ODOT AND LOCAL NORTHWEST OHIO MAJOR PROJECTS 2018 AND BEYOND

Size: px
Start display at page:

Download "ODOT AND LOCAL NORTHWEST OHIO MAJOR PROJECTS 2018 AND BEYOND"

Transcription

1 ODOT AND LOCAL NORTHWEST OHIO MAJOR PROJECTS 2018 AND BEYOND TMACOG TRANSPORTATION SUMMIT MARCH 16, 2018 Mike Gramza, District Two, Capital Programs Administrator John R. Kasich, Governor Jerry Wray, ODOT Director Patrick McColley, ODOT Deputy Director

2 I-75 RECONSTRUCTION NORTHWEST OHIO Proj. Sale Date Compl. Date Cost A Dec 2014 Oct 2017 $70,000,000 B Nov 2014 Oct 2018 $134,210,000 C May 2014 Oct 2016 $33,500,000 D May 2018 Spring 2022 $150,000,000 E Feb 2019 Fall 2022 $185,000,000 F May 2014 Aug 2017 $71,500,000 G April 2014 Nov 2016 $74,200,000 H April 2014 Aug 2016 $57,200,000 I Feb 2014 June 2017 $72,800,000 J Feb 2017 Aug 2020 $114,117,000 Total $962,527,000 2

3 RECAP 2017 MAJOR CONSTRUCTION PROJECTS 3

4 I-75 WIDENING: SR582 TO I-475 Cost: $71.5M Completion: spring 2018 Contractor: ES Wagner Designer: ODOT, TetraTech, DGL, Baker 4

5 I-75 WIDENING: SR582 TO I-475 5

6 I-75 WIDENING: SR582 TO I-475 6

7 SR 25 OVER I-475 PERRYSBURG Cost: $8.8M Completion: spring 2018 Contractor: ES Wagner Designer: DGL 7

8 SR 25 OVER I-475 PERRYSBURG 8

9 ANTHONY WAYNE BRIDGE PAINTING Cost: $12.6M Completion: spring 2018 Contractor: UCL Inc. Designer: Arcadis 9

10 PHASE 2: BRIDGE PAINTING 10

11 PHASE 2: BRIDGE PAINTING 11

12 HEN-109 MAUMEE RIVER BRIDGE Cost: $12M Bridge Opened: June 9, 2017 Contractor: Miller Bros. Designer: EL Robinson 12

13 HEN-109 MAUMEE RIVER BRIDGE 13

14 HEN-109 MAUMEE RIVER BRIDGE 14

15 I-75 LAGRANGE TO I-280 Cost: $70M Completion: fall 2017 Contractor: Kokosing Designer: HDR 15

16 I-75 LAGRANGE TO I

17 I-75 LAGRANGE TO I

18 CURRENT MAJOR CONSTRUCTION PROJECTS 18

19 HAN-75 FINDLAY WIDENING Cost: $113M Completion: fall 2020 Contractor: Beaver Designer: WSP 19

20 HAN-75 FINDLAY WIDENING 20

21 HAN-75 FINDLAY WIDENING New fly over ramp (SB I-75 to US68) opens mid summer US68 to SB I-75 closes mid summer NB US224 Ramps will close late spring/early summer for reconstruction NB SR12 ramps will close this summer for reconstruction 21

22 LUC-75/475 Cost: $134M Completion: October 31, 2018 Contractor: Kokosing Designer: B&N, Mannik, TetraTech 22

23 LUC-75/475 23

24 LUC-75/475 24

25 LUC-75/475 Status of major work items 3 spans of Berdan SB deck to be poured-estimated to open to traffic by July 2018 New SB I-75 to WB I-475 ramp to be complete by Aug 2018 New EB I-475 to NB I-75 will be complete in Sept 2018 Berdan and Haverhill, Phillips and Manhattan, Willys parkway roundabouts to be completed yet 25

26 LUC-75/ MOT impacts Phillips to SB I-75 closed All Jeep Parkway ramps except the NB I-75 exit are closed Berdan & Haverhill closed 60 days (May-July) Haverhill closed 60 days (July-Sept) Manhattan & Phillips closed 60 days (June-Aug) Traffic shifts to move into final configuration 26

27 WATERVILLE BRIDGE Cost: $13.4M Completion: September 30, 2020 Contractor: Miller Bros Const. Designer: Mannik & Smith 27

28 WATERVILLE BRIDGE 28

29 WATERVILLE BRIDGE 29

30 WATERVILLE BRIDGE 2018 MOT impacts 45 day closure of SR64 and SR65 to construct the roundabout Scheduled for summer 2018 when school is out between June 1 and Aug. 15 (dates TBD) 30

31 WATERVILLE BRIDGE 31

32 WATERVILLE BRIDGE 32

33 PORT CLINTON LIFT BRIDGE Cost: $13M Completion: May 24, 2018 Contractor: Ruhlin/Perram Designer: Hardesty and Hanover End River closure: April 1, 2018 End Road closure: May 24,

34 PORT CLINTON LIFT BRIDGE 34

35 PORT CLINTON LIFT BRIDGE 35

36 LUC-75 INDIANA AVE Cost: $5M Completion: May 31, 2019 Contractor: Kokosing Designer: WSP 36

37 LUC-75 INDIANA AVE 2018 MOT impacts Washington St. ramp from SB I-75 is reduced to one lane Indiana Ave. will close around Aug 1,

38 TRANSPORTATION SUMMIT 2018 Chris Matta Deputy Chief Engineer Ohio Turnpike and Infrastructure Commission Friday, March 16, 2018

39 3 rd Lane Construction Service Plaza Reconstruction , 03, 10, 11 E ZPass 2009 Pavement Replacement

40 $250,000,000 $225,000,000 $200,000,000 $175,000,000 $150,000,000 $125,000,000 $100,000,000 $75,000,000 $50,000,000 $25,000,000 $0

41

42 Bridge Painting Program Project No MP 21.4 Williams County MP 24.7, 36.3, 37.1, 38.3, 39.3 Fulton County OZEU Paint System Bridge Painting Program Project No MP 94.7, 97.6, 98.1, 100.2, Sandusky County MP 106.1, Erie County OZEU Paint System Bridge Rehabilitation Program Project No MP 59.0 Lucas County MP 84.4 Sandusky County Bridge Replacement / Deck Replacement

43 Mainline Pavement Reconstruction Project No Milepost Lorain & Cuyahoga Counties Full Depth Excavation & Replacement of Pavement Right 2 Lanes & Right Shoulder Bridge Repairs (4 Structures) Construction: April 2018 November 2020 Mainline Pavement Resurfacing Project No Milepost Erie & Lorain Counties Resurfacing of all 3 East & Westbound lanes Construction: April 2018 October 2018 Mainline Pavement Reconstruction Project No Milepost Summit & Cuyahoga Counties Full Depth Excavation & Replacement of Pavement Right 2 Lanes & Right Shoulder Bridge Repairs (4 Structures) Interchange 173 Repairs and Reconstruction Construction: April 2018 November 2020 *All 2018 Mainline Pavement Reconstruction will take place in the Eastbound direction.

