ODOT AND LOCAL NORTHWEST OHIO MAJOR PROJECTS 2018 AND BEYOND
|
|
- Todd Alexander
- 5 years ago
- Views:
Transcription
1 ODOT AND LOCAL NORTHWEST OHIO MAJOR PROJECTS 2018 AND BEYOND TMACOG TRANSPORTATION SUMMIT MARCH 16, 2018 Mike Gramza, District Two, Capital Programs Administrator John R. Kasich, Governor Jerry Wray, ODOT Director Patrick McColley, ODOT Deputy Director
2 I-75 RECONSTRUCTION NORTHWEST OHIO Proj. Sale Date Compl. Date Cost A Dec 2014 Oct 2017 $70,000,000 B Nov 2014 Oct 2018 $134,210,000 C May 2014 Oct 2016 $33,500,000 D May 2018 Spring 2022 $150,000,000 E Feb 2019 Fall 2022 $185,000,000 F May 2014 Aug 2017 $71,500,000 G April 2014 Nov 2016 $74,200,000 H April 2014 Aug 2016 $57,200,000 I Feb 2014 June 2017 $72,800,000 J Feb 2017 Aug 2020 $114,117,000 Total $962,527,000 2
3 RECAP 2017 MAJOR CONSTRUCTION PROJECTS 3
4 I-75 WIDENING: SR582 TO I-475 Cost: $71.5M Completion: spring 2018 Contractor: ES Wagner Designer: ODOT, TetraTech, DGL, Baker 4
5 I-75 WIDENING: SR582 TO I-475 5
6 I-75 WIDENING: SR582 TO I-475 6
7 SR 25 OVER I-475 PERRYSBURG Cost: $8.8M Completion: spring 2018 Contractor: ES Wagner Designer: DGL 7
8 SR 25 OVER I-475 PERRYSBURG 8
9 ANTHONY WAYNE BRIDGE PAINTING Cost: $12.6M Completion: spring 2018 Contractor: UCL Inc. Designer: Arcadis 9
10 PHASE 2: BRIDGE PAINTING 10
11 PHASE 2: BRIDGE PAINTING 11
12 HEN-109 MAUMEE RIVER BRIDGE Cost: $12M Bridge Opened: June 9, 2017 Contractor: Miller Bros. Designer: EL Robinson 12
13 HEN-109 MAUMEE RIVER BRIDGE 13
14 HEN-109 MAUMEE RIVER BRIDGE 14
15 I-75 LAGRANGE TO I-280 Cost: $70M Completion: fall 2017 Contractor: Kokosing Designer: HDR 15
16 I-75 LAGRANGE TO I
17 I-75 LAGRANGE TO I
18 CURRENT MAJOR CONSTRUCTION PROJECTS 18
19 HAN-75 FINDLAY WIDENING Cost: $113M Completion: fall 2020 Contractor: Beaver Designer: WSP 19
20 HAN-75 FINDLAY WIDENING 20
21 HAN-75 FINDLAY WIDENING New fly over ramp (SB I-75 to US68) opens mid summer US68 to SB I-75 closes mid summer NB US224 Ramps will close late spring/early summer for reconstruction NB SR12 ramps will close this summer for reconstruction 21
22 LUC-75/475 Cost: $134M Completion: October 31, 2018 Contractor: Kokosing Designer: B&N, Mannik, TetraTech 22
23 LUC-75/475 23
24 LUC-75/475 24
25 LUC-75/475 Status of major work items 3 spans of Berdan SB deck to be poured-estimated to open to traffic by July 2018 New SB I-75 to WB I-475 ramp to be complete by Aug 2018 New EB I-475 to NB I-75 will be complete in Sept 2018 Berdan and Haverhill, Phillips and Manhattan, Willys parkway roundabouts to be completed yet 25
26 LUC-75/ MOT impacts Phillips to SB I-75 closed All Jeep Parkway ramps except the NB I-75 exit are closed Berdan & Haverhill closed 60 days (May-July) Haverhill closed 60 days (July-Sept) Manhattan & Phillips closed 60 days (June-Aug) Traffic shifts to move into final configuration 26
27 WATERVILLE BRIDGE Cost: $13.4M Completion: September 30, 2020 Contractor: Miller Bros Const. Designer: Mannik & Smith 27
28 WATERVILLE BRIDGE 28
29 WATERVILLE BRIDGE 29
30 WATERVILLE BRIDGE 2018 MOT impacts 45 day closure of SR64 and SR65 to construct the roundabout Scheduled for summer 2018 when school is out between June 1 and Aug. 15 (dates TBD) 30
31 WATERVILLE BRIDGE 31
32 WATERVILLE BRIDGE 32
33 PORT CLINTON LIFT BRIDGE Cost: $13M Completion: May 24, 2018 Contractor: Ruhlin/Perram Designer: Hardesty and Hanover End River closure: April 1, 2018 End Road closure: May 24,
34 PORT CLINTON LIFT BRIDGE 34
35 PORT CLINTON LIFT BRIDGE 35
36 LUC-75 INDIANA AVE Cost: $5M Completion: May 31, 2019 Contractor: Kokosing Designer: WSP 36
37 LUC-75 INDIANA AVE 2018 MOT impacts Washington St. ramp from SB I-75 is reduced to one lane Indiana Ave. will close around Aug 1,
38 TRANSPORTATION SUMMIT 2018 Chris Matta Deputy Chief Engineer Ohio Turnpike and Infrastructure Commission Friday, March 16, 2018
39 3 rd Lane Construction Service Plaza Reconstruction , 03, 10, 11 E ZPass 2009 Pavement Replacement
40 $250,000,000 $225,000,000 $200,000,000 $175,000,000 $150,000,000 $125,000,000 $100,000,000 $75,000,000 $50,000,000 $25,000,000 $0
41
42 Bridge Painting Program Project No MP 21.4 Williams County MP 24.7, 36.3, 37.1, 38.3, 39.3 Fulton County OZEU Paint System Bridge Painting Program Project No MP 94.7, 97.6, 98.1, 100.2, Sandusky County MP 106.1, Erie County OZEU Paint System Bridge Rehabilitation Program Project No MP 59.0 Lucas County MP 84.4 Sandusky County Bridge Replacement / Deck Replacement
43 Mainline Pavement Reconstruction Project No Milepost Lorain & Cuyahoga Counties Full Depth Excavation & Replacement of Pavement Right 2 Lanes & Right Shoulder Bridge Repairs (4 Structures) Construction: April 2018 November 2020 Mainline Pavement Resurfacing Project No Milepost Erie & Lorain Counties Resurfacing of all 3 East & Westbound lanes Construction: April 2018 October 2018 Mainline Pavement Reconstruction Project No Milepost Summit & Cuyahoga Counties Full Depth Excavation & Replacement of Pavement Right 2 Lanes & Right Shoulder Bridge Repairs (4 Structures) Interchange 173 Repairs and Reconstruction Construction: April 2018 November 2020 *All 2018 Mainline Pavement Reconstruction will take place in the Eastbound direction.
