Conversion of One-Way Couplet Streets to Two-Way

Size: px
Start display at page:

Download "Conversion of One-Way Couplet Streets to Two-Way"

Transcription

1 Conversion of One-Way Couplet Streets to Two-Way May 5, 2016 Oklahoma Traffic Engineers Association 2016 Spring Meeting, Tulsa, OK Kevin St. Jacques, P.E., PTOE, PTP Freese and Nichols

2 Overview Initial Considerations Assess the Alternatives Implementation Strategies Case Studies 2

3 INITIAL CONSIDERATIONS Why Are One-Way Pairs Created? Streets grew, engineers provided solution Positive attributes of one-way couplets Distributes traffic off congested street Reduces crashes Allows for better signal progression Can reduce delay and emissions Expands traffic exposure for development Can allow room to retain/add parking on street Can allow room to retain/add pedestrian space along street 3

4 INITIAL CONSIDERATIONS Benefits of one way pairs No need for left turn bays = Room for Bulb-outs Logical terminus can signify change in uses 4

5 INITIAL CONSIDERATIONS Why Convert Back to Two-way Streets? 5 Negative attributes of One-way couplets vs. Two-way Can induce higher traffic speeds More complex traffic circulation Splits development energy, neighborhoods Potential economic enhancements End terminus configuration issues Development intensity/attraction imbalance on pair Traffic volumes or traffic patterns change Development patterns change

6 INITIAL CONSIDERATIONS Existing One-Way Character One direction traffic flow Parking both sides Short Ped Crossings

7 INITIAL CONSIDERATIONS Desired Two-Way Character Two directional flow Left turn bays Retain parking both sides Short Ped Crossings

8 INITIAL CONSIDERATIONS Initial Steps: 1. Review the Pros and Cons Internally History of installation (dates, supporters, funding, etc.) Benefits/challenges of current configuration Bike/ped, density, development vision, etc. Identification of city internal issues and concerns Maintenance, crime, crashes, etc. 8

9 INITIAL CONSIDERATIONS Initial Steps: 2. Review the Pros and Cons with Stakeholders Reminder of benefits of current configuration Identify known shortcomings of current configuration Vetting of stakeholder issues, concerns, desires, vision 9

10 INITIAL CONSIDERATIONS Initial Steps: 3. Formal Initiation of Corridor Study Define extent and context of study Stakeholder concurrence with study Formation of Project Steering Committee of staff and stakeholders 10

11 ASSESS THE ALTERNATIVES 1. Multimodal Performance Measures (manage expectations, data needs & analysis tools) Traffic Delay, Avg. Speed, Level of Service Net gain/loss in parking Traffic access and circulation complexity Intensity/safety of pedestrian crossings Streetscape (curb to ROW) space allocation Costs vs. Benefits Relative Weight of each measure Review Performance Measures with stakeholders 11

12 ASSESS THE ALTERNATIVES 2. Operational Data Collection Geometrics: ROW, curb lines, sidewalks, parking, etc. Traffic operations (daily counts, TMCs, speeds, trucks, etc.) Parking operations (occupancy, turnover, etc.) Pedestrian and bicycle observations Traffic control information Crashes and other incidents Other (rail crossings, special events, etc.) 12

13 ASSESS CASETHE ALTERNATIVES STUDY #2 13 Gray Street Main Street Gray Street Main Street Gray Street Main Street Operational Data Collection Geometrics: ROW, curb lines, sidewalks, parking, etc. Traffic operations (daily counts, TMCs, speeds, crashes, etc.) Other (traffic control, special events, etc.) University to Webster Santa Fe James Garner Jones Peters Crawford Porter Ent. Ext. Ent. Ext. Ent. Ext. Ent. Ext. Ent. Ext. Ent. Ext. Ent. Ext. North Side South Side North Side South Side University to Webster Webster to Webster to Santa Fe Santa Fe to Santa Fe to James Garner James Garner to James Garner to Jones Jones to Jones to Peters Peters to Peters to Crawford Crawford to Porter North Side South Side North Side South Side Crawford to University Webster Santa Fe James Garner Jones Peters Crawford Porter Northbound Southbound Northbound Southbound Table 1. Parking Maneuver Counts along Main and Gray Streets Table 2. Available On-Street Parking Spaces along Main and Gray Streets Table 3. Pedestrian Crossings PM Peak Hour

14 ASSESS CASETHE ALTERNATIVES STUDY #2 3. Land Use Data Collection Existing: successes and challenges Development locations Development performance indicators (revenue data, etc.) Planned and emerging development Latent and potential development 14

15 ASSESS THE ALTERNATIVES 4. Develop Alternative Concepts Geometric configuration options Enhanced one-way pair Various two-way street concepts Tradeoffs between lanes and parking Side Street circulation options Terminus treatments 15

16 ASSESS THE ALTERNATIVES Alternative Concepts Existing Two-Way (3) Two-Way (4) Two-Way (5) Modified One-Way 16

17 ASSESS THE ALTERNATIVES 5. Analyze the Alternatives Re-distribution of existing traffic, new traffic Initial screening of alternatives Comparative performance assessments Cost implications of top ranked alternatives Other implications (railroad, etc.) 17

18 ASSESS THE ALTERNATIVES REALLOCATE VOLUMES FOR TWO-WAY OPERATIONS Critical Peak Hour Traffic Volumes Terminus configurations effect Crossing street turn choices Key destination routes 18

19 IMPLEMENTATION STRATEGIES Consensus Building for Solutions Corridor visioning charrette with stakeholders Collaboration on performance measures and weights Screening of possible concepts Traffic reallocation exercises (modeled vs. calculated) Traffic flow simulation presentations Concept visualization 19

20 IMPLEMENTATION STRATEGIES Costs and Funding of Solution Quantify Monetary and Other Costs of Solution Identify Benefits of Solution (for funding justifications) Identify Potential Sources of Funds Public (City, other agencies) Private (Individual, Company, Association, Foundation, others) Concur on an Action Plan Champion(s) Partners and Responsibilities 20

21 Waco Downtown Couplets Assessment (7) CASE STUDY #1 Deciding Issues Volumes Geometrics Termini Connections Driveways Parking Context Circulation Full or Part Cost Impacts 21

22 CASE STUDY #1 Waco Downtown Couplets Assessment Convert 11 th /12 th to two-way streets 11 th St. 12 th St. 22 Deciding Issues Volumes Geometrics Termini Connections Driveways Parking Context Circulation Full or Part Cost Impacts

23 CASE STUDY #1 Waco Downtown Couplets Assessment Convert 11 th /12 th to two-way streets 23

24 CASE STUDY #1 Waco Downtown Couplets Assessment Convert 11 th /12 th to two-way streets 24

25 CASE STUDY #1 Waco Downtown Couplets Assessment Keep Bosque/Homan, 17 th /18th one-way Deciding Issues Volumes Geometrics Termini Connections Driveways Parking Context Circulation Full or Part Cost Impacts 25