44 2019 & Beyond Toll Collection System Modifications

45

46 Legal & Policy 241 Miles 160 Miles of 3 Lanes 8 Long Combination Vehicle Lots (28.4 Total Acres) 7 Sets of Service Plazas (1,412 Commercial Parking Spaces) 241 Miles of Fiber 6 Pavement Markings 55 Emergency Pull Off Areas

47 15 Roadside Units

48

49

50

51 This Tech will Immediately Improve Our Efficiency Provide a Significant Opportunity for Savings of Labor and Materials

52 Thank You Follow us TRANSPORTATION SUMMIT 2018

53 2018 MAJOR CONSTRUCTION PROJECTS 53

54 LUC-25 AWT OVER NORFOLK SOUTHERN RAILROAD Cost: $9.5M Bid Opening: March 2018 Completion: Fall 2019 Designer: Mannik & Smith 54

55 LUC-25 AWT OVER NORFOLK SOUTHERN RAILROAD 55

56 LUC-25 AWT OVER NORFOLK SOUTHERN RAILROAD 56

57 LUC-25 AWT OVER NORFOLK SOUTHERN RAILROAD 2018 MOT impacts AWT will be down to 1 lane inbound and 2 lanes outbound for entire 2018 season (starting about May 1) 57

58 LUC-75 SOUTH AVE. TO DORR ST. Cost: $150M Bid Opening: May 2018 Completion: summer 2022 Designer: WSP 58

59 LUC-75 SOUTH AVE. TO DORR ST MOT impacts Dorr St. Bridge closes for 300 days (late summer/early fall) Weiler Ave closes for storm sewer Installation for approx. 2 weeks (late summer) SR-25 Ramp C (SB I-75 to Outbound AW Trail) closes for 2 Weeks for Storm Sewer installation (summer) 59

60 PHASE 3: LIGHTING AND DEHUMIDIFICATION Cost: $13M Bid Opening: June 2018 Completion: summer 2020 Designer: Arcadis 60

61 DEHUMIDIFICATION 61

62 PHASE 3: LIGHTING AND DEHUMIDIFICATION 62

63 DEHUMIDIFICATION EXTERIOR WRAP 63

64 DEHUMIDIFICATION BUILDING RENDERING 64

65 DECORATIVE LIGHTING Tower Cable Deck Edge 65

66 TOP OF TOWER Historic housing to remain Replace internal HPS lamps with custom LED light source 66

67 EXISTING LIGHTING SYSTEM 67

68 LED LIGHTING 68

69 WOOSTER STREET INTERCHANGE AT I-75 69

70 WOOSTER STREET INTERCHANGE AT I-75 70

71 2018 ODOT AWARDED PROJECTS 2018 ( to ODOT Awarded Projects) 50 ODOT LET Projects for a total of $251M 71

72 Anthony Wayne Trail Gateway Erie Street to I 75 Cost: $4.5 m Roadway Construction completed 2017

73 Anthony Wayne Trail Gateway Erie Street to I 75

74 Anthony Wayne Trail Gateway Erie Street to I 75 Streetscape/Landscape elements complete Fall 2018

75 Bancroft Street Westwood to Parkside east end road diet 3 lanes & bike lanes completed 2017 Westwood to Perth Perth to Parkside

76 Bancroft Street Secor to Westwood west end 5 lanes, median islands at UT & bike lanes construction 2018 Secor to Campus UT Area University HIlls- to Westood

77 Overland Industrial Park Connector Phillips to Willys Parkway Redevelop connecting corridor reconstruct Berdan & Jeep Parkway 5 roundabouts, bike path complete Fall 2018 A NEW CORRIDOR TO SUPPORT REDEVELOPMENT

78 North and South Expressway Drives Lagrange to Stickney Finish Polish Village interchange roads & bike path $3.2 m. Fall 2018

79 AWT Reconstruction Plan Downtown to Maumee Phase 1 South to CBD, reconstruct with committed projects by 2022 Phase 2 Glendale to South, resurface 2018 Phase 3 Detroit to Glendale, reconstruct/narrow, partially programmed

80 Front/Millard from I 280 to Tiffin Avenue (related to new Cliffs Furnace) $5.7 m. Toledo Port Partnership Begin Fall 2018 complete 2019

81 Downtown Toledo Resurfacing/Utility Improvements Toledo Waterways Initiative CSO elimination and Monroe/Summit/Erie/Michigan Resurface

82 Overland Trail (OV) and Chessie Circle (CC) UT to Bowman Park and Stickney (Bike) 2018 OV Project 1 S. Cove to Jeep Parkway OV Project 2 Bancroft to Monroe cc Project 3 Connector Bancroft to Chessie Corridor 2021 CC North Paved Path Bowman Park to Bancroft (UT)

83 Major 2019 Committed Projects Detroit Avenue Byrne to Copland, full reconstruct, roundabout at Byrne, bike lanes $3.5 m. Complete Fall 2019 South Avenue Reynolds to Byrne, full reconstruct, roundabout at Wenz, bike lanes $5.3 m. Complete Fall 2019 Monroe Street Talmadge to Secor, reconstruct/realign mall entrances/resurface $3.2 m. Complete Fall 2019 Heatherdowns/Perrysburg Holland/Garden Road intersection, reconstruct $3.6 m. Complete Fall 2019

84 Cherry St Transit Hub Goodwill Building

85 Downtown Toledo Bike Share 18 Stations near hubs of activity within a 2 mile radius downtown 100 bikes / 150 rack-capacity Smart Bike Technology Launch as early as July 31, 2018

86 UPCOMING MAJOR CONSTRUCTION PROJECTS CONSTRUCTION FUNDING SECURED 86

87 WOO/LUC-75 GLENWOOD TO SOUTH Cost: $185M Bid Opening: Feb 2019 Completion: fall 2022 Designer: AECOM 87

88 LUC-475 WIDENING SR2 TO US20 88

89 TRAC 89

90 TRAC ADDITIONS TIER 1 90

91 I-475 DORR ST. INTERCHANGE Cost: $41M Bid Opening: spring 2020 Completion: summer 2021 Designer: TetraTech, Mannik,DGL 91

92 DORR ST AND MCCORD ROUNDABOUT 92

93 FUTURE MAJOR CONSTRUCTION PROJECTS CONSTRUCTION FUNDING NOT SECURED 93

94 LUC-20A INTERCHANGE & I-475 WIDENING Cost: $28M US 20A $64M I-475 Bid Opening: unknown Completion: Bid opening + 2 Designer: Arcadis 94

95 LUC-20A INTERCHANGE 95

96 WHERE IS ODOT HEADING IN THE FUTURE? 96

97 The Future of Smart Mobility will continuously Drive Ohio s preparation and leadership for the future of transportation technology Governor Kasich signs the Executive Order establishing DriveOhio as the statewide center for smart mobility Executive Director Jim Barna