44 2019 & Beyond Toll Collection System Modifications
45
46 Legal & Policy 241 Miles 160 Miles of 3 Lanes 8 Long Combination Vehicle Lots (28.4 Total Acres) 7 Sets of Service Plazas (1,412 Commercial Parking Spaces) 241 Miles of Fiber 6 Pavement Markings 55 Emergency Pull Off Areas
47 15 Roadside Units
48
49
50
51 This Tech will Immediately Improve Our Efficiency Provide a Significant Opportunity for Savings of Labor and Materials
52 Thank You Follow us TRANSPORTATION SUMMIT 2018
53 2018 MAJOR CONSTRUCTION PROJECTS 53
54 LUC-25 AWT OVER NORFOLK SOUTHERN RAILROAD Cost: $9.5M Bid Opening: March 2018 Completion: Fall 2019 Designer: Mannik & Smith 54
55 LUC-25 AWT OVER NORFOLK SOUTHERN RAILROAD 55
56 LUC-25 AWT OVER NORFOLK SOUTHERN RAILROAD 56
57 LUC-25 AWT OVER NORFOLK SOUTHERN RAILROAD 2018 MOT impacts AWT will be down to 1 lane inbound and 2 lanes outbound for entire 2018 season (starting about May 1) 57
58 LUC-75 SOUTH AVE. TO DORR ST. Cost: $150M Bid Opening: May 2018 Completion: summer 2022 Designer: WSP 58
59 LUC-75 SOUTH AVE. TO DORR ST MOT impacts Dorr St. Bridge closes for 300 days (late summer/early fall) Weiler Ave closes for storm sewer Installation for approx. 2 weeks (late summer) SR-25 Ramp C (SB I-75 to Outbound AW Trail) closes for 2 Weeks for Storm Sewer installation (summer) 59
60 PHASE 3: LIGHTING AND DEHUMIDIFICATION Cost: $13M Bid Opening: June 2018 Completion: summer 2020 Designer: Arcadis 60
61 DEHUMIDIFICATION 61
62 PHASE 3: LIGHTING AND DEHUMIDIFICATION 62
63 DEHUMIDIFICATION EXTERIOR WRAP 63
64 DEHUMIDIFICATION BUILDING RENDERING 64
65 DECORATIVE LIGHTING Tower Cable Deck Edge 65
66 TOP OF TOWER Historic housing to remain Replace internal HPS lamps with custom LED light source 66
67 EXISTING LIGHTING SYSTEM 67
68 LED LIGHTING 68
69 WOOSTER STREET INTERCHANGE AT I-75 69
70 WOOSTER STREET INTERCHANGE AT I-75 70
71 2018 ODOT AWARDED PROJECTS 2018 ( to ODOT Awarded Projects) 50 ODOT LET Projects for a total of $251M 71
72 Anthony Wayne Trail Gateway Erie Street to I 75 Cost: $4.5 m Roadway Construction completed 2017
73 Anthony Wayne Trail Gateway Erie Street to I 75
74 Anthony Wayne Trail Gateway Erie Street to I 75 Streetscape/Landscape elements complete Fall 2018
75 Bancroft Street Westwood to Parkside east end road diet 3 lanes & bike lanes completed 2017 Westwood to Perth Perth to Parkside
76 Bancroft Street Secor to Westwood west end 5 lanes, median islands at UT & bike lanes construction 2018 Secor to Campus UT Area University HIlls- to Westood
77 Overland Industrial Park Connector Phillips to Willys Parkway Redevelop connecting corridor reconstruct Berdan & Jeep Parkway 5 roundabouts, bike path complete Fall 2018 A NEW CORRIDOR TO SUPPORT REDEVELOPMENT
78 North and South Expressway Drives Lagrange to Stickney Finish Polish Village interchange roads & bike path $3.2 m. Fall 2018
79 AWT Reconstruction Plan Downtown to Maumee Phase 1 South to CBD, reconstruct with committed projects by 2022 Phase 2 Glendale to South, resurface 2018 Phase 3 Detroit to Glendale, reconstruct/narrow, partially programmed
80 Front/Millard from I 280 to Tiffin Avenue (related to new Cliffs Furnace) $5.7 m. Toledo Port Partnership Begin Fall 2018 complete 2019
81 Downtown Toledo Resurfacing/Utility Improvements Toledo Waterways Initiative CSO elimination and Monroe/Summit/Erie/Michigan Resurface
82 Overland Trail (OV) and Chessie Circle (CC) UT to Bowman Park and Stickney (Bike) 2018 OV Project 1 S. Cove to Jeep Parkway OV Project 2 Bancroft to Monroe cc Project 3 Connector Bancroft to Chessie Corridor 2021 CC North Paved Path Bowman Park to Bancroft (UT)
83 Major 2019 Committed Projects Detroit Avenue Byrne to Copland, full reconstruct, roundabout at Byrne, bike lanes $3.5 m. Complete Fall 2019 South Avenue Reynolds to Byrne, full reconstruct, roundabout at Wenz, bike lanes $5.3 m. Complete Fall 2019 Monroe Street Talmadge to Secor, reconstruct/realign mall entrances/resurface $3.2 m. Complete Fall 2019 Heatherdowns/Perrysburg Holland/Garden Road intersection, reconstruct $3.6 m. Complete Fall 2019