26 CASE STUDY #1 Waco Downtown Couplets Assessment Convert 25 th /26 th to two-way streets Deciding Issues Volumes Geometrics Termini Connections Driveways Parking Context Circulation Full or Part Cost Impacts 26

27 CASE STUDY #1 Waco Downtown Couplets Assessment Convert 25 th /26 th to two-way streets 12

28 CASE STUDY #2 Downtown Norman Grey St Lower Intensity Congested Terminus Roundabout (Terminus) Main St (4 Lane) To I-35 Main St (5 Lane) Indirect Terminus Main St Higher Intensity

29 CASE STUDY #2 History of Main & Gray Streets Originally configured as two-way streets 1 lane each way plus angled parking Converted to one-way in 1974 Traffic Operations Program to Increase Capacity and Safety (TOPICS) University Blvd to Porter Ave the most accident prone segment in Norman. Head-in parking was identified as the major cause of the collisions Requests to convert back to 2-way began in 1990s Quick study concluded traffic would overwhelm Main Street Transportation Plan for 2035 showed changing traffic patterns Main & Gray Streets could be reduced by one travel lane thru Downtown 29

30 CASE STUDY #2 Alternative Concepts Geometric configuration options Tradeoffs between lanes and parking Terminus treatments Preferred Existing Two-Way (3) Two-Way (3) Two-Way (4) Two-Way (5) Evaluated 30

31 CASE STUDY #2 Traffic Distribution onto Two-way Network 31

32 CASE STUDY #2 32 Traffic Operations Analysis Existing 1-way with 2015 Traffic Existing 1-way with 1.2 Growth Factor Two-Way Scenario 1.2 Growth Factor Mitigation Scenario 1.2 Growth Factor Intersection Intersection Control Control Control Control Delay Delay LOS Delay LOS Delay LOS (Sec/veh) (Sec/veh) (Sec/veh) (Sec/veh) LOS Gray Street at Flood Avenue Gray 12.6 Street at B Flood Avenue 10.9 B 6.5 A 6.4 A Gray Street at Lahoma Avenue* Gray 4.6 Street at A Lahoma Avenue* 4.4 A 3.4 A 3.4 A Gray Street at University Boulevard Gray 10.5 Street at B University 10.2 Boulevard B 12.0 B 12.2 B Gray Street at Webster Avenue Gray 5.5 Street at A Webster Avenue 10.5 B 9.0 A 6.8 A Gray Street at Santa Fe Avenue Gray 4.2 Street at A Santa Fe Avenue 5.3 A 10.5 B 10.6 B Gray Street at James Garner Avenue* Gray 3.4 Street at A James Garner 20.8Avenue C 15.3 B 15.1 B Gray Street at Jones Avenue* Gray 0.0 Street at A Jones Avenue* 0.0 A 5.8 A 5.8 A Gray Street at Peters Avenue Gray 16.9 Street at B Peters Avenue 14.7 B 8.4 A 11.0 B Gray Street at Crawford Avenue* Gray 1.7 Street at A Crawford Avenue* 1.4 A 5.4 A 5.4 A Gray Street at Porter Avenue Gray 20.3 Street at C Porter Avenue 17.8 B 20.2 C 20.3 C Main Street at Flood Avenue Main 32.8 Street Cat Flood Avenue 37.3 D 24.7 C 24.9 C Main Street at Lahoma Avenue* Main 31.7 Street Dat Lahoma Avenue 63.8 F 4.1 A 4.0 A Main Street at Downtown Shopping Main Street at Downtown Shopping 13.9 B 3.7 A Center Center 3.3 A 3.4 A Main Street at University Boulevard Main 11.7 Street Bat University 15.8 Boulevard B 47.4 D 35.4 D Main Street at Webster Avenue Main 11.5 Street Bat Webster Avenue 23.2 C 59.6 E 50.8 D Main Street at Santa Fe Avenue Main 3.1 Street Aat Santa Fe Avenue 4.2 A 17.7 B 20.8 B Main Street at James Garner Avenue* Main 1.5 Street Aat James Garner 15.7Avenue C 34.9 C 35.9 D Main Street at Jones Avenue* Main 1.4 Street Aat Jones Avenue* 1.0 A 29.6 D 10.6 B Main Street at Peters Avenue Main 7.5 Street Aat Peters Avenue 8.8 A 21.3 C 18.3 B Main Street at Crawford Avenue Main 4.0 Street Aat Crawford Avenue 6.6 A 12.5 B 12.1 B Main Street at Porter Avenue Main 16.9 Street Bat Porter Avenue 17.3 B 37.2 D 37.7 D * Two-way stop controlled intersection. Delay based on HCM 2010 methodology Synchro Analysis Results for Existing One-Way And Two-way Configurations (PM Peak Hour)

33 CASE STUDY #2 Multimodal Pros and Cons of 1-1 TWLTL Factor Positive Attributes Negative Attributes Traffic Operations Creates a calmer traffic environment, better suited to Downtown destination. The new directional flow on both streets provides more direct access to destinations. Higher average delay, lower LOS, parking interrupts flow of the one through lane Train Crossings Pedestrian Crossings Queuing traffic still has two lanes in each direction spread across two streets, queues generally dissipate after one traffic signal cycle The bulb-outs are retained, keeping crossing distances minimal with good pedestrian visibility and accommodations Traffic queues are about 1.5 to 2 times as long as existing, back of queue extends to over 3 blocks on Main Street during PM peak Pedestrians must watch for added conflicts from left and right turning vehicles from added traffic direction Parking Retains angled parking on both sides, center turn lane allows use of angled parking from both directions by smaller vehicles (special ordinance) Added cost to re-orient parking stalls and modify bulb-outs, large vehicles would need to turn from through lane to enter opposite side parking Special Events Downtown functional as a destination with same amount of angled parking and new parking garage, traffic flow more logical for visitors High traffic generation events will not be as well accommodated for throughput. Development The two-way flow of traffic on both streets and the traffic calming allow for better visibility of businesses, less focus on passing through Downtown Current pass-thru traffic may divert to other routes, reducing exposure 33

34 CASE STUDY #2 Steps to Converting Main and Gray Streets from 1-way to 2-way 1. Oversized base on pedestals for future opposite flow signal pole 34 Oversized base on pedestals for future opposite flow Signal pole

35 CASE STUDY #2 Steps to Converting Main and Gray Streets from 1-way to 2-way 1. Convert one lane to opposite flow on lower volume street 35

36 CASE STUDY #2 Steps to Converting Main and Gray Streets from 1-way to 2-way 3. Convert one lane to Eastbound on Westbound Gray Street only A.Erect EB signal poles & test lights, install RR xing arms, bag new signs, then B. Stripe the lane line, connect signal heads, unbag signs, open EB 36