98 WORKING GROUPS/FOCUS AREAS Data Analytics and Security Infrastructure Telecommunications/Right-of-Way Vehicle Deployment Budget/Partnerships Communications Policy/Regulatory Education & Workforce Development

99 SMART MOBILITY IN OHIO: HAPPENING NOW

100 INITIATIVES o US 33 Smart Mobility Corridor o Interstate 90 Lake Effect Corridor o Interstate 670 Smart lane o Interstate 80 - Ohio Turnpike o Connected Marysville o Smart Columbus

101 REAL-TIME TRAFFIC MANAGEMENT o Planning and Asset Management o Predictive Traffic Analytics o Hard Shoulder Running o Traffic Re-routing o Emergency Response o Wrong-way Warning/Avoidance o Adverse Weather/Road Conditions o Enhanced Traveler Information o Just-in-time Delivery/Commuter Commercial Truck Parking Availability o Work Zone Identification

102 2016 OHIO CRASHES 305,959 Crashes 9,207 Serious injuries 112,276 Injuries 1,133 Fatalities 102

103 FEEDBACK 103

104 FEEDBACK 104

105 QUESTIONS 105

District 2 Projects Scheduled for award during the period from 06/19/18 to 06/18/19 Sorted by PID

District 2 Projects Scheduled for award during the period from 06/19/18 to 06/18/19 Sorted by PID 77825 SA US 6/20 14.61/14.59 R Resurface US-6/US-20; perform necessary (Originally PID 76709); UPDATE (9/25/14) added culvert at SA-20-22.50 PID 95861. SSAUS00006**C 14.610 18.450 8,950,000.00 SA US 6/20

More information

ODOT DISTRICT CONSTRUCTION PROGRAM SERVING BUTLER, CLERMONT, CLINTON, GREENE, HAMILTON, PREBLE AND WARREN COUNTIES.

ODOT DISTRICT CONSTRUCTION PROGRAM SERVING BUTLER, CLERMONT, CLINTON, GREENE, HAMILTON, PREBLE AND WARREN COUNTIES. ODOT DISTRICT 8 2018 CONSTRUCTION PROGRAM Preble Greene SERVING BUTLER, CLERMONT, CLINTON, GREENE, HAMILTON, PREBLE AND WARREN COUNTIES. Butler Hamilton Warren Clinton Lebanon Clermont John R. Kasich,

More information

Highway Construction

Highway Construction Ohio Department of Transportation Traffic Advisory DISTRICT 1 KIRK SLUSHER, P.E., DISTRICT DEPUTY DIRECTOR 1885 North McCullough St. Lima, Ohio 45801 www.transportation.ohio.gov/dist1 www.facebook.com/odotdistrict1;

More information

COMMITTED TOTAL 9,518,714 5,167, ,800 15,185,405 BALANCE (2,486,243) 6,751, ,256 5,082,514

COMMITTED TOTAL 9,518,714 5,167, ,800 15,185,405 BALANCE (2,486,243) 6,751, ,256 5,082,514 TMACOG TIP PROGRAM FY2010 AND FY2011 PLUS PIPELINE PROJECTION FY2012 THROUGH 2017 revised 02/03/2010 FISCAL PROJECT R/W PS&E FEDERAL PROJECT CONSTRUCT CONSTRUCT YEAR PID SPONSOR PROJECT NAME PROJECT LIMITS

More information

DISTRICT CONSTRUCTION PROGRAM

DISTRICT CONSTRUCTION PROGRAM ODOT DISTRICT 3 2016 CONSTRUCTION PROGRAM photo by Tom Puskar SERVING ASHLAND, CRAWFORD, ERIE, HURON, LORAIN, MEDINA, RICHLAND AND WAYNE COUNTIES JOHN R. KASICH, OHIO GOVERNOR JERRY WRAY, ODOT DIRECTOR

More information

Ohio Department of Transportation STIP Project Listing (Appendix 6) as of 7/25/2018 Query: "Current STIP Detail 4"

Ohio Department of Transportation STIP Project Listing (Appendix 6) as of 7/25/2018 Query: Current STIP Detail 4 Ohio Department of Transportation - Listing (Appendix 6) as of 7/25/ Query: "Current Detail 4" Agency Dist PID MPO Cnty Name (ie CRS) Descript / Category / Termini Sponsoring Agency Air Quality Status

More information

VT15 / Allen Martin Drive Intersection Scoping Study

VT15 / Allen Martin Drive Intersection Scoping Study VT15 / Allen Martin Drive Intersection Scoping Study ALTERNATIVES PRESENTATION MEETING DECEMBER 19, 2016 Agenda Study Area Project Background Existing Conditions Identified Issues Proposed Alternatives

More information

CITY OF WOODINVILLE ONGOING CAPITAL IMPROVEMENT PROJECT UPDATES

CITY OF WOODINVILLE ONGOING CAPITAL IMPROVEMENT PROJECT UPDATES CITY OF WOODINVILLE ONGOING CAPITAL IMPROVEMENT PROJECT UPDATES PROJECT LOCATION MAP (1) DEYOUNG PARK IMPROVEMENTS Project Description - DeYoung Park Improvements include treehouse deck, play area, new

More information

I-70 NEW STANTON INTERCHANGE

I-70 NEW STANTON INTERCHANGE I-70 NEW STANTON INTERCHANGE Westmoreland County, PA Submitted by: PROJECT DESCRIPTION Situated adjacent to the PA Turnpike (I-76) and Interstate 70 in Westmoreland County, New Stanton bills itself as

More information

Welcome. Thank you for your interest in the Lewis & Clark Viaduct Concept Study

Welcome. Thank you for your interest in the Lewis & Clark Viaduct Concept Study Welcome Thank you for your interest in the Lewis & Clark Viaduct Concept Study Please use the arrows in the upper left hand corner to navigate through the presentation. Use the envelope icon to ask a question

More information

A: PLANNED P ROJECTS PROJECTS

A: PLANNED P ROJECTS PROJECTS Appendix A: PLANNED PROJECTS Programming Study Sound Barrier along south side of for approx. 2100 feet. Construction Complete $850,000 5 8613.00 Y Y Y Sound Barrier along south side of for 500' west of

More information

Interstate Route 77 / US Route 62 / State Route 687 (Fulton Road) Transportation Improvement Project. Prepared September 6, 2017

Interstate Route 77 / US Route 62 / State Route 687 (Fulton Road) Transportation Improvement Project. Prepared September 6, 2017 EODOT Project: ODOT Project: STA-IR 77-.50; PID 00290 Interstate Route 77 / US Route 62 / State Route 687 (Fulton Road) Transportation Improvement Project Summary of Public Comments Received and Responses