84 Cherry St Transit Hub Goodwill Building
85 Downtown Toledo Bike Share 18 Stations near hubs of activity within a 2 mile radius downtown 100 bikes / 150 rack-capacity Smart Bike Technology Launch as early as July 31, 2018
86 UPCOMING MAJOR CONSTRUCTION PROJECTS CONSTRUCTION FUNDING SECURED 86
87 WOO/LUC-75 GLENWOOD TO SOUTH Cost: $185M Bid Opening: Feb 2019 Completion: fall 2022 Designer: AECOM 87
88 LUC-475 WIDENING SR2 TO US20 88
89 TRAC 89
90 TRAC ADDITIONS TIER 1 90
91 I-475 DORR ST. INTERCHANGE Cost: $41M Bid Opening: spring 2020 Completion: summer 2021 Designer: TetraTech, Mannik,DGL 91
92 DORR ST AND MCCORD ROUNDABOUT 92
93 FUTURE MAJOR CONSTRUCTION PROJECTS CONSTRUCTION FUNDING NOT SECURED 93
94 LUC-20A INTERCHANGE & I-475 WIDENING Cost: $28M US 20A $64M I-475 Bid Opening: unknown Completion: Bid opening + 2 Designer: Arcadis 94
95 LUC-20A INTERCHANGE 95
96 WHERE IS ODOT HEADING IN THE FUTURE? 96
97 The Future of Smart Mobility will continuously Drive Ohio s preparation and leadership for the future of transportation technology Governor Kasich signs the Executive Order establishing DriveOhio as the statewide center for smart mobility Executive Director Jim Barna
98 WORKING GROUPS/FOCUS AREAS Data Analytics and Security Infrastructure Telecommunications/Right-of-Way Vehicle Deployment Budget/Partnerships Communications Policy/Regulatory Education & Workforce Development
99 SMART MOBILITY IN OHIO: HAPPENING NOW
100 INITIATIVES o US 33 Smart Mobility Corridor o Interstate 90 Lake Effect Corridor o Interstate 670 Smart lane o Interstate 80 - Ohio Turnpike o Connected Marysville o Smart Columbus
101 REAL-TIME TRAFFIC MANAGEMENT o Planning and Asset Management o Predictive Traffic Analytics o Hard Shoulder Running o Traffic Re-routing o Emergency Response o Wrong-way Warning/Avoidance o Adverse Weather/Road Conditions o Enhanced Traveler Information o Just-in-time Delivery/Commuter Commercial Truck Parking Availability o Work Zone Identification
102 2016 OHIO CRASHES 305,959 Crashes 9,207 Serious injuries 112,276 Injuries 1,133 Fatalities 102
103 FEEDBACK 103
104 FEEDBACK 104
105 QUESTIONS 105
District 2 Projects Scheduled for award during the period from 06/19/18 to 06/18/19 Sorted by PID
77825 SA US 6/20 14.61/14.59 R Resurface US-6/US-20; perform necessary (Originally PID 76709); UPDATE (9/25/14) added culvert at SA-20-22.50 PID 95861. SSAUS00006**C 14.610 18.450 8,950,000.00 SA US 6/20
More informationODOT DISTRICT CONSTRUCTION PROGRAM SERVING BUTLER, CLERMONT, CLINTON, GREENE, HAMILTON, PREBLE AND WARREN COUNTIES.
ODOT DISTRICT 8 2018 CONSTRUCTION PROGRAM Preble Greene SERVING BUTLER, CLERMONT, CLINTON, GREENE, HAMILTON, PREBLE AND WARREN COUNTIES. Butler Hamilton Warren Clinton Lebanon Clermont John R. Kasich,
More informationHighway Construction
Ohio Department of Transportation Traffic Advisory DISTRICT 1 KIRK SLUSHER, P.E., DISTRICT DEPUTY DIRECTOR 1885 North McCullough St. Lima, Ohio 45801 www.transportation.ohio.gov/dist1 www.facebook.com/odotdistrict1;
More informationCOMMITTED TOTAL 9,518,714 5,167, ,800 15,185,405 BALANCE (2,486,243) 6,751, ,256 5,082,514
TMACOG TIP PROGRAM FY2010 AND FY2011 PLUS PIPELINE PROJECTION FY2012 THROUGH 2017 revised 02/03/2010 FISCAL PROJECT R/W PS&E FEDERAL PROJECT CONSTRUCT CONSTRUCT YEAR PID SPONSOR PROJECT NAME PROJECT LIMITS
More informationDISTRICT CONSTRUCTION PROGRAM
ODOT DISTRICT 3 2016 CONSTRUCTION PROGRAM photo by Tom Puskar SERVING ASHLAND, CRAWFORD, ERIE, HURON, LORAIN, MEDINA, RICHLAND AND WAYNE COUNTIES JOHN R. KASICH, OHIO GOVERNOR JERRY WRAY, ODOT DIRECTOR
More informationOhio Department of Transportation STIP Project Listing (Appendix 6) as of 7/25/2018 Query: "Current STIP Detail 4"
Ohio Department of Transportation - Listing (Appendix 6) as of 7/25/ Query: "Current Detail 4" Agency Dist PID MPO Cnty Name (ie CRS) Descript / Category / Termini Sponsoring Agency Air Quality Status
More informationVT15 / Allen Martin Drive Intersection Scoping Study
VT15 / Allen Martin Drive Intersection Scoping Study ALTERNATIVES PRESENTATION MEETING DECEMBER 19, 2016 Agenda Study Area Project Background Existing Conditions Identified Issues Proposed Alternatives