37 CASE STUDY #2 Steps to Converting Main and Gray Streets from 1-way to 2-way 4. Convert one lane to Westbound on Eastbound Main Street only A. Erect WB signal poles & test lights, install RR xing arms, bag new signs, then B. Re-stripe angled parking on north side of Main Street to reverse the angle, then C. Stripe the lane line, connect signal heads, unbag signs, open WB lane 37 14

38 CASE STUDY #2 Steps to Converting Main and Gray Streets from 1-way to 2-way 5. Convert center lane on Main and Gray Streets to TWLTL w/ LT bays A. Stripe the lane line, adjust signal indications as needed 38 14

39 CASE STUDY #2 Costs of Converting Main and Gray Streets from 1-way to 2-way Improvement Estimated Costs Traffic Signal Modifications (opposite flow signal at 7 intersections) $200,000 Traffic Signal Operation Modifications at Terminus Intersections $100,000 New traffic signals (4 $250K ea.) $1,000,000 Intersection modification for improved LOS for key cross streets $200,000 Pavement Markings and opposing direction signage $200,000 Railroad Crossing Improvements (opposite flow Signals and Gates) $300,000 Supplemental Safety Devices for Railroad Quiet Zone $1,000,000 Total Potential Cost $3.0 Million 39

40 Discussion Kevin St. Jacques, P.E., PTOE, PTP Freese and Nichols (OKC) (Dallas) 40

City of Moorhead Committee of the Whole Meeting

City of Moorhead Committee of the Whole Meeting City of Moorhead Committee of the Whole Meeting Corridor Study Limits Center Avenue (Red River to 8th Street) TH 10 (Red River to TH 336) TH 75 (20th Ave S to Main Avenue) 2 Study Need: Project Overview

More information

METHODOLOGY. Signalized Intersection Average Control Delay (sec/veh)

METHODOLOGY. Signalized Intersection Average Control Delay (sec/veh) Chapter 5 Traffic Analysis 5.1 SUMMARY US /West 6 th Street assumes a unique role in the Lawrence Douglas County transportation system. This principal arterial street currently conveys commuter traffic

More information

Figure 1: Vicinity Map of the Study Area

Figure 1: Vicinity Map of the Study Area ARIZONA TEXAS NEW MEXICO OKLAHOMA May 5, 2016 Mr. Anthony Beach, P.E. BSP Engineers 4800 Lakewood Drive, Suite 4 Waco, Texas 76710 Re: Intersection and Access Analysis along Business 190 in Copperas Cove

More information

Appendix B. Environmental Resource Technical Memorandum. Assessment on Travel Pattern and Access Impacts

Appendix B. Environmental Resource Technical Memorandum. Assessment on Travel Pattern and Access Impacts Appendix B Environmental Resource Technical Memorandum Assessment on Travel Pattern and Access Impacts TECHNICAL MEMORANDUM ENVIRONMENTAL RE-EVALUATION FOR UNION STATION TO OAK CLIFF DALLAS STREETCAR To:

More information

Traffic Circulation Study for Neighborhood Southwest of Mockingbird Lane and Airline Road, Highland Park, Texas

Traffic Circulation Study for Neighborhood Southwest of Mockingbird Lane and Airline Road, Highland Park, Texas ARIZONA TEXAS NEW MEXICO OKLAHOMA February 13, 2015 Mr. Meran Dadgostar P.E., R.S. Town of Highland Park 4700 Drexel Dr. Highland Park, Texas 75205 Re: Traffic Circulation Study for Neighborhood Southwest

More information

City of Wausau Wausau Center Urban Design and Transportation Master Plan. Design Workshop // October 18, 2018

City of Wausau Wausau Center Urban Design and Transportation Master Plan. Design Workshop // October 18, 2018 City of Wausau Wausau Center Urban Design and Transportation Master Plan Design Workshop // October 18, 2018 Design Workshops // October 15-18 Workshop Study Evaluate circulation and parking patterns around

More information

Balancing Operation & Safety for Motorized and Non-Motorized Traffic

Balancing Operation & Safety for Motorized and Non-Motorized Traffic Balancing Operation & Safety for Motorized and Non-Motorized Traffic Brian Willham, PE, PTOE Iowa Director - MOVITE June 30, 2014 Learning Objectives: When & Why should we measure the performance of complete

More information

133 rd Street and 132 nd /Hemlock Street 132 nd Street and Foster Street MINI ROUNDABOUTS. Overland Park, Kansas

133 rd Street and 132 nd /Hemlock Street 132 nd Street and Foster Street MINI ROUNDABOUTS. Overland Park, Kansas 133 rd Street and 132 nd /Hemlock Street 132 nd Street and Foster Street MINI ROUNDABOUTS Overland Park, Kansas September 1, 2017 TABLE OF CONTENTS 1. INTRODUCTION... 1 2. LITERATURE REVIEW... 1 3. CONCEPT

More information

WELCOME. Stakeholder Involvement Group Meeting #2 Round Lake Public Works October 24, 2018

WELCOME. Stakeholder Involvement Group Meeting #2 Round Lake Public Works October 24, 2018 WELCOME Stakeholder Involvement Group Meeting #2 Round Lake Public Works October 24, 2018 MEETING AGENDA 1. Welcome and Introductions 2. Study Progress Update 3. Problem Statement 4. Technical Analysis

More information

Shockoe Bottom Preliminary Traffic and Parking Analysis

Shockoe Bottom Preliminary Traffic and Parking Analysis Shockoe Bottom Preliminary Traffic and Parking Analysis Richmond, Virginia August 14, 2013 Prepared For City of Richmond Department of Public Works Prepared By 1001 Boulders Pkwy Suite 300, Richmond, VA

More information

Washington St. Corridor Study

Washington St. Corridor Study FIGURE 7.17 Bridge Alternatives - Cross Sections 86 Discarded Alternative: Short-Term Bridge Repair Short-term repairs and west bridge span replacement were considered during analysis. Short-term repairs

More information

Traffic Impact Study WestBranch Residential Development Davidson, NC March 2016

Traffic Impact Study WestBranch Residential Development Davidson, NC March 2016 Traffic Impact Study WestBranch Residential Development Davidson, NC March 216 TRAFFIC IMPACT STUDY FOR THE WestBranch Residential Development LOCATED IN DAVIDSON, NC Prepared For: Lennar Carolinas, LLC

More information

Bicycle Facilities Planning

Bicycle Facilities Planning Bicycle Facilities Planning Overview Types of Cyclists Purpose for Riding Types of Facilities Bike Lanes Bicycle Boulevards Cycle Tracks Intersections Signals Signing and Marking Discussion Types of Bicyclists

More information

Downtown Naples Mobility and Connectivity Study. Naples City Council Presentation January 2017