More information

FDOT Treasure Coast Traffic Report

FDOT Treasure Coast Traffic Report July 13, 2018 Barbara Kelleher, 954 777 4090 Barbara.Kelleher@dot.state.fl.us FDOT Treasure Coast Traffic Report July 13 through July 20, 2018 TREASURE COAST Construction and maintenance related lane closures

More information

INGHAM COUNTY ROAD DEPARTMENT AUSTIN E. CAVANAUGH ADMINISTRATION BUILDING 301 Bush Street, P.O. Box 38, Mason, MI

INGHAM COUNTY ROAD DEPARTMENT AUSTIN E. CAVANAUGH ADMINISTRATION BUILDING 301 Bush Street, P.O. Box 38, Mason, MI INGHAM COUNTY ROAD DEPARTMENT AUSTIN E. CAVANAUGH ADMINISTRATION BUILDING 301 Bush Street, P.O. Box 38, Mason, MI 48854-0038 March 27, 2018 William M. Conklin, P.E. Managing Director FOR IMMEDIATE RELEASE:

More information

Sarasota/Manatee MPO Project Priorities 2016 Adopted April 25, 2016

Sarasota/Manatee MPO Project Priorities 2016 Adopted April 25, 2016 All projects on the following priority lists should be implemented in the priority sequence listed, as consistent with the fiscal constraints identified in the MPO s adopted Long Range Transportation Plan

More information

FM #: ETDM #: 11241

FM #: ETDM #: 11241 SR 826/Palmetto Expressway PD&E Study From SR 93/I 75 to the Golden Glades Interchange FM #: 418423 1 22 01 ETDM #: 11241 Agency/ Kick Off Meeting October 27, 2011 2 Location Map From SR 93/I 75 to Golden

More information

APPENDIX D: SACRAMENTO URBAN AREA TRANSPORTATION PRIORITIES

APPENDIX D: SACRAMENTO URBAN AREA TRANSPORTATION PRIORITIES 1 County County County County 2 Yolo Arterial Roadway Collector Roadway Urban Residential Street Rural Residential Roadway I-80 / U.S. 50 Bus/Carpool Lanes in both directions Richards Blvd PM Yol 80 0.237

More information

Design Criteria. Design Criteria

Design Criteria. Design Criteria F Design Criteria Design Criteria Ministry of Transportation Ministère des Transports DESIGN CRITERIA Page: 1 of 13 WORK PROJECT NO. N/A GO Bloomington Station TYPE OF PROJECT LOCATION Bloomington Road

More information

Blair/Williamson Intersection Expressed Needs

Blair/Williamson Intersection Expressed Needs Blair/Williamson Intersection Expressed Needs NORTH Blair Street is a barrier for pedestrians and bicycles Relocate Capitol City Trail crossing from Blair Street and John Nolen Drive intersection to Williamson

More information

Ohio Department of Transportation STIP Project Listing as of 7/27/2017 Query: "Current STIP Detail 4"

Ohio Department of Transportation STIP Project Listing as of 7/27/2017 Query: Current STIP Detail 4 Ohio Department of Transportation - Listing as of 7/27/ Query: "Current Detail 4" Dist PID MPO Cnty Name (ie CRS) Descript / Category / Termini Sponsoring Air Quality Status Reference (New) FHWA 1 80441

More information

Description: Widen I-64 to 6 lanes from I-265 to the KY 53 interchange in Shelby County.

Description: Widen I-64 to 6 lanes from I-265 to the KY 53 interchange in Shelby County. I-64 KIPDA ID # 350 Project Type: ROADWAY CAPACITY Description: Widen I-64 to 6 lanes from I-265 to the KY 53 interchange in Shelby County. Purpose: Project will improve capacity and address safety concerns.

More information

FDOT Treasure Coast Traffic Report

FDOT Treasure Coast Traffic Report July 6, 2018 Barbara Kelleher, 954 777 4090 Barbara.Kelleher@dot.state.fl.us FDOT Treasure Coast Traffic Report July 6 through July 13, 2018 TREASURE COAST Construction and maintenance related lane closures

More information

FY 2006 TRANSPORTATION CAPITAL PROGRAM

FY 2006 TRANSPORTATION CAPITAL PROGRAM Eden Lane Bridge over Whippany River NS9908 The existing structure was built in 1972 as a temporary single-span structure. The bridge consists of simply supported steel acrow panel trusses and is supported

More information

May 10, 2013 Meredith Cruz, (561) Palm Beach County Traffic Report May 10 through May 17, 2013

May 10, 2013 Meredith Cruz, (561) Palm Beach County Traffic Report May 10 through May 17, 2013 May 10, 2013 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report May 10 through May 17, 2013 Palm Beach County Palm Beach County traffic will be affected this week by ongoing

More information

SR 53 Corridor Study. Final Report Presentation. Friday, October 3, :00 AM to noon

SR 53 Corridor Study. Final Report Presentation. Friday, October 3, :00 AM to noon SR 53 Corridor Study Final Report Presentation Friday, October 3, 2014 10:00 AM to noon SR 53 Corridor Study Final Report Presentation Study Purpose: Investigate safety improvements along the SR 53 corridor

More information

MIAMI & ERIE CANAL SHARED USE TRAIL

MIAMI & ERIE CANAL SHARED USE TRAIL New Bremen, Ohio Survey Transportation Engineering Grant Writing Project Cost Engineers Estimate: $509,358 Bid Amount $480,892 Size 1.12 miles $597,696 ODOT TEP $249,815 ODNR Completion Projected 11/15/14

More information

Deck Rehabilitation and Steel Repairs Maurice J. Tobin Memorial Bridge

Deck Rehabilitation and Steel Repairs Maurice J. Tobin Memorial Bridge Deck Rehabilitation and Steel Repairs Maurice J. Tobin Memorial Bridge US 1 NB & Ramps Chelsea September 11, 2017 Maurice J. Tobin Memorial Bridge Big Mystic Truss Current Project Little Mystic Truss Toll

More information

North Carolina Department of Transportation American Recovery and Reinvestment Act of 2009 Division One Highway Infrastructure Program Summary

North Carolina Department of Transportation American Recovery and Reinvestment Act of 2009 Division One Highway Infrastructure Program Summary Division One Highway Infrastructure Program Summary 1 Hyde NC 12 Northern Ferry Dock Ocracoke Village R-5149 Resurface and Widening to Accommodate Bicycling 13.3 $3,310,000 $0 $3,310,000 Jul-09 1 Dare

More information

Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, AGENDA ITEM #2.B Presentation

Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, AGENDA ITEM #2.B Presentation Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, 2015 AGENDA ITEM #2.B Presentation Previous Presentations Los Altos Hills Town Council in May 2014 and February 2015 Palo Alto

More information

Let s Make I-40 Better Action Team. Friday, March 29, 2019 Hosted by RTP Foundation

Let s Make I-40 Better Action Team. Friday, March 29, 2019 Hosted by RTP Foundation Let s Make I-40 Better Action Team Friday, March 29, 2019 Hosted by RTP Foundation RTA Welcome Geoff Lang, MetLife, RTA Chair Jim Beley, The Umstead Hotel & Spa, RTA regional travel experience chair NCDOT

More information

Route 245 over Broad Run. The recently replaced bridge links The Plains and other communities in northern Fauquier to Interstate 66.