More informationCITY OF WOODINVILLE ONGOING CAPITAL IMPROVEMENT PROJECT UPDATES
CITY OF WOODINVILLE ONGOING CAPITAL IMPROVEMENT PROJECT UPDATES PROJECT LOCATION MAP (1) DEYOUNG PARK IMPROVEMENTS Project Description - DeYoung Park Improvements include treehouse deck, play area, new
More informationI-70 NEW STANTON INTERCHANGE
I-70 NEW STANTON INTERCHANGE Westmoreland County, PA Submitted by: PROJECT DESCRIPTION Situated adjacent to the PA Turnpike (I-76) and Interstate 70 in Westmoreland County, New Stanton bills itself as
More informationWelcome. Thank you for your interest in the Lewis & Clark Viaduct Concept Study
Welcome Thank you for your interest in the Lewis & Clark Viaduct Concept Study Please use the arrows in the upper left hand corner to navigate through the presentation. Use the envelope icon to ask a question
More informationA: PLANNED P ROJECTS PROJECTS
Appendix A: PLANNED PROJECTS Programming Study Sound Barrier along south side of for approx. 2100 feet. Construction Complete $850,000 5 8613.00 Y Y Y Sound Barrier along south side of for 500' west of
More informationInterstate Route 77 / US Route 62 / State Route 687 (Fulton Road) Transportation Improvement Project. Prepared September 6, 2017
EODOT Project: ODOT Project: STA-IR 77-.50; PID 00290 Interstate Route 77 / US Route 62 / State Route 687 (Fulton Road) Transportation Improvement Project Summary of Public Comments Received and Responses
More informationFDOT Treasure Coast Traffic Report
July 13, 2018 Barbara Kelleher, 954 777 4090 Barbara.Kelleher@dot.state.fl.us FDOT Treasure Coast Traffic Report July 13 through July 20, 2018 TREASURE COAST Construction and maintenance related lane closures
More informationINGHAM COUNTY ROAD DEPARTMENT AUSTIN E. CAVANAUGH ADMINISTRATION BUILDING 301 Bush Street, P.O. Box 38, Mason, MI
INGHAM COUNTY ROAD DEPARTMENT AUSTIN E. CAVANAUGH ADMINISTRATION BUILDING 301 Bush Street, P.O. Box 38, Mason, MI 48854-0038 March 27, 2018 William M. Conklin, P.E. Managing Director FOR IMMEDIATE RELEASE:
More informationSarasota/Manatee MPO Project Priorities 2016 Adopted April 25, 2016
All projects on the following priority lists should be implemented in the priority sequence listed, as consistent with the fiscal constraints identified in the MPO s adopted Long Range Transportation Plan
More informationFM #: ETDM #: 11241
SR 826/Palmetto Expressway PD&E Study From SR 93/I 75 to the Golden Glades Interchange FM #: 418423 1 22 01 ETDM #: 11241 Agency/ Kick Off Meeting October 27, 2011 2 Location Map From SR 93/I 75 to Golden
More informationAPPENDIX D: SACRAMENTO URBAN AREA TRANSPORTATION PRIORITIES
1 County County County County 2 Yolo Arterial Roadway Collector Roadway Urban Residential Street Rural Residential Roadway I-80 / U.S. 50 Bus/Carpool Lanes in both directions Richards Blvd PM Yol 80 0.237
More informationDesign Criteria. Design Criteria
F Design Criteria Design Criteria Ministry of Transportation Ministère des Transports DESIGN CRITERIA Page: 1 of 13 WORK PROJECT NO. N/A GO Bloomington Station TYPE OF PROJECT LOCATION Bloomington Road
More informationBlair/Williamson Intersection Expressed Needs
Blair/Williamson Intersection Expressed Needs NORTH Blair Street is a barrier for pedestrians and bicycles Relocate Capitol City Trail crossing from Blair Street and John Nolen Drive intersection to Williamson
More informationOhio Department of Transportation STIP Project Listing as of 7/27/2017 Query: "Current STIP Detail 4"
Ohio Department of Transportation - Listing as of 7/27/ Query: "Current Detail 4" Dist PID MPO Cnty Name (ie CRS) Descript / Category / Termini Sponsoring Air Quality Status Reference (New) FHWA 1 80441
More informationDescription: Widen I-64 to 6 lanes from I-265 to the KY 53 interchange in Shelby County.
I-64 KIPDA ID # 350 Project Type: ROADWAY CAPACITY Description: Widen I-64 to 6 lanes from I-265 to the KY 53 interchange in Shelby County. Purpose: Project will improve capacity and address safety concerns.