Downtown Naples Mobility and Connectivity Study. Naples City Council Presentation January 2017 Downtown Naples Mobility and Connectivity Study Naples City Council Presentation January 2017 Agenda 1. Introduction 2. Scope Review 3. Project Schedule 4. Existing Conditions 5. Public Charrette 6. Mobility

More information

TRAFFIC IMPACT STUDY And A TRAFFIC SIGNAL WARRANT ANALYSIS FOR A SENIOR LIVING AND APARTMENT DEVELOPMENT

TRAFFIC IMPACT STUDY And A TRAFFIC SIGNAL WARRANT ANALYSIS FOR A SENIOR LIVING AND APARTMENT DEVELOPMENT TRAFFIC IMPACT STUDY And A TRAFFIC SIGNAL WARRANT ANALYSIS FOR A SENIOR LIVING AND APARTMENT DEVELOPMENT DEERFIELD TOWNSHIP, WARREN COUNTY, OHIO Nantucket Circle and Montgomery Road () Prepared for: ODLE

More information

Reference number /VP. Lafayette Downtown Congestion Study - Additional Traffic Analysis

Reference number /VP. Lafayette Downtown Congestion Study - Additional Traffic Analysis To James Hinkamp and Tony Coe, City of Lafayette Date January 19, 2017 Copies Reference number 243381/VP From Michael Iswalt and Vanessa Peers File reference 4-05 Subject Lafayette Downtown Congestion

More information

Orange County Rail-Highway Grade Crossing Safety Enhancement Program. City of San Juan Capistrano April 17, 2012

Orange County Rail-Highway Grade Crossing Safety Enhancement Program. City of San Juan Capistrano April 17, 2012 Orange County Rail-Highway Grade Crossing Safety Enhancement Program City of San Juan Capistrano April 17, 2012 Orange County Rail-Highway Grade Crossing Safety Enhancement Program (OCX) 52 crossings 8

More information

Operational Comparison of Transit Signal Priority Strategies

Operational Comparison of Transit Signal Priority Strategies Operational Comparison of Transit Signal Priority Strategies Revision Submitted on: November, 0 Author: Adriana Rodriguez, E.I Assistant Engineer Parsons Brinckerhoff 0 South Orange Avenue, Suite 00 Orlando,

More information

Grant Avenue Streetscape

Grant Avenue Streetscape REPORT TYPE GOES HERE Grant Avenue Streetscape PREPARED FOR City of Manassas 9027 Center Street Manassas, VA 20110 PREPARED BY 8300 Boone Boulevard Suite 700 Vienna, Virginia 22182 571.389.8121 July 31,

More information

CITY OF OAKLAND. 27th Street Bikeway Feasibility and Design. Final Report (v3) March 23, Kimley-Horn and Associates, Inc.

CITY OF OAKLAND. 27th Street Bikeway Feasibility and Design. Final Report (v3) March 23, Kimley-Horn and Associates, Inc. CITY OF OAKLAND 27th Street Bikeway Feasibility and Design Final Report (v3) March 23, 2007 PREPARED BY: Kimley-Horn and Associates, Inc. Table of Contents 1. Introduction 3 2. 27 th Street/Bay Place Corridor

More information

WISCONSIN AVENUE EXTENSION SECOND PUBLIC INFORMATION MEETING. March 28, 2017

WISCONSIN AVENUE EXTENSION SECOND PUBLIC INFORMATION MEETING. March 28, 2017 WISCONSIN AVENUE EXTENSION SECOND PUBLIC INFORMATION MEETING March 28, 2017 STUDY AREA N MEETING AGENDA Introductions Study Background Alternatives Studied Recommended Alternative Discussion STUDY BACKGROUND

More information

THIS PAGE LEFT BLANK INTENTIONALLY

THIS PAGE LEFT BLANK INTENTIONALLY GA SR 25 Spur at Canal Road Transportation Impact Analysis PREPARED FOR GLYNN COUNTY, GEORGIA 1725 Reynolds Street, Suite 300 Brunswick, Georgia 31520 PREPARED BY 217 Arrowhead Boulevard Suite 26 Jonesboro,

More information

Summary: Mercer County Princeton Avenue & Spruce Street Study January 2009

Summary: Mercer County Princeton Avenue & Spruce Street Study January 2009 Summary: Several recent studies have assessed potential development and redevelopment opportunities in the Mercer Crossing area of Trenton, Ewing, and Lawrence. This Princeton Avenue and Spruce Street

More information

Joshua Saak, P.E., PTOE Traffic Design Engineer Ada County Highway District May 23, 2013

Joshua Saak, P.E., PTOE Traffic Design Engineer Ada County Highway District May 23, 2013 Joshua Saak, P.E., PTOE Traffic Design Engineer Ada County Highway District May 23, 2013 Creating Great Streets Through Road Diets and Conversions The Charlotte Experience Topics to Discuss Charlotte s

More information

Road Diets FDOT Process

Road Diets FDOT Process Florida Department of TRANSPORTATION Road Diets FDOT Process Humberto Castillero, PE, PTOE Roadway Design Office Purpose of Guide Develop a statewide lane elimination review process Balance state & local

More information

ALLEY 24 TRAFFIC STUDY

ALLEY 24 TRAFFIC STUDY ALLEY 24 TRAFFIC STUDY in City of Frostburg, Maryland January 2013 3566 Teays Valley Road Hurricane, WV Office: (304) 397-5508 www.denniscorporation.com Alley 24 Traffic Study January 2013 Frostburg, Maryland

More information

Albany Shaker Road Corridor Study Public Meeting # 2

Albany Shaker Road Corridor Study Public Meeting # 2 Albany Shaker Road Corridor Study Public Meeting # 2 Scope / Meeting Purpose This project is a CDTC Linkage Study. The Linkage Program is designed to implement the adopted planning and investment principles

More information

PRELIMINARY DRAFT WADDLE ROAD / I-99 INTERCHANGE PROJECT ALTERNATIVE ANALYSIS FINAL TRAFFIC SUMMARY REPORT

PRELIMINARY DRAFT WADDLE ROAD / I-99 INTERCHANGE PROJECT ALTERNATIVE ANALYSIS FINAL TRAFFIC SUMMARY REPORT PRELIMINARY DRAFT WADDLE ROAD / I-99 INTERCHANGE PROJECT ALTERNATIVE ANALYSIS FINAL TRAFFIC SUMMARY REPORT Prepared by: In Association with: November 2013 EXECUTIVE SUMMARY Patton Township, in partnership

More information

Blair/Williamson Intersection Expressed Needs

Blair/Williamson Intersection Expressed Needs Blair/Williamson Intersection Expressed Needs NORTH Blair Street is a barrier for pedestrians and bicycles Relocate Capitol City Trail crossing from Blair Street and John Nolen Drive intersection to Williamson