Route 245 over Broad Run. The recently replaced bridge links The Plains and other communities in northern Fauquier to Interstate 66. 28 VIRGINIA DEPARTMENT OF TRANSPORTATION \\ CULPEPER DISTRICT Route 245 over Broad Run. The recently replaced bridge links The Plains and other communities in northern Fauquier to Interstate 66. PROJECT

More information

Harrah s Station Square Casino

Harrah s Station Square Casino Transportation Analysis Harrah s Station Square Casino Pittsburgh, Pennsylvania Submitted To: City of Pittsburgh and Pennsylvania Gaming Control Board Prepared By: DKS Associates GAI Consultants December

More information

Bluffdale/ UDOT South High-T Intersection Project Type Operations

Bluffdale/ UDOT South High-T Intersection Project Type Operations Bluffdale/ UDOT 14600 South High-T Intersection Project Type Operations 14600 South and Redwood Road $ 600,000 $ 550,000 This project is to install a new High-T intersection at Redwood Road and 14600 South

More information

I-95/Temple Avenue Improvements Project Colonial Heights, VA

I-95/Temple Avenue Improvements Project Colonial Heights, VA I-95/Temple Avenue Improvements Project Colonial Heights, VA Pardon Our Dust Informational Meeting February 3, 2016 Harold Dyson, P.E. Construction Manager, Richmond District Tom Heil, P.E. Allan Myers

More information

Terwillegar Drive Expressway Draft Concept Plan

Terwillegar Drive Expressway Draft Concept Plan Terwillegar Drive Expressway Draft Concept Plan Anthony Henday Drive to Whitemud Drive November 28 5:00-8:00 p.m. December 1 10:00 a.m. - 3:00 p.m. Let s Talk Today you can: Learn about the new direction

More information

PRESENTATION WILL BEGIN AT APPROXIMATELY 6:05 P.M. I-90 EXIT 406 INTERCHANGE MODIFICATION STUDY AND ENVIRONMENTAL ASSESSMENT MARKET

PRESENTATION WILL BEGIN AT APPROXIMATELY 6:05 P.M. I-90 EXIT 406 INTERCHANGE MODIFICATION STUDY AND ENVIRONMENTAL ASSESSMENT MARKET PRESENTATION WILL BEGIN AT APPROXIMATELY 6:05 P.M. MARKET I-90 EXIT 406 INTERCHANGE MODIFICATION STUDY AND ENVIRONMENTAL ASSESSMENT JANUARY 23, 2017 Public Meeting & Open House #2 TODAY S MEETING Purpose:

More information

FY 2018 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects

FY 2018 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects Camden County Bus Purchase Project ID Numbers: D0601 / 068082 In the DVRPC region, a combination of fixed route, subscription, and demand responsive transit services are provided in Camden County by Senior

More information

FI N A N C I A L RESOURCER S REVIEW AND UPDATE M I A M I-DADE LO N G R A N G E TRANSPORT T ATION PLAN UPDATE TO THE YE

FI N A N C I A L RESOURCER S REVIEW AND UPDATE M I A M I-DADE LO N G R A N G E TRANSPORT T ATION PLAN UPDATE TO THE YE Appendix B: Miami-Dade LRTP Cost Feasible Projects (Fully Funded and Partially Funded Projects) Fully Funded Projects Existing County roads O&M $317.9 $316.7 $811.5 Non Motorized set aside $27.9 $24.7

More information

Delaware Avenue Corridor Study

Delaware Avenue Corridor Study Delaware Avenue Corridor Study City of Marysville, Ohio February 19, 2009 ms consultants, inc. engineers, architects, planners 2221 Schrock Road Columbus, Ohio 43229-1547 ms ms consultants, inc. engineers

More information

ODOT construction cost is $51,000,000. State assumes and bears 100 percent of the cost of improvement.

ODOT construction cost is $51,000,000. State assumes and bears 100 percent of the cost of improvement. 1. I 271 WIDENING & RESURFACING - PID 89458 Project consists of major reconstruction, widening and bridge deck replacement. Project will accomplish widening from 4 to 6 lanes, including redecking and widening

More information

I 595 Express Corridor Improvements Project. February 2014 Update

I 595 Express Corridor Improvements Project. February 2014 Update I 595 Express Corridor Improvements Project February 2014 Update PROJECT COMPONENTS Reversible Express Lanes Direct Connect to Florida s Turnpike Open Road Tolling SR 84 Continuous Connection Florida s

More information

Freeway System Considerations

Freeway System Considerations Session 11 Jack Broz, PE, HR Green May 5-7, 2010 Freeway System Considerations Mainline Transit: Shoulder Operations, BRT, Stations HOV, HOT, UPA Interchanges Exit Ramps Entrance Ramps Bridges Local Crossings

More information

Congress Avenue. Palm Beach MPO Subcommittee Meetings December 2017

Congress Avenue. Palm Beach MPO Subcommittee Meetings December 2017 1 Congress Avenue Palm Beach MPO Subcommittee Meetings December 2017 2 Agenda Study Purpose Study Process Multimodal Alternatives Development Next Steps *ACTION ITEM: CONFIRM ALTERNATIVES TO MOVE INTO

More information

Operations -- Transit From: N/A To: N/A. Improvement Type: Regionally Significant: No

Operations -- Transit From: N/A To: N/A. Improvement Type: Regionally Significant: No Central Puget Sound Regional 2017-2020 Transportation Improvement Program Amendments and Corrections to be included in the 2017-20 STIP PSRC's Amendment 2017-08 County: King List of 17-08 Amendment Projects:

More information

Princeton Avenue and Spruce Street Transportation and Site Access Enhancements Project

Princeton Avenue and Spruce Street Transportation and Site Access Enhancements Project Princeton Avenue and Spruce Street Transportation and Site Access Enhancements Project Mercer County Planning Division AECOM Transportation (formerly DMJM Harris) January 29, 2009 Agenda Project Status

More information

Northwest Corridor Project Interchange Modification, Interchange Justification and System Analysis Report Reassessment (Phase I)

Northwest Corridor Project Interchange Modification, Interchange Justification and System Analysis Report Reassessment (Phase I) Northwest Corridor Project Interchange Modification, Interchange Justification and System Analysis Report Reassessment (Phase I) Introduction The Georgia Department of Transportation (GDOT) prepared a

More information

Iowa Highway 58 Corridor Improvement Study

Iowa Highway 58 Corridor Improvement Study 1 Iowa Highway 58 Corridor Improvement Study Public Informational Meeting May 6, 2014 2 Welcome and Introductions Randy Lorenzen, City of Cedar Falls Engineer 3 Outline of Presentation Review of Project

More information

RIVERSIDE COUNTY TRANSPORTATION COMMISSION - UPDATE

RIVERSIDE COUNTY TRANSPORTATION COMMISSION - UPDATE RIVERSIDE COUNTY TRANSPORTATION COMMISSION - UPDATE CMAA Southern California Chapter June 21, 2018 Marlin Feenstra, Director of Project Delivery ORG CHART (SIMPLE) Is it Marlin s Project? START Questions?