More informationFDOT Treasure Coast Traffic Report
July 6, 2018 Barbara Kelleher, 954 777 4090 Barbara.Kelleher@dot.state.fl.us FDOT Treasure Coast Traffic Report July 6 through July 13, 2018 TREASURE COAST Construction and maintenance related lane closures
More informationFY 2006 TRANSPORTATION CAPITAL PROGRAM
Eden Lane Bridge over Whippany River NS9908 The existing structure was built in 1972 as a temporary single-span structure. The bridge consists of simply supported steel acrow panel trusses and is supported
More informationMay 10, 2013 Meredith Cruz, (561) Palm Beach County Traffic Report May 10 through May 17, 2013
May 10, 2013 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report May 10 through May 17, 2013 Palm Beach County Palm Beach County traffic will be affected this week by ongoing
More informationSR 53 Corridor Study. Final Report Presentation. Friday, October 3, :00 AM to noon
SR 53 Corridor Study Final Report Presentation Friday, October 3, 2014 10:00 AM to noon SR 53 Corridor Study Final Report Presentation Study Purpose: Investigate safety improvements along the SR 53 corridor
More informationMIAMI & ERIE CANAL SHARED USE TRAIL
New Bremen, Ohio Survey Transportation Engineering Grant Writing Project Cost Engineers Estimate: $509,358 Bid Amount $480,892 Size 1.12 miles $597,696 ODOT TEP $249,815 ODNR Completion Projected 11/15/14
More informationDeck Rehabilitation and Steel Repairs Maurice J. Tobin Memorial Bridge
Deck Rehabilitation and Steel Repairs Maurice J. Tobin Memorial Bridge US 1 NB & Ramps Chelsea September 11, 2017 Maurice J. Tobin Memorial Bridge Big Mystic Truss Current Project Little Mystic Truss Toll
More informationNorth Carolina Department of Transportation American Recovery and Reinvestment Act of 2009 Division One Highway Infrastructure Program Summary
Division One Highway Infrastructure Program Summary 1 Hyde NC 12 Northern Ferry Dock Ocracoke Village R-5149 Resurface and Widening to Accommodate Bicycling 13.3 $3,310,000 $0 $3,310,000 Jul-09 1 Dare
More informationLos Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, AGENDA ITEM #2.B Presentation
Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, 2015 AGENDA ITEM #2.B Presentation Previous Presentations Los Altos Hills Town Council in May 2014 and February 2015 Palo Alto
More informationLet s Make I-40 Better Action Team. Friday, March 29, 2019 Hosted by RTP Foundation
Let s Make I-40 Better Action Team Friday, March 29, 2019 Hosted by RTP Foundation RTA Welcome Geoff Lang, MetLife, RTA Chair Jim Beley, The Umstead Hotel & Spa, RTA regional travel experience chair NCDOT
More informationRoute 245 over Broad Run. The recently replaced bridge links The Plains and other communities in northern Fauquier to Interstate 66.
28 VIRGINIA DEPARTMENT OF TRANSPORTATION \\ CULPEPER DISTRICT Route 245 over Broad Run. The recently replaced bridge links The Plains and other communities in northern Fauquier to Interstate 66. PROJECT
More informationHarrah s Station Square Casino
Transportation Analysis Harrah s Station Square Casino Pittsburgh, Pennsylvania Submitted To: City of Pittsburgh and Pennsylvania Gaming Control Board Prepared By: DKS Associates GAI Consultants December
More informationBluffdale/ UDOT South High-T Intersection Project Type Operations
Bluffdale/ UDOT 14600 South High-T Intersection Project Type Operations 14600 South and Redwood Road $ 600,000 $ 550,000 This project is to install a new High-T intersection at Redwood Road and 14600 South
More informationI-95/Temple Avenue Improvements Project Colonial Heights, VA
I-95/Temple Avenue Improvements Project Colonial Heights, VA Pardon Our Dust Informational Meeting February 3, 2016 Harold Dyson, P.E. Construction Manager, Richmond District Tom Heil, P.E. Allan Myers
More informationTerwillegar Drive Expressway Draft Concept Plan
Terwillegar Drive Expressway Draft Concept Plan Anthony Henday Drive to Whitemud Drive November 28 5:00-8:00 p.m. December 1 10:00 a.m. - 3:00 p.m. Let s Talk Today you can: Learn about the new direction
More informationPRESENTATION WILL BEGIN AT APPROXIMATELY 6:05 P.M. I-90 EXIT 406 INTERCHANGE MODIFICATION STUDY AND ENVIRONMENTAL ASSESSMENT MARKET
PRESENTATION WILL BEGIN AT APPROXIMATELY 6:05 P.M. MARKET I-90 EXIT 406 INTERCHANGE MODIFICATION STUDY AND ENVIRONMENTAL ASSESSMENT JANUARY 23, 2017 Public Meeting & Open House #2 TODAY S MEETING Purpose:
More informationFY 2018 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects
Camden County Bus Purchase Project ID Numbers: D0601 / 068082 In the DVRPC region, a combination of fixed route, subscription, and demand responsive transit services are provided in Camden County by Senior
More informationFI N A N C I A L RESOURCER S REVIEW AND UPDATE M I A M I-DADE LO N G R A N G E TRANSPORT T ATION PLAN UPDATE TO THE YE
Appendix B: Miami-Dade LRTP Cost Feasible Projects (Fully Funded and Partially Funded Projects) Fully Funded Projects Existing County roads O&M $317.9 $316.7 $811.5 Non Motorized set aside $27.9 $24.7
More informationDelaware Avenue Corridor Study
Delaware Avenue Corridor Study City of Marysville, Ohio February 19, 2009 ms consultants, inc. engineers, architects, planners 2221 Schrock Road Columbus, Ohio 43229-1547 ms ms consultants, inc. engineers
More informationODOT construction cost is $51,000,000. State assumes and bears 100 percent of the cost of improvement.