More information

Evaluation of M-99 (Broad Street) Road Diet and Intersection Operational Investigation

Evaluation of M-99 (Broad Street) Road Diet and Intersection Operational Investigation Evaluation of M-99 (Broad Street) Road Diet and Intersection Operational Investigation City of Hillsdale, Hillsdale County, Michigan June 16, 2016 Final Report Prepared for City of Hillsdale 97 North Broad

More information

Cycle Track Design Best Practices Cycle Track Sections

Cycle Track Design Best Practices Cycle Track Sections Design Best Practices Sections It is along street segments where the separation and protection methods of cycle tracks offer more comfort than conventional bicycle lanes, and are more attractive to a wide

More information

DUNBOW ROAD FUNCTIONAL PLANNING

DUNBOW ROAD FUNCTIONAL PLANNING DUNBOW ROAD FUNCTIONAL PLANNING Final Report August 3, 216 #31, 316 5th Avenue NE Calgary, AB T2A 6K4 Phone: 43.273.91 Fax: 43.273.344 wattconsultinggroup.com Dunbow Road Functional Planning Final Report

More information

Mark Malone, P.E. SD DOT

Mark Malone, P.E. SD DOT Mark Malone, P.E. SD DOT SD10 Grading & Surfacing From 8 th Ave W to 8 th Ave E 1 mile plus transition lengths Complete Urban Reconstruction Grading, C&G, Storm Sewer, Sidewalk, Concrete Surfacing Railroad

More information

GARLAND ROAD/GASTON AVENUE/ GRAND AVENUE INTERSECTION IMPROVEMENT STUDY

GARLAND ROAD/GASTON AVENUE/ GRAND AVENUE INTERSECTION IMPROVEMENT STUDY MEETING OF AFFECTED PROPERTY OWNERS AND STAKEHOLDERS GARLAND ROAD/GASTON AVENUE/ GRAND AVENUE INTERSECTION IMPROVEMENT STUDY CSJ 0009-02-067 Meeting Agenda 1 2 3 4 5 6 7 8 9 10 Opening Remarks State Representative

More information

Traffic Impact Analysis Chatham County Grocery Chatham County, NC

Traffic Impact Analysis Chatham County Grocery Chatham County, NC Chatham County Grocery Chatham County, NC TABLE OF CONTENTS 1. INTRODUCTION... 1 1.1. Location and Study Area... 1 1.2. Proposed Land Use and Access... 2 1.3. Adjacent Land Uses... 2 1.4. Existing ways...

More information

Complete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA

Complete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA Complete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA Aaron Elias, Bill Cisco Abstract As part of evaluating the feasibility of a road diet on Orange Grove Boulevard in Pasadena,

More information

Roundabout Feasibility Memorandum

Roundabout Feasibility Memorandum Roundabout Feasibility Memorandum To From Gwen Pipkin Bill Howell Date June 18, 2013 Subject Roundabout Feasibility Study SR 29 PD&E Study From Oil Well Road to SR 82 Collier County, FL FPID 417540-1-22-01

More information

David DiPierro, John Amberson. Steering Committee Meeting #4 Overview

David DiPierro, John Amberson. Steering Committee Meeting #4 Overview IBI GROUP 18401 Von Karman Avenue Suite 110 Irvine CA 92612 USA tel 949 833 5588 fax 949 833 5511 ibigroup.com Memorandum To/Attention Steering Committee Members Date February 17, 2016 From IBI Group Project

More information

Walmart (Store # ) 60 th Street North and Marion Road Sioux Falls, South Dakota

Walmart (Store # ) 60 th Street North and Marion Road Sioux Falls, South Dakota Walmart (Store #4865-00) 60 th Street North and Marion Road Sioux Falls, South Dakota Prepared for: Wal-Mart Stores, Inc. Bentonville, Arkansas Prepared by: Kimley-Horn and Associates, Inc. ã2013 Kimley-Horn

More information

BENNING ROAD & BRIDGES TRANSPORTATION IMPROVEMENTS CRASH DATA AND SAFETY ANALYSIS TECHNICAL MEMORANDUM DRAFT MAY 2016

BENNING ROAD & BRIDGES TRANSPORTATION IMPROVEMENTS CRASH DATA AND SAFETY ANALYSIS TECHNICAL MEMORANDUM DRAFT MAY 2016 BENNING ROAD & BRIDGES TRANSPORTATION IMPROVEMENTS CRASH DATA AND SAFETY ANALYSIS TECHNICAL MEMORANDUM DRAFT MAY 2016 This page left intentionally blank. Table of Contents 1.0 Introduction... 1 1.1 Crash

More information

CONTENTS EXECUTIVE SUMMARY 1

CONTENTS EXECUTIVE SUMMARY 1 CONTENTS CHAPTER PAGE EXECUTIVE SUMMARY 1 1 ISSUES AND PURPOSE OF THE ANALYSIS 2 1.1 Background 2 1.2 Analysis Area 2 1.3 Issues and Observations 3 1.4 Project and Public Meetings 3 2 LIST OF PREFERRED

More information

List of Attachments. Location Map... Site Plan... City of Lake Elsinore Circulation Element... City of Lake Elsinore Roadway Cross-Sections...

List of Attachments. Location Map... Site Plan... City of Lake Elsinore Circulation Element... City of Lake Elsinore Roadway Cross-Sections... List of Attachments Exhibits Location Map... Site Plan... City of Lake Elsinore Circulation Element... City of Lake Elsinore Roadway Cross-Sections... Existing Lane Geometry and Traffic Controls... Existing

More information

North Shore Transportation Improvement Strategy

North Shore Transportation Improvement Strategy North Shore Transportation Improvement Strategy Preliminary, Near-term Recommendation 2016 April Transportation Improvement Strategy (TIS) Comprehensive and Analytical A multi-modal transportation strategy

More information

VT15 / Allen Martin Drive Intersection Scoping Study

VT15 / Allen Martin Drive Intersection Scoping Study VT15 / Allen Martin Drive Intersection Scoping Study ALTERNATIVES PRESENTATION MEETING DECEMBER 19, 2016 Agenda Study Area Project Background Existing Conditions Identified Issues Proposed Alternatives

More information

Main-McVay Transit Study: Phase 2 Options Definition and High Level Constraints Evaluation

Main-McVay Transit Study: Phase 2 Options Definition and High Level Constraints Evaluation Main-McVay Transit Study: Phase 2 Options Definition and High Level Constraints Evaluation APRIL 2016 A collaborative study between: For Additional Information or to Comment If you would like additional

More information

TRAFFIC IMPACT ANALYSIS

TRAFFIC IMPACT ANALYSIS TRAFFIC IMPACT ANALYSIS FOR THE CHAMPAIGN UNIT#4 SCHOOL DISTRICT PROPOSED HIGH SCHOOL (SPALDING PARK SITE) IN THE CITY OF CHAMPAIGN Final Report Champaign Urbana Urbanized Area Transportation Study 6/24/2014

More information

Traffic Impact Analysis Walton Acres at Riverwood Athletic Club Clayton, NC

Traffic Impact Analysis Walton Acres at Riverwood Athletic Club Clayton, NC Traffic Impact Analysis Walton Acres at Riverwood Athletic Club Clayton, NC 1. TABLE OF CONTENTS INTRODUCTION...1 1.1. Site Location and Study Area...1 1.2. Proposed Land Use and Site Access...2 1.3.