More information

ROUTE 81 CORRIDOR STUDY DESIGN CONCEPTS

ROUTE 81 CORRIDOR STUDY DESIGN CONCEPTS RT 81 Corridor Study CLINTON ROUTE 81 CORRIDOR STUDY DESIGN CONCEPTS View north on High Street, with potential improvements to the streetscape Draft Recommendations November 8 th, 2018 TOWN OF CLINTON

More information

Capital Beltway HOT Lanes Project

Capital Beltway HOT Lanes Project New Travel Choices Ahead Some things can t wait for traffic Capital Beltway HOT Lanes Project Fairfax County TAC Update August 16, 2011 Major Milestones Reached Some things can t wait for traffic Project

More information

T W P L A I A A V O L H S Bike Network Plan Sylvania, Ohio. July 20, 2009

T W P L A I A A V O L H S Bike Network Plan Sylvania, Ohio. July 20, 2009 Y 2009 E T W O R K N P L A E N K I B N I A A V O L H S O I 2009 Bike Network Plan Sylvania, Ohio I-75 Lenawee County US 23 Monroe County I-75 Michigan Ohio SYLVANIA Alexis Rd I-475 Monroe 24 I-75 20/120

More information

Chapter 7 ACCESS MANAGEMENT RELATED ACCOMPLISHMENTS

Chapter 7 ACCESS MANAGEMENT RELATED ACCOMPLISHMENTS Chapter 7 ACCESS MANAGEMENT RELATED ACCOMPLISHMENTS Introduction The US-41/M-28 Access Management Plan was the first of its kind in the Upper Peninsula. Since 2004, when the Corridor Advisory Group first

More information

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects Barclay Street Viaduct NS9807 NS9807 This project will provide for the rehabilitation of the Barclay Street Viaduct, from Route 19 to Marshall Street, in order to increase the weight load of the structure.

More information

FDOT Treasure Coast Traffic Impact Report April 7 through April 14, 2017

FDOT Treasure Coast Traffic Impact Report April 7 through April 14, 2017 April 7, 2017 Chuck McGinness, 954 777 4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report April 7 through April 14, 2017 TREASURE COAST Construction and maintenance related

More information

AGENDA ACTION ITEMS INFORMATION ITEMS

AGENDA ACTION ITEMS INFORMATION ITEMS NOACA Bicycle and Pedestrian Advisory Council Meeting Friday, June 20 th, 2014 10:30 a.m. NOACA Office 1299 Superior Avenue Cleveland, Ohio 44114 Phone: (216) 241-2414; website: www.noaca.org AGENDA ACTION

More information

I-264 CORRIDOR EVALUATION STUDY. September 7, 2016 Eric Stringfield VDOT Planning Director Chris Lawrence AECOM Senior Transportation Engineer

I-264 CORRIDOR EVALUATION STUDY. September 7, 2016 Eric Stringfield VDOT Planning Director Chris Lawrence AECOM Senior Transportation Engineer I-264 CORRIDOR EVALUATION STUDY September 7, 2016 Eric Stringfield VDOT Planning Director Chris Lawrence AECOM Senior Transportation Engineer Study Overview Interchange Locations Study Context Follow-up

More information

Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I. OPEN HOUSE June 20, 2017

Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I. OPEN HOUSE June 20, 2017 Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I OPEN HOUSE June 20, 2017 Brooklyn Boulevard (County Road 152) Phase I Project Partners Project Lead Other Project Partners include Brooklyn

More information

Clackamas County Comprehensive Plan

Clackamas County Comprehensive Plan ROADWAYS The County s road system permits the movement of goods and people between communities and regions, using any of a variety of modes of travel. Roads provide access to virtually all property. They

More information

FY 2005 TRANSPORTATION CAPITAL PROGRAM

FY 2005 TRANSPORTATION CAPITAL PROGRAM Avenue P Bridge 03315 This project will provide for the replacement of the existing two-track Conrail Railroad Bridge over Avenue P, a local urban street. The bridge and approaches will be built on the

More information

2018 FTBA ANNUAL CONFERENCE FDOT WORK PROGRAM OVERVIEW BOCA RATON RESORT AND CLUB August 2-5, 2018

2018 FTBA ANNUAL CONFERENCE FDOT WORK PROGRAM OVERVIEW BOCA RATON RESORT AND CLUB August 2-5, 2018 Florida Department of TRANSPORTATION 2018 FTBA ANNUAL CONFERENCE FDOT WORK PROGRAM OVERVIEW BOCA RATON RESORT AND CLUB August 2-5, 2018 Mike Dew, Secretary FLORIDA S CONTINUED GROWTH Florida has currently

More information

Proposed FUL-SR 66 Relocation on to CR 24. Presentation to Archbold Village Council April 17, 2017

Proposed FUL-SR 66 Relocation on to CR 24. Presentation to Archbold Village Council April 17, 2017 Proposed FUL-SR 66 Relocation on to CR 24 Presentation to Archbold Village Council April 17, 2017 Robert J. Seaman, P.E., P.S. Village Engineer Andrew J. Langenderfer, P.E. Sr. Project Manager Agenda Stakeholders

More information

Hard Shoulder Running is a valuable tool July 14, Dean H. Gustafson, PE, PTOE State Operations Engineer VDOT Operations Division

Hard Shoulder Running is a valuable tool July 14, Dean H. Gustafson, PE, PTOE State Operations Engineer VDOT Operations Division Hard Shoulder Running is a valuable tool July 14, 2016 Dean H. Gustafson, PE, PTOE State Operations Engineer VDOT Operations Division Virginia 2 VDOT s Statewide Operations Program Operations Statistics

More information

Financial Project ID No(s).: and ETDM No(s).: and 14181

Financial Project ID No(s).: and ETDM No(s).: and 14181 Palm Beach Metropolitan Planning Organization (MPO) Presentation I-95 at Boynton Beach Boulevard Interchange and I-95 at Gateway Boulevard Interchange Project Development and Environment Study Palm Beach

More information

Building Great Neighbourhoods BONNIE DOON

Building Great Neighbourhoods BONNIE DOON Building Great Neighbourhoods BONNIE DOON We Are Here Today To Explain the Neighbourhood Renewal Process Show you the Westwood Preliminary Design Ask for local knowledge Highlight the Local Improvement

More information

ODOT Major Construction, Bikeways and Enhancements Report for Miami County. (State Fiscal Years 2007 to 2010)