1. I 271 WIDENING & RESURFACING - PID 89458 Project consists of major reconstruction, widening and bridge deck replacement. Project will accomplish widening from 4 to 6 lanes, including redecking and widening
More informationI 595 Express Corridor Improvements Project. February 2014 Update
I 595 Express Corridor Improvements Project February 2014 Update PROJECT COMPONENTS Reversible Express Lanes Direct Connect to Florida s Turnpike Open Road Tolling SR 84 Continuous Connection Florida s
More informationFreeway System Considerations
Session 11 Jack Broz, PE, HR Green May 5-7, 2010 Freeway System Considerations Mainline Transit: Shoulder Operations, BRT, Stations HOV, HOT, UPA Interchanges Exit Ramps Entrance Ramps Bridges Local Crossings
More informationCongress Avenue. Palm Beach MPO Subcommittee Meetings December 2017
1 Congress Avenue Palm Beach MPO Subcommittee Meetings December 2017 2 Agenda Study Purpose Study Process Multimodal Alternatives Development Next Steps *ACTION ITEM: CONFIRM ALTERNATIVES TO MOVE INTO
More informationOperations -- Transit From: N/A To: N/A. Improvement Type: Regionally Significant: No
Central Puget Sound Regional 2017-2020 Transportation Improvement Program Amendments and Corrections to be included in the 2017-20 STIP PSRC's Amendment 2017-08 County: King List of 17-08 Amendment Projects:
More informationPrinceton Avenue and Spruce Street Transportation and Site Access Enhancements Project
Princeton Avenue and Spruce Street Transportation and Site Access Enhancements Project Mercer County Planning Division AECOM Transportation (formerly DMJM Harris) January 29, 2009 Agenda Project Status
More informationNorthwest Corridor Project Interchange Modification, Interchange Justification and System Analysis Report Reassessment (Phase I)
Northwest Corridor Project Interchange Modification, Interchange Justification and System Analysis Report Reassessment (Phase I) Introduction The Georgia Department of Transportation (GDOT) prepared a
More informationIowa Highway 58 Corridor Improvement Study
1 Iowa Highway 58 Corridor Improvement Study Public Informational Meeting May 6, 2014 2 Welcome and Introductions Randy Lorenzen, City of Cedar Falls Engineer 3 Outline of Presentation Review of Project
More informationRIVERSIDE COUNTY TRANSPORTATION COMMISSION - UPDATE
RIVERSIDE COUNTY TRANSPORTATION COMMISSION - UPDATE CMAA Southern California Chapter June 21, 2018 Marlin Feenstra, Director of Project Delivery ORG CHART (SIMPLE) Is it Marlin s Project? START Questions?
More informationROUTE 81 CORRIDOR STUDY DESIGN CONCEPTS
RT 81 Corridor Study CLINTON ROUTE 81 CORRIDOR STUDY DESIGN CONCEPTS View north on High Street, with potential improvements to the streetscape Draft Recommendations November 8 th, 2018 TOWN OF CLINTON
More informationCapital Beltway HOT Lanes Project
New Travel Choices Ahead Some things can t wait for traffic Capital Beltway HOT Lanes Project Fairfax County TAC Update August 16, 2011 Major Milestones Reached Some things can t wait for traffic Project
More informationT W P L A I A A V O L H S Bike Network Plan Sylvania, Ohio. July 20, 2009
Y 2009 E T W O R K N P L A E N K I B N I A A V O L H S O I 2009 Bike Network Plan Sylvania, Ohio I-75 Lenawee County US 23 Monroe County I-75 Michigan Ohio SYLVANIA Alexis Rd I-475 Monroe 24 I-75 20/120
More informationChapter 7 ACCESS MANAGEMENT RELATED ACCOMPLISHMENTS
Chapter 7 ACCESS MANAGEMENT RELATED ACCOMPLISHMENTS Introduction The US-41/M-28 Access Management Plan was the first of its kind in the Upper Peninsula. Since 2004, when the Corridor Advisory Group first
More informationFY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects
Barclay Street Viaduct NS9807 NS9807 This project will provide for the rehabilitation of the Barclay Street Viaduct, from Route 19 to Marshall Street, in order to increase the weight load of the structure.
More informationFDOT Treasure Coast Traffic Impact Report April 7 through April 14, 2017
April 7, 2017 Chuck McGinness, 954 777 4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report April 7 through April 14, 2017 TREASURE COAST Construction and maintenance related
More informationAGENDA ACTION ITEMS INFORMATION ITEMS
NOACA Bicycle and Pedestrian Advisory Council Meeting Friday, June 20 th, 2014 10:30 a.m. NOACA Office 1299 Superior Avenue Cleveland, Ohio 44114 Phone: (216) 241-2414; website: www.noaca.org AGENDA ACTION
More informationI-264 CORRIDOR EVALUATION STUDY. September 7, 2016 Eric Stringfield VDOT Planning Director Chris Lawrence AECOM Senior Transportation Engineer
I-264 CORRIDOR EVALUATION STUDY September 7, 2016 Eric Stringfield VDOT Planning Director Chris Lawrence AECOM Senior Transportation Engineer Study Overview Interchange Locations Study Context Follow-up
More informationBrooklyn Boulevard (County Road 152) Reconstruction Project Phase I. OPEN HOUSE June 20, 2017
Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I OPEN HOUSE June 20, 2017 Brooklyn Boulevard (County Road 152) Phase I Project Partners Project Lead Other Project Partners include Brooklyn
More informationClackamas County Comprehensive Plan
ROADWAYS The County s road system permits the movement of goods and people between communities and regions, using any of a variety of modes of travel. Roads provide access to virtually all property. They
More informationFY 2005 TRANSPORTATION CAPITAL PROGRAM
Avenue P Bridge 03315 This project will provide for the replacement of the existing two-track Conrail Railroad Bridge over Avenue P, a local urban street. The bridge and approaches will be built on the
More information2018 FTBA ANNUAL CONFERENCE FDOT WORK PROGRAM OVERVIEW BOCA RATON RESORT AND CLUB August 2-5, 2018
Florida Department of TRANSPORTATION 2018 FTBA ANNUAL CONFERENCE FDOT WORK PROGRAM OVERVIEW BOCA RATON RESORT AND CLUB August 2-5, 2018 Mike Dew, Secretary FLORIDA S CONTINUED GROWTH Florida has currently
More informationProposed FUL-SR 66 Relocation on to CR 24. Presentation to Archbold Village Council April 17, 2017
