer Highway - 8th Street) New crosswalks
More informationPublic Information Centre
WELCOME Public Information Centre Father Tobin Road Lougheed Middle School - Library Wednesday November 7, 2012 7:00 p.m.to 9:00 p.m. Please sign in Neighbourhood Traffic Calming Guide Background The City
More informationSaskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening
Saskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening We are here today to present the draft plan for the Saskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening project
More informationDerby Street. Project Updates. Salem, Massachusetts
Derby Street Project Updates Salem, Massachusetts September 13, 2017 Project Limits Derby Street Project Objectives 1. Improve complete streets elements on Derby Street 2. Improve sidewalks on finger streets
More informationMunicipal Class EA To Address Traffic Congestion On The Ontario Street Corridor (Grand Bend) Public Information Meeting June 4, 2018
Municipal Class EA To Address Traffic Congestion On The Ontario Street Corridor (Grand Bend) Public Information Meeting June 4, 2018 Background Agenda Traffic Study Update Class EA Alternatives Bridge
More informationPaoli Road Improvement Feasibility Study
Paoli Road Improvement Feasibility Study & Public Participation Project March 24, 2015 Prepared for: Tredyffrin Township Prepared by: McMahon Associates, Inc. with Town Planning Partnership, LLC Glackin
More informationDiamond Springs Parkway Project
Diamond Springs Parkway Project Public Information Meeting, Monday, March 18, 2013 330 Fair Lane, Building A, Placerville County Board of Supervisors Meeting Room, 6:30 8:00 p.m. PRESENTED BY: County of
More informationEl Camino Real Specific Plan. TAC/CAC Meeting #2 Aug 1, 2018
El Camino Real Specific Plan TAC/CAC Meeting #2 Aug 1, 2018 Land Use Alternatives Goals and Tradeoffs Parks & open space Housing Retail & services Civic spaces Parking Community gathering spaces 3 Alternatives
More informationLiving Streets Policy
Living Streets Policy Introduction Living streets balance the needs of motorists, bicyclists, pedestrians and transit riders in ways that promote safety and convenience, enhance community identity, create
More informationTOWN OF PORTLAND, CONNECTICUT COMPLETE STREETS POLICY
TOWN OF PORTLAND, CONNECTICUT COMPLETE STREETS POLICY I. VISION, GOALS & PRINCIPLES VISION To improve the streets of Portland making them safer and more accessible for all users including pedestrians,
More informationCaltrans Sloat Boulevard Pedestrian Safety Project Response to Community Questions, Comments & Concerns
Caltrans Sloat Boulevard Pedestrian Safety Project Response to Community Questions, Comments & Concerns Revised: May 10, 2016 The California Department of Transportation (Caltrans) is planning various
More informationMulti-Modal Traffic Analysis. Parisi and Associates
Mill Valley to Corte Madera Bicycle and Pedestrian Corridor Study Appendix D: Multi-Modal Traffic Analysis Prepared by Parisi and Associates August 2009 Appendix D - Multi-Modal Traffic Analysis Table
More information9/21/2016 VIA . RE: The Knot (DR16-270)
9/21/2016 VIA EMAIL Garrett Norman, Assistant Planner City of Sacramento Community Development Department 300 Richards Boulevard, 3 rd Floor Sacramento, CA 95811 RE: The Knot (DR16-270) Dear Mr. Norman:
More informationINDEX. Geometric Design Guide for Canadian Roads INDEX
Acceleration lane, see Lanes, Acceleration Access, 8.1 Access Management and Functional Classification 8.2 Access Management by Design Classification 8.3 Access Configuration 8.4 Building Set-Back Guidelines
More informationRE: Park Plaza Walgreens (P12-016)
12/5/2014 VIA EMAIL David Hung, Associate Planner City of Sacramento Community Development Department 300 Richards Blvd., 3rd Floor Sacramento, CA 95811 RE: Park Plaza Walgreens (P12-016) Dear Mr. Hung:
More information11/28/2016 VIA
11/28/2016 VIA EMAIL Ethan Meltzer, Assistant Planner City of Sacramento Community Development Department 300 Richards Blvd., 3 rd Floor Sacramento, Ca 95811 RE: Natomas Corporate Center Commercial Building
More informationcomplete streets design and construction standards public primer City of Edmonton
complete streets design and construction standards public primer City of Edmonton introduction Complete Streets are streets for everyone: people who walk, wheel, bike, take transit, or drive. They are
More informationComplete Streets Successes, Opportunities, and Challenges
Complete Streets Successes, Opportunities, and Challenges Juliet Walker, Transportation Planner, City of Portsmouth Rob Houseman, Director of Planning and Development, Town of Wolfeboro Chris Parker, Director
More information2014/2015 BIKE ROUTE PLAN 83 AVENUE PROTECTED BIKE LANE
About the Project The City of Edmonton is planning a major bike route on the southside of Edmonton. The Strathcona Bike Route will connect the communities of Strathcona, Garneau and the University area,
More informationCrosswalk Policy Revisions & Pedestrian & Bicycle Connection Plans. Presentation to Sanibel City Council July 16, 2013
Crosswalk Policy Revisions & Pedestrian & Bicycle Connection Plans Presentation to Sanibel City Council July 16, 2013 Outline Crosswalk Policy Revisions Minimum Standards Goals and Objectives Pedestrian
More informationCycle Track Design Best Practices Cycle Track Sections
Design Best Practices Sections It is along street segments where the separation and protection methods of cycle tracks offer more comfort than conventional bicycle lanes, and are more attractive to a wide
More informationChapter 6: Along the Street
Chapter 6: Along the Street This section describes the types of infrastructure that should be in place along school routes to make walking and bicycling to school safer. Sidewalks In communities with sidewalks,
More informationChapter 4: Funding and Implementation
Chapter 4: Funding and Implementation 83 84 Cost Estimating Cost estimating is an iterative process. When a project is in the conceptual stage, preliminary cost estimates are also provided conceptually,
More informationSan Jose Transportation Policy
San Jose Transportation Policy Protected Intersections in LOS Policies to Support Smart Growth Presented by: Manuel Pineda City of San Jose Department of Transportation Bay Area Map San Francisco Oakland
More informationFOCUS AREA 1 - Alberta Avenue Pocket Park 3 (121 Ave and 92 St)
FOCUS AREA 1 - Alberta Avenue Pocket Park 3 (121 Ave and 92 St) New benches Plant evergreen trees Widen existing sidewalk from 1.5m to 1.8m Marked crosswalk 1.8m wide sidewalk Add pedestrian oriented lights
More informationOff-road Trails. Guidance
Off-road Trails Off-road trails are shared use paths located on an independent alignment that provide two-way travel for people walking, bicycling, and other non-motorized users. Trails specifically along
More informationMEMORANDUM. Earl Haugen and UND Transportation and Traffic Coordination Committee
SRF No. 7766 MEMORANDUM TO: FROM: Earl Haugen and UND Transportation and Traffic Coordination Committee Rick Lane, P.E. DATE: November 26, 2013 SUBJECT: UNIVERSITY AVE REVIEW Our review of the University
More information