More information

Traffic Impact Study for Rolling Ridge Redevelopment

Traffic Impact Study for Rolling Ridge Redevelopment Traffic Impact Study for Rolling Ridge Redevelopment Webster Groves, Missouri October 19, 2018 Prepared For: Gershman Commercial Real Estate 150 North Meramec Avenue Suite 500 St. Louis, Missouri 63105

More information

CITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM

CITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM CITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM Date: April 1, 219 To: Honorable City Council c/o City Clerk, Room 395, City Hall Attention: Honorable Mike Bonin, Chair, Transportation Committee From:

More information

Route 28 (South Orleans Road)/Route 39 (Harwich Road)/Quanset Road Intersection

Route 28 (South Orleans Road)/Route 39 (Harwich Road)/Quanset Road Intersection TRAFFIC FEASIBILITY STUDY Route 28 (South Orleans Road)/Route 39 (Harwich Road)/Quanset Road Intersection Orleans, Massachusetts Prepared for: Town of Orleans Prepared by: Fay, Spofford & Thorndike, LLC

More information

Roundabout Evaluations in Virginia: US 15/US 50 Gilberts Corner, VA SR 106/SR 634 Prince George County, VA

Roundabout Evaluations in Virginia: US 15/US 50 Gilberts Corner, VA SR 106/SR 634 Prince George County, VA Roundabout Evaluations in Virginia: US 15/US 50 Gilberts Corner, VA SR 106/SR 634 Prince George County, VA VDOT & FHWA Roundabout Workshop September 17, 2013 Chris Tiesler, PE Presentation Outline US 15/US

More information

Appendix C. NORTH METRO STATION AREA TRAFFIC IMPACT STATEMENT 88th Avenue Station

Appendix C. NORTH METRO STATION AREA TRAFFIC IMPACT STATEMENT 88th Avenue Station Appendix C NORTH METRO STATION AREA TRAFFIC IMPACT STATEMENT 88th Avenue Station Prepared for: Regional Transportation Department and URS Corporation as part of the North Metro EIS David Evans and Associates,

More information

Gateway Transportation Study

Gateway Transportation Study Gateway Transportation Study Amherst, Massachusetts SUBMITTED TO University of Massachusetts Amherst Town of Amherst SUBMITTED BY Vanasse Hangen Brustlin, Inc. Watertown, Massachusetts March 213 Back of

More information

to the Public Information Centre for the Downtown Traffic Study

to the Public Information Centre for the Downtown Traffic Study to the Public Information Centre for the Downtown Traffic Study City of Sault Ste. Marie July 25, 2018 Purpose of Study Determine if changes to one-way corridors can enhance downtown s character and spaces

More information

Traffic Improvements for the Transit Oriented Development District (TODD) Meriden Public Library March 11, 2014

Traffic Improvements for the Transit Oriented Development District (TODD) Meriden Public Library March 11, 2014 Traffic Improvements for the Transit Oriented Development District (TODD) Meriden Public Library March 11, 2014 Project Overview Coordinate roadway improvements with other major projects HUB Flood Control

More information

Draft North Industrial Area-Wide Traffic Plan

Draft North Industrial Area-Wide Traffic Plan Summary of North Industrial and Hudson Bay Industrial Recommended Improvements Table 1. Summary of s Item Location 1 2 3 4 5 6 7 8 9 10 11 12 Millar Ave north of 51st St Super 8 Motel back lane 400 Block

More information

Corridor Studies. LA 415 and LA 73

Corridor Studies. LA 415 and LA 73 Corridor Studies LA 415 and LA 73 Project Approach for Both Corridors 1. Data Collection 2. Data Summary 3. Traffic Analysis 4. Micro-Simulation modeling 5. Generation of alternatives 6. Modeling alternatives

More information

Table of Contents FIGURES TABLES APPENDICES. Traffic Impact Study Hudson Street Parking Garage MC Project No.: A Table of Contents

Table of Contents FIGURES TABLES APPENDICES. Traffic Impact Study Hudson Street Parking Garage MC Project No.: A Table of Contents Traffic Impact Study Hudson Street Parking Garage MC Project No.: 151714A Table of Contents Table of Contents I. INTRODUCTION... 2 II. EXISTING CONDITIONS... 5 III. 215 EXISTING TRAFFIC CONDITIONS... 6

More information

Display Boards Including Five Refined Design Concepts

Display Boards Including Five Refined Design Concepts APPENDIX D Workshop Session 3 Sign-in sheets Agenda Booklet Display Boards Including Five Refined Design Concepts PowerPoint Presentation Questions Recorded Discussion of Preference Exercise AGENDA

More information

4.0 TRANSPORTATION SYSTEMS

4.0 TRANSPORTATION SYSTEMS Transportation Systems 4.0 TRANSPORTATION SYSTEMS This chapter examines the impacts of the Central Corridor Extension on existing roadways and traffic operations and discusses the transit service, operations,

More information

County Board Workshop

County Board Workshop CH 21 Downtown Reconstruction Project County Board Workshop Tuesday, October 24, 2017 CH 21 Downtown Prior Lake Reconstruction Agenda 1) Review remaining Project Alternatives 2) Public Engagement Summary

More information

TRANSPORTATION NEEDS ASSESSMENT

TRANSPORTATION NEEDS ASSESSMENT TRANSPORTATION NEEDS ASSESSMENT A travel demand analysis was carried out to determine the operational issues and the potential benefit that adding traffic capacity would have on the road network. All the

More information

Average Delay/Vehicle (sec/veh) Signalized. Unsignalized Intersection

Average Delay/Vehicle (sec/veh) Signalized. Unsignalized Intersection Attachment: Traffic Analysis Results Traffic simulation modeling analysis was completed for Santa Cruz Ave from Alameda De Las Pulgas to Junipero Serra Blvd. Analysis was performed for existing conditions

More information

Boston Post Road Design Feasibility Study

Boston Post Road Design Feasibility Study Boston Post Road Design Feasibility Study Prepared for the City of Rye Final Report July 18, 2007 Prepared by: Buckhurst Fish & Jacquemart (BFJ) 115 Fifth Avenue New York, NY 10003 www.bfjplanning.com

More information

Toronto and East York Community Council. Director, Transportation Services, Toronto and East York District