ODOT Major Construction, Bikeways and Enhancements Report for Miami County. (State Fiscal Years 2007 to 2010) Bikeways and Enhancements Report for Miami County (State Fiscal Years 2007 to 2010) Statewide Construction Summary by Major Work Type (in Millions) WORK TYPE SFY 2007 SFY 2008 SFY 2009 SFY 2010 TOTAL #

More information

Access Routes from US 101 to the Richmond San Rafael Bridge

Access Routes from US 101 to the Richmond San Rafael Bridge Access Routes from US 101 to the Richmond San Rafael Bridge TAM Board Meeting January 28, 2016 RSRB Project Elements Eastbound Third Lane: Sir Francis Drake Blvd. to Marine Street 10 ft Barrier Separated

More information

City of Gainesville Transportation/Roadway Needs PROJECT SUMMARY

City of Gainesville Transportation/Roadway Needs PROJECT SUMMARY A1 Roadway Resurfacing $23,846,000 TYPE: Preservation of existing system Roadway resurfacing A2 Signal Replacement $6,000,000 TYPE: Preservation of existing system Replace traffic signals. B1 W 6th St

More information

National Network Safety Analysis (6/4/2015 Revision) FRA and FRA PID 86661

National Network Safety Analysis (6/4/2015 Revision) FRA and FRA PID 86661 Existing Roadway National Network Safety Analysis (6/4/2015 Revision) FRA-23-10.83 and FRA-23-12.24 PID 86661 This 8.82 miles project is on United States Route 23 (US-23) and United States Route 23 Directional

More information

Joshua Saak, P.E., PTOE Traffic Design Engineer Ada County Highway District May 23, 2013

Joshua Saak, P.E., PTOE Traffic Design Engineer Ada County Highway District May 23, 2013 Joshua Saak, P.E., PTOE Traffic Design Engineer Ada County Highway District May 23, 2013 Creating Great Streets Through Road Diets and Conversions The Charlotte Experience Topics to Discuss Charlotte s

More information

Recent and Upcoming Developments along the I-70 Mountain Corridor

Recent and Upcoming Developments along the I-70 Mountain Corridor Recent and Upcoming Developments along the I-70 Mountain Corridor CDOT Region 1 I-70 Mountain Corridor Team Benjamin Acimovic April 2013 10th Annual Transportation Symposium I-70 Corridor Summary I-70

More information

County Road 2 Long Sault Improvements EA Study Schedule C Municipal Class Environmental Assessment. Environmental Study Report

County Road 2 Long Sault Improvements EA Study Schedule C Municipal Class Environmental Assessment. Environmental Study Report Study Schedule C Municipal Class Environmental Assessment Prepared By: BT Engineering 100 Craig Henry Drive, Suite 201 Ottawa, ON K2G 5W3 (613) 228-4813 (855) 228-4813 Toll free Executive Summary Executive

More information

Non-Motorized Transportation 7-1

Non-Motorized Transportation 7-1 Non-Motorized Transportation 7-1 Transportation facilities no longer mean just accommodating a vehicle powered by a combustion engine. Pedestrian and non-motorized facilities are important modes of travel

More information

PUBLIC INFORMATION MEETING

PUBLIC INFORMATION MEETING PUBLIC INFORMATION MEETING Bridge Rehabilitation Project Project Identification Number 5134.45 NY Route 5 Buffalo Skyway I-190 North Ramp, Pearl Street Ramp Wednesday, April 18, 2018 4:00 p.m. to 7:00

More information

Washington DC Section of ITE Project Briefing

Washington DC Section of ITE Project Briefing Washington DC Section of ITE Project Briefing November 5, 2015 Renée Hamilton, VDOT, Deputy District Administrator I-66 Outside the Beltway Improvement Area Project Location Virginia 2 Purpose and Need

More information

Feasibility Study of Pedestrian Crossings Along Route 7, East of Cascades Parkway and West of Dranesville Road. October 3, 2017

Feasibility Study of Pedestrian Crossings Along Route 7, East of Cascades Parkway and West of Dranesville Road. October 3, 2017 Feasibility Study of Pedestrian Crossings Along Route 7, East of Cascades Parkway and West of Dranesville Road October 3, 2017 Study Area (area within a ¼-mile radius of the study intersections) Route

More information

Riverside Drive Complete Streets Project 3 rd Community Meeting. March 26, 2015

Riverside Drive Complete Streets Project 3 rd Community Meeting. March 26, 2015 Riverside Drive Complete Streets Project 3 rd Community Meeting March 26, 2015 Providing Feedback Sign-In with contact information for future updates Complete questionnaire provided tonight Complete comment

More information

COMPLETE STREETS A STEP FORWARD ITE District 10/FSITE Annual Meeting November 3, 2015

COMPLETE STREETS A STEP FORWARD ITE District 10/FSITE Annual Meeting November 3, 2015 COMPLETE STREETS A STEP FORWARD 2015 ITE District 10/FSITE Annual Meeting November 3, 2015 About Lakeland Incorporated: 1885 Population: 100,728 Area: Approx. 75 sq. mi Major Employers: Publix, Lakeland

More information

Route 79/Davol Street Corridor Study

Route 79/Davol Street Corridor Study Route 79/Davol Street Corridor Study Fall River, MA Public Information Meeting #2 November 21, 2013 Fall River Heritage State Park Fall River, MA Agenda Welcome and Introductions Overview of Study Process

More information

PROJECT FACT SHEET May 25, 2018

PROJECT FACT SHEET May 25, 2018 SITE CHALLENGES & PROJECT BACKGROUND In 2014, the City of Aspen identified the Castle Creek Bridge and Hallam Street corridor as a deficient link in Aspen s bicycle and pedestrian network. Safe and efficient

More information

PEDESTRIAN ACCOMMODATIONS DPS 201 AT INTERCHANGES

PEDESTRIAN ACCOMMODATIONS DPS 201 AT INTERCHANGES PEDESTRIAN ACCOMMODATIONS DPS 201 AT INTERCHANGES UNDERSTANDING THE ISSUES Intersections of freeway ramp terminals at crossroads are the most critical components of an interchange Challenge: balance mobility

More information

Trans-Canada Highway 1 RW Bruhn Bridge Replacement

Trans-Canada Highway 1 RW Bruhn Bridge Replacement Trans-Canada Highway 1 RW Bruhn Bridge Replacement May 2016 RW Bruhn Bridge Project Objectives Improve safety, traffic flow and movement of goods Improve safety for pedestrians and cyclists Replace the

More information

Overview. Illinois Bike Summit IDOT Complete Streets Policy Presentation. What is a Complete Street? And why build them? And why build them?