Proposed FUL-SR 66 Relocation on to CR 24 Presentation to Archbold Village Council April 17, 2017 Robert J. Seaman, P.E., P.S. Village Engineer Andrew J. Langenderfer, P.E. Sr. Project Manager Agenda Stakeholders
More informationHard Shoulder Running is a valuable tool July 14, Dean H. Gustafson, PE, PTOE State Operations Engineer VDOT Operations Division
Hard Shoulder Running is a valuable tool July 14, 2016 Dean H. Gustafson, PE, PTOE State Operations Engineer VDOT Operations Division Virginia 2 VDOT s Statewide Operations Program Operations Statistics
More informationFinancial Project ID No(s).: and ETDM No(s).: and 14181
Palm Beach Metropolitan Planning Organization (MPO) Presentation I-95 at Boynton Beach Boulevard Interchange and I-95 at Gateway Boulevard Interchange Project Development and Environment Study Palm Beach
More informationBuilding Great Neighbourhoods BONNIE DOON
Building Great Neighbourhoods BONNIE DOON We Are Here Today To Explain the Neighbourhood Renewal Process Show you the Westwood Preliminary Design Ask for local knowledge Highlight the Local Improvement
More informationODOT Major Construction, Bikeways and Enhancements Report for Miami County. (State Fiscal Years 2007 to 2010)
Bikeways and Enhancements Report for Miami County (State Fiscal Years 2007 to 2010) Statewide Construction Summary by Major Work Type (in Millions) WORK TYPE SFY 2007 SFY 2008 SFY 2009 SFY 2010 TOTAL #
More informationAccess Routes from US 101 to the Richmond San Rafael Bridge
Access Routes from US 101 to the Richmond San Rafael Bridge TAM Board Meeting January 28, 2016 RSRB Project Elements Eastbound Third Lane: Sir Francis Drake Blvd. to Marine Street 10 ft Barrier Separated
More informationCity of Gainesville Transportation/Roadway Needs PROJECT SUMMARY
A1 Roadway Resurfacing $23,846,000 TYPE: Preservation of existing system Roadway resurfacing A2 Signal Replacement $6,000,000 TYPE: Preservation of existing system Replace traffic signals. B1 W 6th St
More informationNational Network Safety Analysis (6/4/2015 Revision) FRA and FRA PID 86661
Existing Roadway National Network Safety Analysis (6/4/2015 Revision) FRA-23-10.83 and FRA-23-12.24 PID 86661 This 8.82 miles project is on United States Route 23 (US-23) and United States Route 23 Directional
More informationJoshua Saak, P.E., PTOE Traffic Design Engineer Ada County Highway District May 23, 2013
Joshua Saak, P.E., PTOE Traffic Design Engineer Ada County Highway District May 23, 2013 Creating Great Streets Through Road Diets and Conversions The Charlotte Experience Topics to Discuss Charlotte s
More informationRecent and Upcoming Developments along the I-70 Mountain Corridor
Recent and Upcoming Developments along the I-70 Mountain Corridor CDOT Region 1 I-70 Mountain Corridor Team Benjamin Acimovic April 2013 10th Annual Transportation Symposium I-70 Corridor Summary I-70
More informationCounty Road 2 Long Sault Improvements EA Study Schedule C Municipal Class Environmental Assessment. Environmental Study Report
Study Schedule C Municipal Class Environmental Assessment Prepared By: BT Engineering 100 Craig Henry Drive, Suite 201 Ottawa, ON K2G 5W3 (613) 228-4813 (855) 228-4813 Toll free Executive Summary Executive
More informationNon-Motorized Transportation 7-1
Non-Motorized Transportation 7-1 Transportation facilities no longer mean just accommodating a vehicle powered by a combustion engine. Pedestrian and non-motorized facilities are important modes of travel
More informationPUBLIC INFORMATION MEETING
PUBLIC INFORMATION MEETING Bridge Rehabilitation Project Project Identification Number 5134.45 NY Route 5 Buffalo Skyway I-190 North Ramp, Pearl Street Ramp Wednesday, April 18, 2018 4:00 p.m. to 7:00
More informationWashington DC Section of ITE Project Briefing
Washington DC Section of ITE Project Briefing November 5, 2015 Renée Hamilton, VDOT, Deputy District Administrator I-66 Outside the Beltway Improvement Area Project Location Virginia 2 Purpose and Need
More informationFeasibility Study of Pedestrian Crossings Along Route 7, East of Cascades Parkway and West of Dranesville Road. October 3, 2017
Feasibility Study of Pedestrian Crossings Along Route 7, East of Cascades Parkway and West of Dranesville Road October 3, 2017 Study Area (area within a ¼-mile radius of the study intersections) Route
More informationRiverside Drive Complete Streets Project 3 rd Community Meeting. March 26, 2015
Riverside Drive Complete Streets Project 3 rd Community Meeting March 26, 2015 Providing Feedback Sign-In with contact information for future updates Complete questionnaire provided tonight Complete comment
More informationCOMPLETE STREETS A STEP FORWARD ITE District 10/FSITE Annual Meeting November 3, 2015
COMPLETE STREETS A STEP FORWARD 2015 ITE District 10/FSITE Annual Meeting November 3, 2015 About Lakeland Incorporated: 1885 Population: 100,728 Area: Approx. 75 sq. mi Major Employers: Publix, Lakeland
More informationRoute 79/Davol Street Corridor Study
Route 79/Davol Street Corridor Study Fall River, MA Public Information Meeting #2 November 21, 2013 Fall River Heritage State Park Fall River, MA Agenda Welcome and Introductions Overview of Study Process
More informationPROJECT FACT SHEET May 25, 2018
SITE CHALLENGES & PROJECT BACKGROUND In 2014, the City of Aspen identified the Castle Creek Bridge and Hallam Street corridor as a deficient link in Aspen s bicycle and pedestrian network. Safe and efficient
More informationPEDESTRIAN ACCOMMODATIONS DPS 201 AT INTERCHANGES
PEDESTRIAN ACCOMMODATIONS DPS 201 AT INTERCHANGES UNDERSTANDING THE ISSUES Intersections of freeway ramp terminals at crossroads are the most critical components of an interchange Challenge: balance mobility
More informationTrans-Canada Highway 1 RW Bruhn Bridge Replacement
Trans-Canada Highway 1 RW Bruhn Bridge Replacement May 2016 RW Bruhn Bridge Project Objectives Improve safety, traffic flow and movement of goods Improve safety for pedestrians and cyclists Replace the
More informationOverview. Illinois Bike Summit IDOT Complete Streets Policy Presentation. What is a Complete Street? And why build them? And why build them?