Toronto and East York Community Council. Director, Transportation Services, Toronto and East York District No Turn on Red Regulations STAFF REPORT ACTION REQUIRED Date: June 1, 2010 To: From: Toronto and East York Community Council Director, Transportation Services, Toronto and East York District Wards: Trinity

More information

Town of Bethlehem. Planning Assessment. Bethlehem Town Board

Town of Bethlehem. Planning Assessment. Bethlehem Town Board Town of Bethlehem US 9W Corridor Transportation Planning Assessment Presented e to: Bethlehem Town Board June 2009 Overview Study Background Route 9W Corridor Conditions and Improvements Selkirk Bypass

More information

Brian McHugh, Buckhead Community Improvement District. SUBJECT: Wieuca Road at Phipps Boulevard Intersection Improvements Project

Brian McHugh, Buckhead Community Improvement District. SUBJECT: Wieuca Road at Phipps Boulevard Intersection Improvements Project MEMO TO: FROM: Brian McHugh, Buckhead Community Improvement District Jagan Kaja, AICP, WSP Parsons Brinckerhoff SUBJECT: Wieuca Road at Phipps Boulevard Intersection Improvements Project DATE: October

More information

Princeton Avenue and Spruce Street Transportation and Site Access Enhancements Project

Princeton Avenue and Spruce Street Transportation and Site Access Enhancements Project Princeton Avenue and Spruce Street Transportation and Site Access Enhancements Project Mercer County Planning Division AECOM Transportation (formerly DMJM Harris) January 29, 2009 Agenda Project Status

More information

Henderson Avenue Mixed-Use Development

Henderson Avenue Mixed-Use Development Zoning Case: Z145-3 Traffic Impact Analysis Henderson Avenue Mixed-Use Development Dallas, TX October 26 th, 216 Kimley-Horn and Associates, Inc. Dallas, Texas Project #644827 Registered Firm F-928 Traffic

More information

Caltrans Sloat Boulevard Pedestrian Safety Project Response to Community Questions, Comments & Concerns

Caltrans Sloat Boulevard Pedestrian Safety Project Response to Community Questions, Comments & Concerns Caltrans Sloat Boulevard Pedestrian Safety Project Response to Community Questions, Comments & Concerns Revised: May 10, 2016 The California Department of Transportation (Caltrans) is planning various

More information

Vision: Traditional hamlet with an attractive business/pedestrian friendly main street connected to adjacent walkable neighborhoods

Vision: Traditional hamlet with an attractive business/pedestrian friendly main street connected to adjacent walkable neighborhoods N D. Focus Area II Vision: Traditional hamlet with an attractive business/pedestrian friendly main street connected to adjacent walkable neighborhoods Transit Road Focus Area II is located in the Hamlet

More information

Broad Street Bicycle Boulevard City Council Study Session Summary

Broad Street Bicycle Boulevard City Council Study Session Summary Broad Street Bicycle Boulevard City Council Study Session Summary Overview: On August 15 th, 2017, a City Council Study Session was held to invite community input and request City Council guidance on a

More information

ADVANCED TRANSIT OPERATIONS AND MODELING

ADVANCED TRANSIT OPERATIONS AND MODELING SOUTHERN DISTRICT OF INSTITUTE OF TRANSPORTATION ENGINEERS (SDITE) 2017 ADVANCED TRANSIT OPERATIONS AND MODELING SURESH KARRE, PE, PTOE ROBERT DUBNICKA, PE, TE, PTOE AGENDA Background Transit operations

More information

Outreach Approach RENEW SF served as the primary liaison with the North Beach community; the Chinatown. Executive Summary

Outreach Approach RENEW SF served as the primary liaison with the North Beach community; the Chinatown. Executive Summary Executive Summary Executive Summary The Columbus Avenue Neighborhood Transportation Study s objective is to identify changes to transportation infrastructure and policies that could enhance the livability

More information

US 278 Corridor Concept Presentation. Avondale Estates Intersection Improvement/Roundabout and Road Diet Feasibility Study March 19, 2015

US 278 Corridor Concept Presentation. Avondale Estates Intersection Improvement/Roundabout and Road Diet Feasibility Study March 19, 2015 US 278 Corridor Concept Presentation Avondale Estates Intersection Improvement/Roundabout and Road Diet Feasibility Study March 19, 2015 Thanks to our Partners Atlanta Regional Commission Georgia Department

More information

Edgemont Village Traffic and Parking Technical Report January 2014

Edgemont Village Traffic and Parking Technical Report January 2014 Edgemont Village Traffic and Parking Technical Report January 2014 In the fall of 2013, the District of North Vancouver engaged consultants to assess existing intersection and parking conditions in Edgemont

More information

M-58 HIGHWAY ACCESS MANAGEMENT STUDY Mullen Road to Bel-Ray Boulevard. Prepared for CITY OF BELTON. May 2016

M-58 HIGHWAY ACCESS MANAGEMENT STUDY Mullen Road to Bel-Ray Boulevard. Prepared for CITY OF BELTON. May 2016 M-58 HIGHWAY ACCESS MANAGEMENT STUDY Prepared for CITY OF BELTON By May 2016 Introduction Missouri State Highway 58 (M-58 Highway) is a major commercial corridor in the City of Belton. As development has

More information

1 st and 2 nd Street Couplet FAQ s

1 st and 2 nd Street Couplet FAQ s 1 st and 2 nd Street Couplet FAQ s Q. Will the proposed roundabout at Flume/2nd/1 st Streets affect access to businesses nearby?... 2 Q. What if the project isn t received well by the community after construction?...

More information

El Camino Real Specific Plan. TAC/CAC Meeting #2 Aug 1, 2018

El Camino Real Specific Plan. TAC/CAC Meeting #2 Aug 1, 2018 El Camino Real Specific Plan TAC/CAC Meeting #2 Aug 1, 2018 Land Use Alternatives Goals and Tradeoffs Parks & open space Housing Retail & services Civic spaces Parking Community gathering spaces 3 Alternatives

More information

CAPE COD COMMISSION 3225 MAIN STREET P.O. BOX 226 BARNSTABLE, MA (508) Fax (508) Transportation Safety Report

CAPE COD COMMISSION 3225 MAIN STREET P.O. BOX 226 BARNSTABLE, MA (508) Fax (508) Transportation Safety Report CAPE COD COMMISSION 3225 MAIN STREET P.O. BOX 226 BARNSTABLE, MA 02630 (508) 362-3828 Fax (508) 362-3136 2006 Transportation Safety Report Bourne: Otis Rotary Harwich: Route 137/Route 39 Orleans: Route

More information

Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, AGENDA ITEM #2.B Presentation

Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, AGENDA ITEM #2.B Presentation Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, 2015 AGENDA ITEM #2.B Presentation Previous Presentations Los Altos Hills Town Council in May 2014 and February 2015 Palo Alto