Overview. Illinois Bike Summit IDOT Complete Streets Policy Presentation. What is a Complete Street? And why build them? And why build them? Overview Illinois Bike Summit IDOT Complete Streets Policy Presentation Aren Kriks, P.E. District One Bicycle Coordinator and Bureau of Programming Project Engineer History of Complete Streets IDOT Policy

More information

PROJECT FACT SHEET March 21, 2018

PROJECT FACT SHEET March 21, 2018 SITE CHALLENGES & PROJECT BACKGROUND In 2014, the City of Aspen identified the Castle Creek Bridge and Hallam Street corridor as a deficient link in Aspen s bicycle and pedestrian network. Safe and efficient

More information

Boston Post Road Design Feasibility Study

Boston Post Road Design Feasibility Study Boston Post Road Design Feasibility Study Prepared for the City of Rye Final Report July 18, 2007 Prepared by: Buckhurst Fish & Jacquemart (BFJ) 115 Fifth Avenue New York, NY 10003 www.bfjplanning.com

More information

FDOT Treasure Coast Traffic Impact Report

FDOT Treasure Coast Traffic Impact Report September 29, 2017 Chuck McGinness, 954 777 4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report September 29 through October 6, 2017 TREASURE COAST Construction and maintenance

More information

FY 2004 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects

FY 2004 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects Avenue P Bridge 03315 This project will address potential construction in the vicinity of the Avenue P Bridge. SPONSOR: City of Newark Bridge Preservation - Local Bridges NJTPA 288 DES STATE $400,000 CARGOMATE

More information

Institute for Real Estate Management Chapter (IREM) 77 VDOT Northern Virginia Megaprojects September 13, 2017

Institute for Real Estate Management Chapter (IREM) 77 VDOT Northern Virginia Megaprojects September 13, 2017 Institute for Real Estate Management Chapter (IREM) 77 VDOT Northern Virginia Megaprojects September 13, 2017 Susan Shaw, P.E., Megaprojects Director Virginia Department of Transportation Northern Virginia

More information

Florida s Turnpike Enterprise Tentative Five-Year Work Program - FY 2015/16 thru FY 2019/20 Summary of Projects in FDOT District Five

Florida s Turnpike Enterprise Tentative Five-Year Work Program - FY 2015/16 thru FY 2019/20 Summary of Projects in FDOT District Five DISTRICT FIVE PROJECT OVERVIEW Florida s Turnpike Enterprise continues to make significant project investments in District Five. In fiscal years 2014 and 2015, current Turnpike projects total over $330

More information

COMMUNITY WORKSHOP (CW) 3 February 21, 2015

COMMUNITY WORKSHOP (CW) 3 February 21, 2015 QEW Improvements QEW Improvements COMMUNITY WORKSHOP (CW) 3 February 21, 2015 1 WORKSHOP PURPOSE MOVING FORWARD Review of Technically Preferred alternative Seeking feed back for progressing to next design

More information

STATE OF GEORGIA OFFICE OF THE GOVERNOR

STATE OF GEORGIA OFFICE OF THE GOVERNOR STATE OF GEORGIA OFFICE OF THE GOVERNOR Nathan Deal GOVERNOR For Immediate Release May 28, 2014 Deal announces $33 million in transportation infrastructure project awards 18 governments and CIDs to receive

More information

FDOT Treasure Coast Traffic Impact Report

FDOT Treasure Coast Traffic Impact Report February 10, 2017 Chuck McGinness, 954 777 4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report February 10 through February 17, 2017 TREASURE COAST Construction and maintenance

More information

Offset Single Point Interchange I-25 at Rio Bravo Boulevard Albuquerque, New Mexico

Offset Single Point Interchange I-25 at Rio Bravo Boulevard Albuquerque, New Mexico Offset Single Point Interchange I-25 at Rio Bravo Boulevard Albuquerque, New Mexico INSTITUTE OF TRANSPORTATION ENGINEERS 2016 WESTERN DISTRICT MEETING JULY 11, 2016 7/11/2016 1 Project Vicinity Map 7/11/2016

More information

District Construction Projects

District Construction Projects District 7 2014 Construction Projects Ohio Department of Transportation District 7 AUG-116/197-8.22/5.10 Auglaize County Projects 2014 AUG-65-13.19 AUG-VAR AUG-196-4.15 AUG-67-3.45 AUG-VAR AUG-Heritage

More information

Welcome. 53 Avenue Overpass over Whitemud Drive Rehabilitation. Public Information Session. Wednesday, March 9, :30-8:00 p.m.

Welcome. 53 Avenue Overpass over Whitemud Drive Rehabilitation. Public Information Session. Wednesday, March 9, :30-8:00 p.m. BRIDGE REHABILITATION Welcome 53 Avenue Overpass over Whitemud Drive Rehabilitation Public Information Session Wednesday, March 9, 2016 4:30-8:00 p.m. Tonight you can: Learn about the 53 Avenue Overpass

More information

Foothill Expressway Improvements Between El Monte and San Antonio

Foothill Expressway Improvements Between El Monte and San Antonio Foothill Expressway Improvements Between El Monte and San Antonio June 29, 2017 - Los Altos Community Meeting Introduction Project Background Agenda Visit Stations: Provide Input and Ask Questions Reconvene:

More information

US 20 Feasibility Study. Village Board Meeting. Shales Parkway to IL Route 390 IL Route 390 Extension (North Ave to US 20)

US 20 Feasibility Study. Village Board Meeting. Shales Parkway to IL Route 390 IL Route 390 Extension (North Ave to US 20) US 20 Feasibility Study Shales Parkway to IL Route 390 IL Route 390 Extension (North Ave to US 20) Village Board Meeting Bartlett Village Hall February 16, 2016 1 Background 1991 IDOT Study Recommendations

More information

I-20 ODESSA-MIDLAND CORRIDOR STUDY. Public Meeting for Schematic Design

I-20 ODESSA-MIDLAND CORRIDOR STUDY. Public Meeting for Schematic Design I-20 ODESSA-MIDLAND CORRIDOR STUDY Public Meeting for Schematic Design The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being,

More information

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects ROUTE/ Project ID No. TIP No. Electrical Load Center Replacement - North 04324 04324 This project will provide for the betterment of the existing highway lighting facilities located along Routes 3, 17

More information

2017 FTBA ANNUAL CONFERENCE FDOT WORK PROGRAM OVERVIEW THE RITZ CARLTON, AMELIA ISLAND August 10-13, 2017

2017 FTBA ANNUAL CONFERENCE FDOT WORK PROGRAM OVERVIEW THE RITZ CARLTON, AMELIA ISLAND August 10-13, 2017 Florida Department of TRANSPORTATION 2017 FTBA ANNUAL CONFERENCE FDOT WORK PROGRAM OVERVIEW THE RITZ CARLTON, AMELIA ISLAND August 10-13, 2017 Mike Dew, Secretary FLORIDA S CONTINUED GROWTH Florida has

More information

Current Roadway Projects Wednesday, September 03, 2014

Current Roadway Projects Wednesday, September 03, 2014 Current Roadway Projects Wednesday, September 03, 2014 Restore our Roads Projects 1 US 72 East at Moores Mill Road Additional lane WB from Moores Mill to Sparkman Drive and intersection improvements at

More information