Overview Illinois Bike Summit IDOT Complete Streets Policy Presentation Aren Kriks, P.E. District One Bicycle Coordinator and Bureau of Programming Project Engineer History of Complete Streets IDOT Policy
More informationPROJECT FACT SHEET March 21, 2018
SITE CHALLENGES & PROJECT BACKGROUND In 2014, the City of Aspen identified the Castle Creek Bridge and Hallam Street corridor as a deficient link in Aspen s bicycle and pedestrian network. Safe and efficient
More informationBoston Post Road Design Feasibility Study
Boston Post Road Design Feasibility Study Prepared for the City of Rye Final Report July 18, 2007 Prepared by: Buckhurst Fish & Jacquemart (BFJ) 115 Fifth Avenue New York, NY 10003 www.bfjplanning.com
More informationFDOT Treasure Coast Traffic Impact Report
September 29, 2017 Chuck McGinness, 954 777 4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report September 29 through October 6, 2017 TREASURE COAST Construction and maintenance
More informationFY 2004 TRANSPORTATION CAPITAL PROGRAM New Jersey Department of Transportation Projects
Avenue P Bridge 03315 This project will address potential construction in the vicinity of the Avenue P Bridge. SPONSOR: City of Newark Bridge Preservation - Local Bridges NJTPA 288 DES STATE $400,000 CARGOMATE
More informationInstitute for Real Estate Management Chapter (IREM) 77 VDOT Northern Virginia Megaprojects September 13, 2017
Institute for Real Estate Management Chapter (IREM) 77 VDOT Northern Virginia Megaprojects September 13, 2017 Susan Shaw, P.E., Megaprojects Director Virginia Department of Transportation Northern Virginia
More informationFlorida s Turnpike Enterprise Tentative Five-Year Work Program - FY 2015/16 thru FY 2019/20 Summary of Projects in FDOT District Five
DISTRICT FIVE PROJECT OVERVIEW Florida s Turnpike Enterprise continues to make significant project investments in District Five. In fiscal years 2014 and 2015, current Turnpike projects total over $330
More informationCOMMUNITY WORKSHOP (CW) 3 February 21, 2015
QEW Improvements QEW Improvements COMMUNITY WORKSHOP (CW) 3 February 21, 2015 1 WORKSHOP PURPOSE MOVING FORWARD Review of Technically Preferred alternative Seeking feed back for progressing to next design
More informationSTATE OF GEORGIA OFFICE OF THE GOVERNOR
STATE OF GEORGIA OFFICE OF THE GOVERNOR Nathan Deal GOVERNOR For Immediate Release May 28, 2014 Deal announces $33 million in transportation infrastructure project awards 18 governments and CIDs to receive
More informationFDOT Treasure Coast Traffic Impact Report
February 10, 2017 Chuck McGinness, 954 777 4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report February 10 through February 17, 2017 TREASURE COAST Construction and maintenance
More informationOffset Single Point Interchange I-25 at Rio Bravo Boulevard Albuquerque, New Mexico
Offset Single Point Interchange I-25 at Rio Bravo Boulevard Albuquerque, New Mexico INSTITUTE OF TRANSPORTATION ENGINEERS 2016 WESTERN DISTRICT MEETING JULY 11, 2016 7/11/2016 1 Project Vicinity Map 7/11/2016
More informationDistrict Construction Projects
District 7 2014 Construction Projects Ohio Department of Transportation District 7 AUG-116/197-8.22/5.10 Auglaize County Projects 2014 AUG-65-13.19 AUG-VAR AUG-196-4.15 AUG-67-3.45 AUG-VAR AUG-Heritage
More informationWelcome. 53 Avenue Overpass over Whitemud Drive Rehabilitation. Public Information Session. Wednesday, March 9, :30-8:00 p.m.
BRIDGE REHABILITATION Welcome 53 Avenue Overpass over Whitemud Drive Rehabilitation Public Information Session Wednesday, March 9, 2016 4:30-8:00 p.m. Tonight you can: Learn about the 53 Avenue Overpass
More informationFoothill Expressway Improvements Between El Monte and San Antonio
Foothill Expressway Improvements Between El Monte and San Antonio June 29, 2017 - Los Altos Community Meeting Introduction Project Background Agenda Visit Stations: Provide Input and Ask Questions Reconvene:
More informationUS 20 Feasibility Study. Village Board Meeting. Shales Parkway to IL Route 390 IL Route 390 Extension (North Ave to US 20)
US 20 Feasibility Study Shales Parkway to IL Route 390 IL Route 390 Extension (North Ave to US 20) Village Board Meeting Bartlett Village Hall February 16, 2016 1 Background 1991 IDOT Study Recommendations
More informationI-20 ODESSA-MIDLAND CORRIDOR STUDY. Public Meeting for Schematic Design
I-20 ODESSA-MIDLAND CORRIDOR STUDY Public Meeting for Schematic Design The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being,
More informationFY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects
ROUTE/ Project ID No. TIP No. Electrical Load Center Replacement - North 04324 04324 This project will provide for the betterment of the existing highway lighting facilities located along Routes 3, 17
More information2017 FTBA ANNUAL CONFERENCE FDOT WORK PROGRAM OVERVIEW THE RITZ CARLTON, AMELIA ISLAND August 10-13, 2017
Florida Department of TRANSPORTATION 2017 FTBA ANNUAL CONFERENCE FDOT WORK PROGRAM OVERVIEW THE RITZ CARLTON, AMELIA ISLAND August 10-13, 2017 Mike Dew, Secretary FLORIDA S CONTINUED GROWTH Florida has
More informationCurrent Roadway Projects Wednesday, September 03, 2014
Current Roadway Projects Wednesday, September 03, 2014 Restore our Roads Projects 1 US 72 East at Moores Mill Road Additional lane WB from Moores Mill to Sparkman Drive and intersection improvements at
More information