More information

Optimizing The Operations of Closely Spaced Traffic Signals. Gordon E. Meth, P.E., PTOE ITE District 1 Annual Meeting May 21, 2004

Optimizing The Operations of Closely Spaced Traffic Signals. Gordon E. Meth, P.E., PTOE ITE District 1 Annual Meeting May 21, 2004 Optimizing The Operations of Closely Spaced Traffic Signals Gordon E. Meth, P.E., PTOE ITE District 1 Annual Meeting May 21, 2004 Closely Spaced Signals - The Challenges According to many sources, minimum

More information

2016 Church Street Access Study. 100 Clinton Square 126 North Salina Street, Suite 100 Syracuse, NY

2016 Church Street Access Study. 100 Clinton Square 126 North Salina Street, Suite 100 Syracuse, NY 2016 Church Street Access Study 100 Clinton Square 126 North Salina Street, Suite 100 Syracuse, NY 13202 www.smtcmpo.org Syracuse Metropolitan Transportation Council Final Report February 23, 2016 This

More information

4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC

4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC 4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC 4.9.1 INTRODUCTION The following section addresses the Proposed Project s impact on transportation and traffic based on the Traffic Study

More information

Sandwich Pedestrian/Bicycle Planning

Sandwich Pedestrian/Bicycle Planning Sandwich Pedestrian/Bicycle Planning Improved Pedestrian and Bicycle Connections with the Cape Cod Canal Multi-use Path February 2014 Table of Contents Introduction... 1 Background... 1 Study Goals...

More information

North Park Mid-City Bikeways Project: Traffic and Safety Impact Assessment

North Park Mid-City Bikeways Project: Traffic and Safety Impact Assessment FINAL REPORT North Park Mid-City Bikeways Project: University Bikeway Traffic and Safety Impact Assessment April 23, 2018 Lead Agency: San Diego Association of Governments (SANDAG) 401 B Street, Suite

More information

REGIONAL BICYCLE AND PEDESTRIAN DESIGN GUIDELINES

REGIONAL BICYCLE AND PEDESTRIAN DESIGN GUIDELINES REGIONAL BICYCLE AND PEDESTRIAN DESIGN GUIDELINES November 16, 2011 Deb Humphreys North Central Texas Council of Governments Bicycle and Pedestrian Advisory Committee Snapshot of the Guide 1. Introduction

More information

Environmental Assessment Findings & Recommendations. Public Hearing November 13, 2014

Environmental Assessment Findings & Recommendations. Public Hearing November 13, 2014 Environmental Assessment Findings & Recommendations Public Hearing November 13, 2014 Welcome! Welcome and Introductions Project and Environmental Assessment Overview Public Comments Adjourn Purpose of

More information

CITY OF BLOOMINGTON COMPLETE STREETS POLICY

CITY OF BLOOMINGTON COMPLETE STREETS POLICY CITY OF BLOOMINGTON COMPLETE STREETS POLICY POLICY OBJECTIVE: The City of Bloomington will enhance safety, mobility, accessibility and convenience for transportation network users of all ages and abilities,

More information

Solana Beach Comprehensive Active Transportation Strategy (CATS)

Solana Beach Comprehensive Active Transportation Strategy (CATS) Solana Beach Comprehensive Active Transportation Strategy (CATS) 3.0 Goals & Policies The Solana Beach CATS goals and objectives outlined below were largely drawn from the Solana Beach Circulation Element

More information

1 ALEXANDER STREET BIKEWAY

1 ALEXANDER STREET BIKEWAY ALEXADER STREET BIKEWAY Project Overview The City of Vancouver wants to address a major gap in the bike network by making Alexander Street safer and more comfortable for people of all ages and abilities

More information

East 12 th Street Bikeway Feasibility Study

East 12 th Street Bikeway Feasibility Study Final Report East 12 th Street Bikeway Feasibility Study Prepared for: City of Oakland Public Works Agency Submitted by: 180 Grand Avenue, Suite 250 Oakland, CA 94612 Phone: (510) 839-1742; Fax: (510)

More information

Low Level Road Improvements Traffic Analysis. Report

Low Level Road Improvements Traffic Analysis. Report Low Level Road Improvements Traffic Analysis Report June, 22 Table of Contents. INTRODUCTION.... LOW LEVEL ROAD PROJECT....2 STUDY AREA....2. West-End Corridor Improvements... 2.2.2 East-End Corridor Improvements...

More information

Roadways. Roadways III.

Roadways. Roadways III. Introduction 97 Roadway Design Principles 98 Safe Speeds 99 Optimizing of Street Space 00 Minimum Lane Widths in the City of Boston 02 Design Features that Reduce Operating Speeds 05 Travel Lanes Transit

More information

Multimodal Analysis in the 2010 Highway Capacity Manual

Multimodal Analysis in the 2010 Highway Capacity Manual Multimodal Analysis in the 2010 Highway Capacity Manual It s not just cars anymore! Jamie Parks, AICP HCAT Conference May 9-10, 2011 Multimodal LOS in the 2010 HCM History and background Overview of methods

More information

Glenn Avenue Corridor Traffic Operational Evaluation

Glenn Avenue Corridor Traffic Operational Evaluation Glenn Avenue Corridor Traffic Operational Evaluation PREPARED FOR: THE CITY OF AUBURN PREPARED BY: DECEMBER 2007 Glenn Avenue Corridor Study--Auburn, Alabama TABLE OF CONTENTS Introduction... 1 Background

More information

REPORT CONCURRENCE. City Manager. The General Manager concurs with the recommendation of this report.

REPORT CONCURRENCE. City Manager. The General Manager concurs with the recommendation of this report. COUNCIL REPORT Report No. ENG 08-018 Executive Committee Date: May 0, 018 File No: 5400-1 To: From: Subject: Mayor and Council Purvez Irani, Senior Transportation Engineer Bluejay Street Road Improvements

More information

PROJECT OBJECTIVES. Improve vehicle capacity for the intersection. Improve pedestrian and bicycle access

PROJECT OBJECTIVES. Improve vehicle capacity for the intersection. Improve pedestrian and bicycle access COMMUNITY MEETING Project Update March 15, 2010 Purcellville, Virginia OVERVIEW Project need / objectives Project recap Design elements Proposed improvements Summary of project benefits / next steps PROJECT

More information

CHAPTER 7.0 IMPLEMENTATION

CHAPTER 7.0 IMPLEMENTATION CHAPTER 7.0 IMPLEMENTATION Achieving the vision of the Better Streets Plan will rely on the ability to effectively fund, build and maintain improvements, and to sustain improvements over time. CHAPTER

More information

Polk Streetscape Project

Polk Streetscape Project What is this project? The Polk Streetscape Project is an effort to improve safety for everyone traveling on Polk Street between Union and McAllister streets. Also included in this project are paving, sewer

More information